Decision Maker: Planning Committee
Decision status: Approved
Is Key decision?: No
Is subject to call in?: No
DECISION:
To approve subject to the receipt of positive observations from CADW and the
following conditions:
1.
5 years
2.
Comply with the approved plans
3.
Comply with the Construction Transport Management Plan
4.
Comply with the Initial Ecological and Habitat Enhancement Assessment
5.
Submit and agree a Heritage Management Plan
6.
Submit an Environmental Method Statement
7.
Submit and agree Site Management Plan to include a mechanism to deal
with complaints.
8.
Welsh/bilingual signs
9.
Cadw Conditions
Note –
Natural Resources Wales, Dŵr Cymru.
Publication date: 20/10/2025
Date of decision: 20/10/2025
Decided at meeting: 20/10/2025 - Planning Committee
Accompanying Documents: