PROJECT PRINCE – OUTLINE BUSINESS CASE
Elliw
Hughes to present the report.
Decision:
DECISION
1. To approve the Outline Business Case (OBC) for Project Prince subject to
Welsh Government and UK Government approval of the assurance process
undertaken, and Knauf Insulation Limited addressing the matters set out in the
report, as described in Section 7, and request that a Full Business Case is
prepared for the Sub-committee to consider.
2. To authorise the Portfolio Director in consultation with the Chair, Vice
Chair, Section 151 Officer and Monitoring Officer to agree draft terms in
accordance with this report as a basis for the final funding arrangements for
the project to be entered into subject to Full Business Case approval.
3. That the approval from the Sub-Committee is valid for a period of twelve
months and should the project not proceed to an approved FBC during this time,
it will be required to return and re-present the business case to the
Sub-committee for approval.
4. To note the intention to split the funding between the Growth Deal and
Investment Zone (once approved) and that this position will be confirmed at
Full Business Case stage.
Minutes:
The report was
presented by Elliw Hughes, Growth Deal Programme Manager.
RESOLVED
1.
To approve the Outline Business Case (OBC) for
Project Prince subject to Welsh Government and UK Government approval of the
assurance process undertaken, and Knauf Insulation Limited addressing the
matters set out in the report, as described in Section 7, and request that a
Full Business Case is prepared for the Sub-committee to consider.
2.
To authorise the Portfolio Director in consultation
with the Chair, Vice-chair, Section 151 Officer and Monitoring Officer to agree
draft terms in accordance with this report as a basis for the final funding
arrangements for the project to be entered into subject to Full Business Case
approval.
3.
That the approval from the Sub-committee is valid
for a period of twelve months and should the project not proceed to an approved
FBC during this time, it will be required to return and re-present the business
case to the Sub-committee for approval.
4.
To note the intention to split the funding between the Growth Deal and
Investment Zone (once approved) and that this position will be confirmed at
Full Business Case stage.
REASONS FOR THE DECISION
1.
To seek the Sub-committee’s approval of the
Outline Business Case for Project Prince by Knauf Insulation Limited.
2.
A
decision to approve the Outline Business Case by the Economic Well-being
Sub-committee would enable Knauf to progress to the next stage of their
internal approvals.
DISCUSSION
The Report was discussed.