EGNI - OUTLINE BUSINESS CASE
Elgan
Roberts (Low Carbon Energy Programme Manager) to present the report (which has
been circulated to members separately).
Decision:
1. That
the Board approve the Outline Business Case for the Egni project subject to
Bango University addressing the matters set out in the report, as described in
Section 7, and recommend to the Economic Ambition Board that a Full Business
Case is prepared for the Board to consider following the completion of the
procurement process and the consenting processes.
2. That
the Board delegate final approval of the procurement strategy and the
procurement specifications and social value criteria to be included by Bangor
University in their procurement to the Portfolio Director in consultation with
the Chair and Vice Chair.
3. That
the Board authorise the Portfolio Director in consultation with the Host
Authority Section 151 Officer and Monitoring Officer to agree draft terms in
accordance with this report as a basis for the final funding arrangements for
the project which will form the basis of funding to be agreed by the Board at
the Full Business Case stage.
Minutes:
The report was presented by Elgan Roberts (Energy
Programme Manager) and Hedd Vaughan-Evans (Head of Operations).
RESOLVED
1. That
the Board approves the Outline Business Case for the Egni
project subject to Bangor University addressing the matters set out in the
report, as described in Section 7, and recommends to the Economic Ambition
Board that a Full Business Case is prepared for the Board to consider following
completion of the procurement and consenting processes.
2. That
the Board delegates final approval of the procurement strategy and the
procurement specification and social value criteria to be included by Bangor
University in their procurement process, to the Portfolio Director in
consultation with the Chair and Vice Chair.
3. That
the Board authorises the Portfolio Director in consultation with the Host
Authority's Section 151 Officer and Monitoring Officer to agree draft terms in
accordance with this report as a basis for the final funding arrangements for
the project, which will determine the funding to be agreed by the Board at the
Full Business Case stage.
REASONS FOR THE
DECISION
To seek the Portfolio Board’s approval
of the Outline Business Case for the Egni project.
DISCUSSION
The item was discussed.