5 NORTH WALES GROWTH DEAL - QUARTER 1 PERFORMANCE AND RISK REPORT PDF 246 KB
Hedd
Vaughan-Evans (Head of Operations) to present the report.
Additional documents:
Decision:
1. To
consider and note the Quarter 1 Performance Report and updated Portfolio Risk
Register.
2. To
approve the Quarter 1 Performance Report to the Welsh Government and UK
Government, as well as the local authority scrutiny committees.
Minutes:
The report was presented by the Head of Operations
with the support of Ambition North Wales officers.
RESOLVED
1. To
consider and note the Quarter 1 Performance Report and the updated Portfolio
Risk Register.
2.
To approve the Quarter 1
Performance Report to the Welsh Government and UK Government, as well as the
local authority scrutiny committees.
REASONS FOR THE
DECISION
Quarterly
reporting on progress against the North Wales Growth Deal is one of the
requirements of the Final Growth Deal Agreement. Following consideration by the
Ambition Board, the reports will be shared with the Welsh Government, UK Government and the local authority scrutiny committees.
DISCUSSION
Members were guided
through the Ambition North Wales updates and the following programmes were
specifically highlighted:
The Digital
Programme
Pride was expressed
that an Outline Business Case for '4G+' Linked Sites and Corridors had been
approved by the Board in March. It was explained that the development of a Full
Business Case including preparations for market engagement has already begun.
It was noted
that the Gateway 2 Review on the Outline Business Case of the Connected
Campuses Advanced Wireless scheme had been completed in May. It was confirmed
that the project had received an Amber rating, and it was stressed that work
was under-way to address the recommendations prior to the presentation of the
Outline Business Case to the Board in September.
Reference was
made to a number of regional projects under way to
support SMEs to research new technologies and improve broadband connectivity in
local communities. It was noted that these projects were funded by the Shared
Prosperity Fund.
Low Carbon
Energy Programme
It was stated
that the Bangor University-led 'Egni' project was
making good progress. It was noted that RIBA Phase 3 was ready to be signed off
and it was hoped that a Full Business Case would be presented to the Board in
the spring. Similarly, it was confirmed that positive progress has been made to
overcome key issues relating to the Deeside Anaerobic Digestion Project funding
agreement, before submitting the Full Business case to the Board for
consideration.
It was noted that there was positive
co-operation with the Welsh Government to realise the Holyhead Hydrogen Hub
project. It was explained that the project hoped to strengthen the offtake
purchase position for Hydrogen before moving on to the next step.
It was confirmed that the Fund's Advisor
tender documents attached to the Smart Local Energy project was currently being
finalised, together with the timetable for the launch of the tender and review
of submissions - these were currently being planned.
Land and
Property Programme
Reference was
made to several programme projects including Warren Hall, Western Gateway,
Former North Wales Hospital, Parc Bryn Cegin, Wrexham
Gateway and Holyhead Port.
It was explained that Stage Fifty Ltd, developers of the Kinmel Studios project, had been placed in administration in early April 2024 by their main funder. It was stressed that the proposed discussions had taken place between Ambition North Wales ... view the full minutes text for item 5