Decision Maker: North Wales CJC Economic Well-being Sub-committee
Decision status: Approved
Is Key decision?: No
Is subject to call in?: No
DECISION
1. To agree to the change request to split the delivery of the Former North
Wales Hospital project into two phases with Denbighshire County Council acting
as the Project Sponsor for Phase 1 Essential Demolition and Remediation Works
and Ecological Mitigation Measures and Jones Bros remaining as the Project
Sponsor for Phase 2. (The remaining demolition and remediation works,
construction of commercial units and conversion of the
Main Range Listed Building into apartments and enabling the development of 300
homes).
2. To agree the release of an initial £2m in funding for Phase 1 to
Denbighshire County Council with the option of providing a further £1m
delegated to the Portfolio Director in consultation with the Chair, Vice-Chair,
Section 151 Officer and Monitoring Officer having regard in particular to the
matters in Section 4.3 of the report.
3. To note that the completion of Phase 1 will enable the project to have
full visibility of costs associated with Phase 2 and that this could result in
a request for further funding but this would be subject to a separate decision
in the future if required.
4. To authorise the Portfolio Director in consultation with the Chair, Vice
Chair, Section 151 and Monitoring Officer to agree and enter into a funding
agreement with Denbighshire County Council for Phase 1 subject to completion of
the Subsidy Control assessment.
Publication date: 03/10/2025
Date of decision: 03/10/2025
Decided at meeting: 03/10/2025 - North Wales CJC Economic Well-being Sub-committee