Decision Maker: Planning Committee
Decision status: Approved
Is Key decision?: No
Is subject to call in?: No
To delegate powers to the Assistant Head of Department to
approve the application, subject to the following amendment to Condition 2 of
planning permission C15/0299/34/MW to extend the lifespan of minerals
operations involving the operation of three ancillary silting lagoons and
associated works for an additional four-year period:
The permitted use of
the site as an ancillary silting lagoon shall cease by 31 December 2024;
restoration shall be completed thereafter by 30 June 2025 or upon cessation of
operations, whichever is the sooner.
Consultation response
from Natural Resources Wales attached to the decision notice, advising that
they should be contacted direct in respect of the specific environmental and
operational controls and the provision of utility within their remit.
Planning conditions
as existing in relation to the following regulatory controls;
·
Duration
of work,
·
Restriction
on permitted development rights, buildings, structures, erections, private,
floodlighting and fences,
·
Permitted
operations and Compliance with the submitted Details/Plans,
·
Hours of
Working,
·
Safeguarding
Public Rights of Way,
·
Soil
handling and husbandry,
·
Drainage,
measures to prevent the pollution of local water courses,
·
Restore
to mixed agricultural use and nature conservation,
·
After-care
measures for agricultural use and biodiversity management,
·
Dust
controls and noise limitations the same as existing.
Publication date: 12/04/2021
Date of decision: 12/04/2021
Decided at meeting: 12/04/2021 - Planning Committee