FORMER NORTH WALES HOSPITAL – CHANGE REQUEST
David
Mathews to present the report.
Decision:
DECISION
1. To agree to the change request to split the delivery of the Former North
Wales Hospital project into two phases with Denbighshire County Council acting
as the Project Sponsor for Phase 1 Essential Demolition and Remediation Works
and Ecological Mitigation Measures and Jones Bros remaining as the Project
Sponsor for Phase 2. (The remaining demolition and remediation works,
construction of commercial units and conversion of the
Main Range Listed Building into apartments and enabling the development of 300
homes).
2. To agree the release of an initial £2m in funding for Phase 1 to
Denbighshire County Council with the option of providing a further £1m
delegated to the Portfolio Director in consultation with the Chair, Vice-Chair,
Section 151 Officer and Monitoring Officer having regard in particular to the
matters in Section 4.3 of the report.
3. To note that the completion of Phase 1 will enable the project to have
full visibility of costs associated with Phase 2 and that this could result in
a request for further funding but this would be subject to a separate decision
in the future if required.
4. To authorise the Portfolio Director in consultation with the Chair, Vice
Chair, Section 151 and Monitoring Officer to agree and enter into a funding
agreement with Denbighshire County Council for Phase 1 subject to completion of
the Subsidy Control assessment.
Minutes:
The report was
presented by David Matthews, Land and Property Programme Manager.
RESOLVED
1.
To
agree to the change request to split the delivery of the Former North
Wales Hospital project into
two phases with Denbighshire County Council acting as the Project Sponsor for Phase 1 Essential
Demolition and Remediation Works and Ecological Mitigation Measures and Jones Bros remaining as the Project Sponsor for Phase 2. (The remaining demolition and remediation works, construction of commercial units and conversion of the Main Range Listed Building into apartments and enabling the development of 300 homes).
2.
To
agree the release of an initial £2m in funding for
Phase 1 to Denbighshire County Council with the option of providing a further £1m delegated to the Portfolio Director in consultation
with the Chair, Vice-Chair, Section 151 Officer and Monitoring Officer having regard in particular
to the matters in Section 4.3 of the report.
3.
To
note that the completion of Phase 1 will enable the project to have full visibility
of costs associated with Phase 2 and that this could
result in a request for further
funding but this would be subject
to a separate decision in the future if
required.
4.
To
authorise the Portfolio Director in consultation
with the Chair, Vice Chair, Section 151 and Monitoring Officer to agree and enter into a funding agreement with Denbighshire County Council for Phase
1 subject to completion of
the Subsidy Control assessment.
REASONS FOR THE DECISION
1.
There was a need to
progress Phase 1 works imminently in order to provide
cost certainty on Phase 2 and to address urgent health and safety matters on
site as a result of the deteriorating state of the buildings that needed to be
demolished anyway regardless of health and safety matters.
2.
By bringing the demolition
of these buildings forward, safe access could be achieved to the Main Range
Listed Building (MRLB) allowing:
i. them to be inspected to
obtain up-to-date assessments of conversion costs, viability of the overall
project etc.
ii. Any urgent works can be carried out to
the MRLB to limit any further deterioration in its structural integrity
iii.
momentum/confidence to be built in the project in terms of the other milestones
that needed to be achieved.
3.
All parties have agreed
that the clearance of the buildings to be demolished should be the priority.
Whilst these works were ongoing, negotiations regarding the content of the S106
relating to giving planning permission would continue.
DISCUSSION
The Report was discussed.