8 PORTFOLIO MANAGEMENT OFFICE RESOURCING
PDF 367 KB
Alwen
Williams (Portfolio Director) and Hedd Vaughan-Evans (Head of Operations) to
present the report.
Decision:
That the Board approve the increase in the amount of Growth Deal grant
available to support the Portfolio Management Office from 1.5% to 2% reducing
the overall amount of funding to support new projects through the project
replacement process by £1.2 million and to consider a further increase should
there be any unallocated funding at the end of the process to select
replacement projects for the Growth Deal.
Minutes:
The report was submitted by Alwen Williams
(Portfolio Director).
RESOLVED
That the Board approve the increase in the amount of Growth Deal grant
available to support the Portfolio Management Office from 1.5% to 2% reducing
the overall amount of funding to support new projects through the project
replacement process by £1.2 million and to consider a further increase should
there be any unallocated funding at the end of the process to select
replacement projects for the Growth Deal.
REASONS FOR THE
DECISION
To set out options for resourcing the Portfolio Management Office over
the next four years to oversee the key delivery period of the North Wales
Growth Deal.
DISCUSSION
The Chair noted that we had
an incredibly capable and strong team in North Wales, which was an asset to us,
and that it was important to look at every opportunity to keep that team
together.
It was asked whether
increasing the amount of grant available to support the Portfolio Management
Office from 1.5% to 2% was sufficient.
In response, it was noted
that a 0.5% increase was thought to be realistic and proportional, and
compatible with other growth deals, and that it was important to retain as much
capital as possible for delivering the projects and allowing us to meet the
objectives of the Growth Deal and deliver jobs.
It was noted that paragraphs 4.12 and 4.13 of the
report stated that the proposal was to use 50% of the additional £1.2m to
enable the extension of existing fixed term contracts within the team to March
2025, and that no further extension could be provided until alternative sources
of funding were secured. In light of
this, it was asked what was happening to the other £600,000.
In response, it was
explained:-
·
£600,000 was planned to be used next year to enable that 12-month
extension, which would mitigate the risk of staff leaving in the next year and
buy us time to see what the outcome of the other funding package we were
applying for through the Common Prosperity Fund (SPF) would be.
·
Therefore, the £600,000 was theoretically allocated for years 3 and 4,
but if no additional funding was secured, that money might have to be used in a
different way, and it would not be possible to extend everyone's contract with
that amount of money.
·
If the application to the Common Prosperity Fund, or any other external
source, was successful, it would be necessary to re-profile how we would use
the £1.2m, so instead of using the £600,000 next year, we would use it in years
3 and 4.
It was suggested that the
wording in the report contradicted itself as it said that no further extension
can be provided until other sources of funding were secured.
In response, it was
confirmed, for clarity, that no further extensions could be provided to all
staff on that basis, so no further extensions could be offered to all if the
£1.2m was the only funding available.
It was noted that ... view the full minutes text for item 8