  • Decision details

    Application No C25/0946/44/EIA Land Along The A483 Corridor, Porthmadog

    • Find out more about this issue

    Decision status: Approved

    Is Key decision?: No

    Is subject to call in?: No

    Decision:

    DECISION: To permit

     

    1.     Time Limit  

    The development must commence within 5 years of the date of the permission.

    2.     Approved Schemes        

    The development to be carried out in accordance with the approved plans and documents.

    3.     Hours of Work:     

    Limits construction work hours and manages out-of-hours operations.

    4.     Piling

    Requires non-percussive piling methods and restricts piling hours. 

    5.     Lighting      

    Requires approval of a lighting scheme to protect bats and control light spill before operational lighting is installed. 

    6.     Enclosures 

    Requires approval of colours and finishes for fences, walls, gates and other boundary treatments.

    7.     Contamination      

    Requires investigation and remediation of any previously unidentified contamination encountered during development.    

    8.     Flood Mitigation

    Requires approval and implementation of a temporary flood mitigation scheme for construction works.  

    9.     Wern Registered Park and Garden     

    Requires a mitigation/offsetting scheme for impacts on the Wern Registered Park and Garden. 

    10. Habitat Management and Monitoring Plan (HMP)   

    Secures habitat compensation, biodiversity net benefit, habitat monitoring and INNS management over the long term.  

     

    11. Landscape and Ecological Management Plan (LEMP)     

    Secures landscape restoration, planting, habitat management, ecological monitoring and long-term maintenance. 

    12. Archaeological Investigation (WSI)    

    Requires archaeological investigation and recording before groundworks commence.  

    13. Archaeological Reporting         

    Requires submission of an archaeological report and archive following fieldwork. 

    14. Materials and Waste Management Plan

    Secures sustainable management, reuse, recovery and disposal of excavated materials and waste.

    15. Public Rights of Way      

    Requires management arrangements for public rights of way and National Cycle Route 8 during construction.

    16. Construction Method Statement        

    Prior to the commencement of any works on site, Construction Method Statements (CMS) and Risk Assessments shall be submitted to the satisfaction of the Overseeing Organisation for the Strategic Roads Network (SRN).

    17. Carriageway reinstatement design     

    Prior to the commencement of any works on site a carriageway reinstatement design and pavement specification shall be submitted to the satisfaction of the Welsh Government as Overseeing Organisation for the Strategic Roads Network.

    18. Welsh Water Assets       

    Requires surveys and protection/diversion arrangements for water and sewerage infrastructure. 

    19. Surface Water Drainage

    Prevents connection of surface water to the public sewer network.

    20. Welsh language signs    

    Requires development-related signage to be Welsh or bilingual with Welsh given priority. 

    21. Minffordd Tunnel Head House CTMP 

    Requires a package-specific Construction Traffic Management Plan for the Minffordd Tunnel Head House works. 

    22. Minffordd Tunnel Head House CEMP 

    Requests a package-specific Construction Environmental Management Plan for the Minffordd Tunnel Head House works. 

    23. Minffordd Tunnel Head House HMP   

    Requests a package-specific Habitat Management Plan for the Minffordd Tunnel Head House works.

    24. CTMPs for the Main Work Packages   

    Requires separate Construction Traffic Management Plans for the Wern CSEC, Garth CSEC, Minffordd CSEC and Glaslyn Cables work packages.   

    25. CEMPs for the Main Work Packages

    Requires separate Construction Environmental Management Plans for the Wern CSEC, Garth CSEC, Minffordd CSEC and Glaslyn Cables work packages.

    26. Community facilities restoration plan

    Bodawen Playground and Ysgol Eifionydd.

     

    Note: Amendment of Dŵr Cymru/Welsh Water conditions in line with the late representations received

     

    Publication date: 28/09/2026

    Date of decision: 28/09/2026

    Decided at meeting: 28/09/2026 - Planning Committee

    Accompanying Documents:

    • Land Along The A483 Corridor, Porthmadog pdf icon PDF 921 KB
    • Plans pdf icon PDF 5 MB
    • 2 - Glaslyn Cables Temporary Site Plans pdf icon PDF 34 MB
    • 3 - Glaslyn Cables Proposed Permanent Site Plans pdf icon PDF 43 MB
    • 4 - Glaslyn Cables Wern CSE Compound Proposed Site Plan pdf icon PDF 2 MB
    • 5 - Glaslyn Cables Wern CSE Compound Sections and Elevations pdf icon PDF 1 MB
    • 6 - Glaslyn Cables Minffordd CSE Compound Proposed Site Plan pdf icon PDF 2 MB
    • 7 - Glaslyn Cables Minffordd CSE Compound Sections and Elevations pdf icon PDF 3 MB
    • 8 - Glaslyn Cables Minffordd THH North South Elevations pdf icon PDF 108 KB