• Calendar
  • Committees
  • Community Councils
  • Consultations
  • Decisions
  • Election results
  • ePetitions
  • Forthcoming Decisions
  • Forward Plans
  • Library
  • Meetings
  • Outside bodies
  • Search documents
  • Subscribe to updates
  • Your councillors
  • Your MPs
  • Your MEPs
  • What's new
  • Issue - meetings

    FLINTSHIRE AND WREXHAM INVESTMENT ZONE

    • Issue Details
    • Issue History
    • Related Decisions
    • Related Meetings
     

     

    Meeting: 07/11/2025 - North Wales Corporate Joint Committee (Item 5)

    5 FLINTSHIRE AND WREXHAM INVESTMENT ZONE pdf icon PDF 189 KB

    The Chief Executive, the Monitoring Officer, and a representative from AMION Consulting to present the report.

     

    Appendix 3 is an Exempt Document as the report relates to draft Memorandum of Understanding for the Investment Zone which has been designated as confidential information by a Government Department for the purposes of Section 100A(2) of the Local Government Act 1972. As a consequence, it is a requirement that Appendix 3 is excluded from publication as this would disclose the confidential information.  

      

     

    Additional documents:

    • Appendix 1 - Inter Authority Agreement (draft), item 5 pdf icon PDF 328 KB
    • Appendix 2 - IZ Year 1 projects, item 5 pdf icon PDF 216 KB

    Decision:

    The Update Report was accepted and the work undertaken by Flintshire County Council and Wrexham County Borough Council and the Investment Zone team, Welsh Government and UK Government was noted.

     

    A draft Inter-Authority Agreement (IAA) was approved between the North Wales Corporate Joint Committee (CJC), Flintshire County Council and Wrexham County Borough Council, delegating the right to agree and finalise the final version to the Chief Executive in consultation with the Monitoring Officer, Section 151 Officer, the Vice-chair and Leader of Denbighshire County Council, as the appointed representatives of the Flintshire and Wrexham Investment Zone Advisory Board.

     

    A Year 1 and 2 Schedule of Projects, activities and milestones drafted to support the Annual Delivery Plan was approved.

     

    A draft Memorandum of Understanding was approved, delegating the right to agree and finalise the final version to the Chief Executive in consultation with the Monitoring Officer, Section 151 Officer, the Vice-chair and Leader of Denbighshire County Council, as the appointed representatives of the Flintshire and Wrexham Investment Zone Advisory Board.

     

    Minutes:

    The report was presented by Iwan Evans, Monitoring Officer and Iain Taylor from AMION Consulting.

     

    RESOLVED:

     

    The Update Report was accepted and the work undertaken by Flintshire County Council and Wrexham County Borough Council and the Investment Zone team, Welsh Government and UK Government was noted.

     

    A draft Inter-Authority Agreement (IAA) was approved between the North Wales Corporate Joint Committee (CJC), Flintshire County Council and Wrexham County Borough Council, delegating the right to agree and finalise the final version to the Chief Executive in consultation with the Monitoring Officer, Section 151 Officer, the Vice-chair and Leader of Denbighshire County Council, as the appointed representatives of the Flintshire and Wrexham Investment Zone Advisory Board.

     

    A Year 1 and 2 Schedule of Projects, activities and milestones drafted to support the Annual Delivery Plan was approved.

               

    A draft Memorandum of Understanding was approved, delegating the right to agree and finalise the final version to the Chief Executive in consultation with the Monitoring Officer, Section 151 Officer, the Vice-chair and Leader of Denbighshire County Council, as the appointed representatives of the Flintshire and Wrexham Investment Zone Advisory Board.

     

    DISCUSSION

     

    The Members were thanked for their time and consideration of the report.

     

    It was reported that the development of the programme was now at a key point and had reached the approval phase with the Welsh Government and the UK Government. The Five Gateways Process had expired and the agreement for the Gateways had been accepted. It was explained that the CJC's approval for the Memorandum of Understanding and the Inter-Authority Agreement (IAA) between the CJC, Flintshire County Council and Wrexham County Borough Council was required. It was elaborated that these would govern the transfer of revenue funding and key activities in the programme.

     

    It was explained that annual delivery plans would be agreed every year to support the way the Investment Zones were structured and delivered. The draft Annual Delivery Plan would be submitted to the meeting of the Investment Zone Work Group, where the leaders of Flintshire County Council and Wrexham County Borough Council would meet and review the Annual Delivery Plan. It was noted that the intention was to hold a meeting of the Investment Zone Work Group on 28 November, to discuss the programme's initial activities. Further details were given of another meeting to be held to discuss the second year Delivery Plan.

     

    An overview was given to Members of the Annual Delivery Plan, drawing particular attention to some of the key points of the Investment Zone Programme included in Appendix 2. It was noted that these had been split into business support, skills, innovation, infrastructure and tax sites. The members were informed that the tax sites had been published on Legislation.gov, and they would come into force legally on 21 November. 

     

    The members were informed that should the CJC approve the Memorandum of Joint Understanding and the IAA, that the Government would act to issue signed versions of the document within the week. 

     

    Members’ attention was drawn to the Delivery  ...  view the full minutes text for item 5