Decision Maker: Planning Committee
Decision status: Approved
Is Key decision?: No
Is subject to call in?: No
DECISION:
To delegate powers to the Assistant Head of
the Environment Department to approve the application, with conditions relating
to the following:
1.
Development to
commence within 12 months of permission date.
2.
Operations shall
cease by 31/12/2028. Restoration of the site by 30/06/2029 (to correspond with
minerals permission ref. C24/1126/34/AC).
3.
In accordance with
the approved plans.
4.
Mark the boundaries of the permission area and build a surface water
collection point, including a bund to keep them on the site before commencing
the development.
5.
Restriction on
Permitted Development Rights, buildings, erection of structures, private roads,
floodlighting and fences.
6.
Nothing other than
inert waste excavation material shall be imported to the site (Waste Codes
noted in the Waste Planning Assessment). An inspection of the material should
be available upon request.
7.
No more than 50,000
tonnes of inert waste material is permitted to be carried to the site per year.
No more than 20,000 tonnes will be stored on the site at any time.
8.
Unless otherwise
agreed in writing, the details of the location and specifications of any
floodlights will be submitted for the approval of the Waste Planning Authority
before the installation work.
9.
Working Hours (to
correspond with the existing).
10. Noise restrictions (to correspond with the existing).
11. Noise Control Plan to be submitted within 3 months of obtaining
permission.
12. All vehicles, equipment and plant operated on the site will be
maintained in such a way so as to restrict the maximum levels of noise
emissions to those noted in the manufacturers' specification. No equipment,
plant or machinery will be operated on the site unless they have been installed
with noise prevention screens, casework enclosures and silencers.
13. No operations on the site shall be undertaken in such a manner as to
cause the raising of fugitive dust, and a water spray or other dust suppression
system shall be maintained on site at all times together with an adequate
supply of water. Stockpiles of materials and areas traversed by wheeled
vehicles or within which the handling or movement of material is undertaken
shall be watered or otherwise treated at such times and intervals as may be
necessary to prevent the raising of such dust.
14. The surface of the site access to the public highway shall be kept free
from mud and other debris and maintained at all times in a condition acceptable
to the Waste Planning Authority such as to ensure that mud is prevented from
being deposited onto the public highway.
15. Sheeting of lorries leaving and arriving at site with stone or material
less than 500mm.
16. Restriction of vehicular access to existing access arrangements.
17. A copy of this determination and the approved plans showing the method
and direction of working and restoration shall be displayed in the operator's
site office at all times during the life of the site.
18. The best practicable means and/or ‘white noise’ reversing alarms shall
be fitted to mobile plant and vehicles used on site.
19. Oil, fuels and chemicals stored on impervious base and bunds.
20. The operator shall monitor the site for the presence of non-native
invasive plant species for each phase of the development, focusing particularly
on Japanese knotweed, and implement control measures as appropriate.
21. Restoration and aftercare (to match existing).
Publication date: 15/06/2026
Date of decision: 15/06/2026
Decided at meeting: 15/06/2026 - Planning Committee
Accompanying Documents: