    CHANGE CONTROL : BODELWYDDAN KEY STRATEGIC SITE PROJECT

    • Issue Details
    • Issue History
    • Related Decisions
    • Related Meetings
     

     

    Meeting: 30/09/2022 - North Wales Economic Ambition Board (Item 10)

    10 CHANGE CONTROL : BODELWYDDAN KEY STRATEGIC SITE PROJECT pdf icon PDF 515 KB

    Alwen Williams, Portfolio Director and David Mathews, Land and Property Programme Manager to present a report to recommend the withdraw of the Bodelwyddan Key Strategic Site project from the North Wales Growth Deal.

    Decision:

    To agree to formally withdraw the Bodelwyddan Key Strategic Site project from the North Wales Growth Deal and notify Welsh Government and UK Government of the decision.

     

    To agree that the Board note that funding provisionally allocated to the project is retained with the North Wales Growth Deal and that the decision on a replacement project or projects is a matter for the Economic Ambition Board to determine.

     

    To request that the Portfolio Management Office bring forward a paper to a future Board meeting setting out the process for selecting a replacement project for the Board to consider.

     

    Minutes:

    The report was presented by Hedd Vaughan-Evans (Operations Manager) and David Mathews (Land and Property Programme Manager).

     

    DECISION

     

    To agree to formally withdraw the Bodelwyddan Key Strategic Site project from the North Wales Growth Deal and notify the Welsh Government and UK Government of the decision.
     

    It was agreed that the Board noted that funding provisionally allocated to the project was retained with the North Wales Growth Deal and that the decision on a replacement project or projects was a matter for the Ambition Board to determine.

     

    The Portfolio Management Office was requested to bring forward a paper to a future meeting setting out the process for selecting a replacement project for the Board to consider.

     

    REASONS FOR THE DECISION

     

    The project Outline Planning Consent as originally scoped of 1,700 plus residential units, 26 ha of employment land, local centre, school, medical centre, hotel, extra care home, recreation and leisure uses lapsed in March 2021. Both private sector developers had withdrawn from the project before the permission lapsed.

     

    It was explained that the project was one of six within the Land and Property programme and was estimated to deliver 26 ha of employment land, 1,715 new homes, primary school, local centre, recreation and leisure facilities, 576 jobs, £20m pa GVA and circa £185m capital investment.

     

    Consequently, the Board was asked to remove the project from the North Wales Growth Deal.

     

    DISCUSSION

     

    The report was submitted noting that it was a request to formally withdraw the Bodelwyddan Key Strategic Site project from the North Wales Growth Deal. It was stated that this was a major scheme and it was highlighted that a number of changes had been undertaken following a Review of Denbighshire's Local Development Plan for 2023.

     

    It was explained that household information had been updated for the 2023-33 period and the Employment Land Survey 2021 for the same period estimated that demand for new housing and employment land for the Bodelwyddan project had reduced to 400 homes from 1715 back in 2016. It was also added that planning permission had lapsed back in March 2021 and the developer had withdrawn. It was stated that the timeline to adopt the Local Delivery Plan, that had also been reviewed, had been extended and it was estimated that the new Plan would not be adopted until mid-2025. As a result, it was explained that the work would not commence until mid-2028 at the earliest.

     

    It was explained that a discussion had been held by the Programme Board and that they recommended withdrawing it and earmarking the funding within the Growth Deal in order for the Portfolio Management Office to submit a paper to a future meeting outlining the process for selecting a replacement project for the Board to consider.

     

    Observations arising from the discussion

    ¾     It was stated that it must be accepted that some schemes would not proceed and that the horizon scanning process needed to commence as soon as possible.