Decision status: Approved
Is Key decision?: No
Is subject to call in?: No
1.
To agree the request for change for the Responsible
Adventures project, making the following changes:
a) To
approve the removal of the eBus element from the project scope
b) To
approve the process of developing and delivering a business case
c) To
confirm that the two remaining conditions imposed during approval of the
Outline Business Case have been adequately met and that the project can proceed
to submit business cases for funding approval in accordance with the
step-by-step delivery proposal in the change request.
d) To
request further detailed information on the proposed change request to replace
the eBus element of the project with the development of a Forest Masterplan at
Betws y Coed and that this will be submitted to the next Sub-Committee in
October for consideration.
Publication date: 18/07/2025
Date of decision: 11/07/2025
Decided at meeting: 11/07/2025 - North Wales CJC Economic Well-being Sub-committee