OUTLINE BUSINESS CASE FOR PARC BRYN CEGIN, BANGOR
David Mathews
(Land and Property Programme Manager) and Margaret Peters (Land and Property
Project Manager) to present the report.
Decision:
1.
To approve the Outline Business Case for the Parc
Bryn Cegin project, subject to Welsh and UK
Governments' approval of the assurance process, and Ambition North Wales
addressing the matters set out in the report, as described in Section 7, and
recommend to the NWEAB that a Full Business Case is prepared for the Board to
consider.
2.
To accept that the approval of the Outline Business
Case will act as approval for the project change request to reduce the project
scope for Phase 1 from 3,000 square metres to 1,856 square metres of proposed
new employment units.
3.
To agree the revised process which will see a Full
Business Case presented upon the completion of the Joint Venture Agreement and
confirmation of Welsh Government funding prior to commencing procurement.
4.
To agree the principles of the Joint Venture
proposal as set out and delegate to the Portfolio Director in consultation with
the Chair, Vice-Chair, Section 151 Officer and
Monitoring Officer to approve and enter into the agreement.
5.
To note the forecast return as part of the Joint
Venture Agreement and approve in principle (subject to confirmation at Full
Business Case) that the income received is allocated to a reserve to be used to
fund the Portfolio Management Office in future years.
6.
To hold further discussions on Phase 2 of the
Project following the completion of Phase 1.
Minutes:
The report was
submitted by the Land and Property Programme Manager and the Land and Property
Project Manager.
DECISION
1.
To
approve the Outline Business Case for the Parc Bryn Cegin
project, subject to Welsh and UK Governments' approval of the assurance
process, and Ambition North Wales addressing the matters set out in the report,
as described in Section 7, and recommend to the NWEAB that a Full Business Case
is prepared for the Board to consider.
2.
To
accept that the approval of the Outline Business Case will act as approval for
the project change request to reduce the project scope for Phase 1 from 3,000
square metres to 1,856 square metres of proposed new employment units.
3.
To
agree the revised process which will see a Full Business Case presented upon
the completion of the Joint Venture Agreement and confirmation of Welsh
Government funding prior to commencing procurement.
4.
To
agree the principles of the Joint Venture proposal as set out and delegate to
the Portfolio Director in consultation with the Chair, Vice-Chair, Section 151 Officer and Monitoring Officer to approve and enter into the
agreement.
5.
To
note the forecast return as part of the Joint Venture Agreement and approve in
principle (subject to confirmation at Full Business Case) that the income
received is allocated to a reserve to be used to fund the Portfolio Management
Office in future years.
6.
To
hold further discussions on Phase 2 of the Project following the completion of
Phase 1.
REASONS FOR THE DECISION
To seek the Portfolio Board’s approval of the Outline
Business Case for the Parc Bryn Cegin project, and
the subsequent project change request.
The Board should note that no grant funding agreement
would be required for this Project, as the Joint Venture Agreement would act as
a legal contract between Ambition North Wales and Welsh Government. No approval
was requested at this stage, but this would be when the Full Business Case
would be presented to the Board in due course.
DISCUSSION
The report was
discussed.