Venue: Hybrid Meeting - Siambr Hywel Dda, Council Offices, Caernarfon, Gwynedd, LL55 1SH and on Zoom
Contact: Annes Siôn 01286 679490
No. | Item |
---|---|
APOLOGIES Additional documents: Minutes: An apology was received from Councillors Dyfrig
Siencyn and Beca Brown. Cabinet Members and Officers were welcomed to the
meeting. |
|
DECLARATION OF PERSONAL INTEREST Additional documents: Minutes: A declaration of interest was received from Cllr Nia Jeffreys in item 7,
however it was not a prejudicial interest and she did not need to withdraw from
the meeting. |
|
URGENT ITEMS Additional documents: Minutes: There were no urgent items. |
|
MATTERS ARISING FROM OVERVIEW AND SCRUTINY Additional documents: Minutes: There were no matters arising from overview and scrutiny. |
|
MINUTES OF THE MEETING HELD ON 27 SEPTEMBER 2022 PDF 170 KB Additional documents: Minutes: It was noted that the minutes had been noted in
the following agenda, therefore, they would be accepted at the next meeting. |
|
ANNUAL COMPLAINTS AND SERVICE IMPROVEMENT REPORT 2021-22 PDF 522 KB Cyflwynwyd gan: Cllr. Menna Jones Additional documents:
Decision: To accept and note the information in the
report. Minutes: The report was submitted by Cllr Menna Jones. DECISION To accept and note the information in the report. DISCUSSION The report was submitted, noting that it was an annual report on
complaints and service improvement. It was explained that arrangements had been
in place in order to report on the work of the service every six months, but
that circumstances over the past years had varied the timing. It was noted that
arrangements were now in place for the service to return to submitting reports
every six months. It was expressed that the Service Improvement policy had been updated
back in April 2021, and that it complied with the plans of the Welsh Government
and the Ombudsman's guidelines. It was highlighted when the policy was updated
that the service had moved to the Learning and Development Service within the
Corporate Support Department. It was explained that the report provided an
overview of the team's work and it was highlighted that the number of
complaints had increased substantially this year compared to the last year, but
that this was to be seen across Local Government and was not unique to Gwynedd.
Attention was drawn to the fact that the number of complaints that reached the
Ombudsman had also increased. It was noted that the figures received from the Ombudsman had been
highlighted as realistic and that the Gwynedd complaints procedure worked and
that lessons were learnt from every complaint. It was noted that the Service
continued to work with the departments in order to change mindsets. It was
explained that the majority of departments were prepared and happy to accept
complaints, but that changing culture across the Council would take time. It was highlighted that training in the
Customer Care field had been held with the Ombudsman and that training on
responding to correspondence was on the way.
Attention was drawn to the Successes Wall and gratitude were expressed
for the comments as they often raised the morale of staff. Observations arising from the discussion ¾ It was highlighted
that the number of complaints to the Adults department had increased
substantially but that the report noted that the department dealt with them
within seven days and the staff were thanked for responding within the
timetable. ¾ Gratitude was
expressed for the report and pride was expressed as the Council was using
complaints as a way to improve service. ¾ It was noted that a table within the report reflected the fact that a number of complaints were about the lack of response and action and that some departments had received over 10 complaints within this category. It was noted that work was being done with these departments and it was highlighted in the Housing and Property Department that 10 complaints had been presented in 2021/22 for the lack of response and that the first six months of this year highlighted one complaint for the same reasons. It was highlighted that the work being done in the background was coming to fruition ... view the full minutes text for item 6. Awdur: Geraint Owen |
|
DISCRETIONARY COST OF LIVING SUPPORT SCHEME PDF 469 KB Cyflwynwyd gan: Cllr. Ioan Thomas Additional documents:
Decision: To adopt the Discretionary Cost of Living
Support Scheme. Minutes: The
report was submitted by Cllr Ioan Thomas.
DECISION The Discretionary Cost of
Living Support Scheme was adopted. DISCUSSION The
report was submitted, noting that the purpose of this report was to receive
approval to the Council's Discretionary Scheme to assist with the costs of
living. It was explained that this was a scheme that had been developed jointly
between the Taxation Service and Supporting Families Team. It
was expressed that the Discretionary Scheme was a follow-up of the Core Plan,
where the Council had already distributed £150 each to approximately 40,000
households in Gwynedd. It was noted that the households needed to live in
properties in Council Tax Bands A to D in order to receive the support through
the Council Tax Reduction Scheme. It was emphasised that this scheme had been
successful and that the Council was the quickest Authority in Wales to achieve
this work. It was explained that the Welsh Government had
earmarked £25m to provide discretionary support for other purposes relating to
the costs of living, and it was explained that this scheme highlighted the
Council's proposals on how to use Cyngor Gwynedd's proportion of the money.
First of all, it was noted that a £150 payment to households that were not
eligible to receive a payment under the original scheme would receive a Council
Tax exception. It was highlighted that property that received a Council Tax
exception on 15 February was not eligible to receive a payment, and in
addition, the proposal would give a payment to households where the household
income was restricted since only one person lived there. It was emphasised that the second part of the
proposed support provided a financial contribution towards the Supporting
People Hubs Network. It is believed that giving the network a contribution is a
very effective way of securing support to households that need support with
their costs of living. It was expressed that the cabinet member believed that
this scheme was an effective and efficient way of making use of this additional
grant, targeting the money towards the neediest households in the county. It
was noted that this money was to be welcomed, despite the fact that it was far
from sufficient to meet the needs of the most vulnerable families in the
county. Observations arising from the discussion ¾
Gratitude
was expressed for the report and for the work done within the field. An enquiry
was made about plans to support people in specific catchment areas but, e.g. in
Bangor, Maesgeirchen was noted but not the rest of
Bangor. It was asked whether work would be done outside these areas. It was
expressed that hubs would be established in deprived locations but that
satellite locations would be opened outside the main hubs. It was explained
that a support network and events would be seen outside the main hubs also. ¾ In terms of the support to Food Schemes, a request was made for more details. It was explained that many types of support was ... view the full minutes text for item 7. Awdur: Bleddyn Jones and Catrin Thomas |
|
REVENUE BUDGET REPORT - END OF AUGUST 2022 REVIEW PDF 213 KB Cyflwynwyd gan: Cllr. Ioan Thomas Additional documents: Decision: To accept the report on the end of August
2022 review of the Revenue Budget, and consider the latest financial position
regarding the budgets of each department/service. To note that the financial impact of Covid on some fields continued in 2022/23, although the
impact is not as substantial in 2022/23 compared to the last two years, which
are a combination of additional costs, income losses and a slippage in the
savings programme. To note that significant overspend is
anticipated in the Adults, Health and Well-being Department, Education
Department, Economy and Community Department, Highways and Municipal Department
and the Housing and Property Department this year. The specific reasons that
affect departments are detailed in section 5 of the report, but the impact of
increased inflation and electricity prices is a particularly prominent factor. Given the substantial overspend anticipated
by the Adults, Health and Well-being Department and the Highways and Municipal
Department, the Chief Executive’s intention to convene a meeting with the
relevant officers was noted in an attempt to get to the root of the overspend,
to ensure that definitive steps are taken in an attempt to bring the situation
under control before the end of the financial year, and to report to the
Cabinet on the response plan. Although it was premature to transfer money
from funds until the financial position is finalised at the end of the year, it
is recommended that the procedure in terms of using funds to fund the financial
deficit at the time will be: ¾ firstly, use School Balances to fund the
increase in electricity prices in schools ¾ secondly, use £4.5 million from the post-Covid recovery arrangements fund established to fund the
associated financial challenges that face the Council ¾ finally, finance the rest from the Financial
Strategy Reserve. Minutes: The
report was submitted by Cllr Ioan Thomas.
DECISION To accept the report on the end of August
2022 review of the Revenue Budget, and consider the latest financial position
regarding the budgets of each department/service. To note that the financial impact of Covid on some fields continued in 2022/23, although the
impact is not as substantial in 2022/23 compared to the last two years, which
are a combination of additional costs, income losses and a slippage in the
savings programme. To note that significant overspend is
anticipated in the Adults, Health and Well-being Department, Education
Department, Economy and Community Department, Highways and Municipal Department
and the Housing and Property Department this year. The specific reasons that
affect departments are detailed in section 5 of the report, but the impact of
increased inflation and electricity prices is a particularly prominent factor. Given the substantial overspend anticipated
by the Adults, Health and Well-being Department and the Highways and Municipal
Department, the Chief Executive's intention to convene a meeting with the
relevant officers was noted in an attempt to get to the root of the overspend,
to ensure that definitive steps are taken in an attempt to bring the situation
under control before the end of the financial year, and to report to the Cabinet
on the response plan. Although it was premature to transfer money
from funds until the financial position is finalised at the end of the year, it
is recommended that the procedure in terms of using funds to fund the financial
deficit at the time will be:
DISCUSSION The report was submitted, noting that the
report detailed the latest review of the Council's revenue budget for 2022/23,
along with the projections for the end of the financial year. It was expressed that the report had already
been submitted to the Governance and Audit Committee and they had been very
supportive of the recommendation. It was noted that the current projections
suggested that the Adults, Health and Well-being; Children and Families;
Education; Economy and Community; Highways and Municipal and Housing and
Property Departments were overspending by the end of the financial year. It was
highlighted that the impact of an increase in inflation, particularly the
electricity costs above the budget was to be seen most prominently in the
Education, Highways and Municipal and Economy and Community departments. It was noted that the rest of the Council's
departments were operating within their budget. It was expressed that the impact of Covid could not be seen as substantial as what had been seen over the past two years, but that additional costs, income losses and slippages on savings schemes continued in some fields. It was highlighted that a delay in realising savings was evident in the Adults, ... view the full minutes text for item 8. Awdur: Ffion Madog Evans |
|
SAVINGS OVERVIEW REPORT - END OF AUGUST 2022 REVIEW PDF 415 KB Cyflwynwyd gan: Cllr. Ioan Thomas Additional documents:
Decision: To accept the information in the report and to
note the progress towards realising the savings schemes for 2022/23, 2021/22
and previous years. To note that the impact of Covid-19 had
contributed to a slippage in the savings programme, as the Council had given
the utmost priority to safeguarding the health and lives of the people of
Gwynedd in response to the crisis. Minutes: The report was submitted by Cllr Ioan Thomas DECISION To accept
the information in the report and to note the progress towards realising the
savings schemes for 2022/23, 2021/22 and previous years. It was
noted that the impact of Covid-19 had contributed to a slippage in the savings
programme, as the Council had prioritised responding to the emergency during
the initial period of the crisis. DISCUSSION The report was submitted, noting that the report
summarised the Council's savings' situation. It was explained as per the
previous report, that the report had been submitted to the Governance and Audit
Committee, which was eager to recommend to the Cabinet that the schemes that were
not being realised needed to be challenged in detail and that there was a need
to ensure a regular review of those schemes that were slipping and refer the
schemes to the work programmes of the relevant Scrutiny Committees. It was expressed that since 2015/16, savings to the
value of £35.4m had been approved to be realised during the 2015/16 - 2022/23
period. It was further emphasised that a total of £3.4m of savings had been
realised, which was 94% of the required sum over the period. It was explained
for the period from 2015/16 to 2020/21 that 97% of the savings schemes had been
realised, with schemes from the Adults, Health and Well-being Department and
Highways and Municipal Department yet to be achieved. Attention was drawn to the 2021/22 savings, noting
that 65% of the schemes had now been delivered, with delivery problems to be
seen in the Highways and Municipal Department and the Housing and Property
Department. It was explained that when preparing the 2022/23 budget, it had to
be acknowledged that the situation had changed so much that it had not been
possible to deliver the savings schemes that had been planned originally and
almost half a million pounds' worth of schemes had been completely removed from
the budget. In addition, the delivery profile for schemes to the value of £1.3m
had been moved to 2023/24 and therefore, £595k was the value of the residual
schemes to be removed from the 2022/23 budget. Of these schemes for this year, it was noted that 22%
of the schemes had already been realised, with 19% now on track to deliver on
time. It was highlighted that the departments with the highest value schemes
that were yet to be delivered were the Highways and Municipal and Economy and
Community Departments. It was highlighted that realising £33.4m since April
2015 had been incredibly challenging, and that there were delays and delivery
risks with some of the remaining schemes. The need to review the schemes by the
end of the financial year was emphasised. Observations arising from the discussion ¾ It was noted that savings to the value of £33.4m which had been realised since 2015/16 highlighted the work that had been done by staff to face and realise the savings within the Council. Staff were thanked for their work. ... view the full minutes text for item 9. Awdur: Ffion Madog Evans |
|
CAPITAL PROGRAMME 2022/23 - END OF AUGUST REVIEW PDF 227 KB Cyflwynwyd gan: Cllr. Ioan Thomas Additional documents: Decision: To accept the report on the end of August
review (31 August 2020 position) of the capital programme. To approve the revised financing as presented
in part 4 of the report, as follows: ¾ use of various sources, worth a total of
£26,751,000, to fund actual slippages ¾ no change in the use of borrowing, ¾ an increase of £7,396,000 in the use of
grants and contributions, ¾ no change in the use of capital receipts, ¾ an increase of £2,156,000 in the use of
revenue contributions, ¾ an increase of £13,000 in the use of the
capital reserve, and ¾ an increase of £538,000 in the use of renewal
and other reserves. Minutes: The report was submitted by Cllr Ioan Thomas DECISION To accept
the report on the end of August review (31 August 2020 position) of the capital
programme. The revised
financing as presented in part 4 of the report was approved, as follows: ·
use
of various sources, worth a total of £26,751,000, to fund actual slippages ·
no
change in the use of borrowing, ·
an
increase of £7,396,000 in the use of grants and contributions, ·
no
change in the use of capital receipts, ·
an
increase of £2,156,000 in the use of revenue contributions, ·
an
increase of £13,000 in the use of the capital reserve, and ·
an
increase of £538,000 in the use of renewal and other reserves. DISCUSSION The report was submitted noting that the report presented
the revised capital programme and sought approval for the relevant financing
sources. It was explained that this report had also been submitted to the
Governance and Audit Committee and they supported the recommendations. The main conclusions were highlighted, namely that the
Council had definitive plans in place to invest around £79.8m this year, with
£21.1m funded through specific grants. It was explained that the impact of
recent financial challenges continued on the capital programme, with only 11%
of the budget spent up to the end of August this year, compared with 16% over
the same period last year and 13% two years ago. It was noted that £12.1m of proposed expenditure had
been re-profiled from 2022/23 to 2023/24 and 2024/25 with the main schemes
including, £5.1 million for Schools Schemes, £3.0 million for Flood Prevention
Schemes and £1.6 million for the Penygroes Health and
Care Hub. Since the last review, it was expressed that the
Council had managed to attract the following grants: ¾
£1.6
million - Free School Meals Capital Grant. ¾
£0.9
million - Sustainable Learning Communities Grant - Schools Community Use. ¾
£0.9
million - Road Safety Capital Grant from the Welsh Government. ¾
£0.7
million - Wales Voluntary Action Council (WVAC) Grant towards rural schemes. Observations arising from the discussion ¾
It was noted that this
report was technical which highlighted some good news. Nevertheless, it was
noted that the impact of inflation would affect the Council's ability to
complete the schemes that were seeing a 30-40% increase in costs. It was
explained that the schemes may need to be prioritised in the future. Awdur: Ffion Madog Evans |