12 CAPITAL PROGRAMME 2023/24 - END OF AUGUST REVIEW (31 AUGUST 2023 POSITION)
PDF 992 KB
Cyflwynwyd gan: Cllr. Ioan Thomas
Additional documents:
Decision:
1.
To
accept the report on the end of August review (31 August 2023 position) of the
capital programme.
2.
To
approve the revised financing as shown in part 3.2.3 of the report, namely:
-
Use
of various sources, worth a total of £17,421,000, to fund actual slippages from
2022/23
- A decrease of £1,836,000 in the use
of borrowing
- An increase of £61,991,000 in the
use of grants and contributions
- A decrease of £9,000 in the use of
capital receipts
- An increase of £991,000 in the use
of revenue contributions
-
An
increase of £194,000 in the use of renewal and other reserves
Minutes:
The report was submitted by Cllr Ioan Thomas.
DECISION
1. To accept the report on the end of
August review (31 August 2023 position) of the capital programme.
2. To approve the revised financing as
shown in part 3.2.3 of the report, namely:
- Use of various sources, worth
a total of £17,421,000, to fund actual slippages from 2022/23
- A decrease of £1,836,000 in the use
of borrowing
-
An
increase of £61,991,000 in the use of grants and contributions
-
A
decrease of £9,000 in the use of capital receipts
-
An
increase of £991,000 in the use of revenue contributions
- An increase of £194,000 in the
use of renewal and other reserves
DISCUSSION
It was explained that the main aim of the report was to submit the revised
capital programme (31 August 2023 position) and it was noted that the report
included an analysis per Department of the capital programme, which was £178.6
million for the 3 financial years between 2023/24 and 2025/26.
It was concluded
that the Council had firm plans in place to invest approximately £107.3 million
in 2023/24 on capital schemes (with £42.8 million (40%) funded by specific
grants).
It was reported that
the impact of recent financial challenges continued on
the capital programme, with £311.5m (11%) of the budget spent up to the end of
August this year. This was compared to 11% of the budget spent within the same
period last year and 16% two years ago.
It was confirmed
that a further £312.5m of proposed expenditure had been re-profiled from
2023/24 to 2024/25 and 2025/26. It was detailed that the main schemes included:
·
£5.7 million – Schools
Schemes (Sustainable Learning Communities and Others)
·
£2.8 million – Carbon
Management and Solar Panels Schemes
·
£1.5m – Penygroes
Health and Care Hub
·
£1.4m – Residential
Organisations, day care and others in the Adults field
·
£0.9m – Flood Prevention
Schemes.
It was noted that
the Council had managed to attract a number of grants
since the original budget, which included:
·
£36.9m
– Shared Prosperity Fund Grant from the UK Government, to be distributed across
the counties of North Wales.
·
£16.7m
– Levelling Up Fund Grant from the UK Government.
·
£3.0m – Grants from the
Local Transport Fund (LTF) and Active Travel Fund (ATF) from the Welsh
Government.
·
£1.3m – Sustainable
Learning Communities Grant – Schools Community Use 2023-2025.
It was explained that this report had recently been submitted to the
Governance and Audit Committee where members had noted that construction costs
had recently increased significantly and, therefore, there was a possibility
that those projects were now more costly. Officers had reported to the
Committee that there had been an intentional delay to projects while prices and
inflation were high and that this had been reflected in the slippages.
Pride was expressed
in the Council's ability to attract grants to improve resources and services
while investing for the future.
Awdur: Ffion Madog Evans: Assistant Head of Finance