6 TOWN CENTRE REGENERATION
PDF 313 KB
To receive
an update on the work and consider its impact.
Additional documents:
Decision:
DECISION
• To accept the report and note the
observations.
• To ask the Cabinet Member for Economy
and Community to discuss car parking fees and the impact of changing
enforcement hours in car parks on the local economy with the relevant Cabinet
Members and departments.
Minutes:
The Cabinet Member for
Economy and Community presented the report noting that the challenges facing
town centres were evident, including changes in shopping habits, the growth of
on-line shopping and cost of living pressures. It was explained that the challenge
was to re-purpose town centres and make them attractive places to live, work
and spend time. It was noted that discussions had begun with the new Welsh
Government regarding the field.
It was elaborated that the
report buildt on information previously submitted to the Committee and focused
on the activities of the Regeneration Programme Service, including town centre
regeneration, the development and implementation of regeneration projects and
the response to empty properties. Reference was made to the framework for the
towns of Gwynedd and the Place Making Schemes developed for Bangor, Caernarfon,
Porthmadog, Pwllheli, Bala and Dolgellau. It was noted that these schemes had
been prepared since the report was submitted to the Committee in 2023.
The report included
information on the development and implementation of regeneration projects and
the main grant programmes. It was noted that grants worth £31.8 million had
been secured between 2023-26 for the development and implementation of town centre
regeneration projects across the county. Reference was made to the projects to
be implemented through the Pride in Place Impact Fund and the Local Growth
Fund, as well as the work on empty properties in town centres.
It was elaborated that work
was being carried out to develop performance measures and collect data to be
able to measure the impact of the regeneration work on town centres. Reference
was made to the Council's new Economic Strategy and the need to assess the
impact of projects as well as monitor the number and condition of vacant
properties. It was explained that the final part of the report summarised the
main conclusions and lessons learnt, along with further issues to consider over
the following months.
During the discussion, the
following observations were made:
Clarification was sought
regarding the definition of vacant properties. Reference was made to examples
in Pwllheli where a shop continued to operate on the ground floor of a building
but the top floor was empty, noting that the situation could lead to significant
Council Tax Premium costs and put additional pressure on the viability of the
ground floor business.
In response, it was
clarified that there was no single simple definition of empty properties across
the Council, as a number of services and departments related to empty
properties and operated under different legislations and regulations. It was
noted that the relevant definitions and periods may therefore vary between
services. In relation to town centre regeneration work, it was explained that
the Service tended to focus on properties that had been empty for more than a
year, prioritising substantial buildings in central locations where their
condition was deteriorating and impacting the area.
It was noted that there was a marked difference between the performance of different streets and town centres, with some thriving while others found ... view the full minutes text for item 6