Venue: Cyfarfod Rhithiol / Virtual Meeting. View directions
Contact: Rhodri Jones 01286 679325
No. | Item |
---|---|
APOLOGIES To note any
apologies for absence. Minutes: Apologies were received from:- ·
Councillor Gary
Pritchard (Isle of Anglesey County Council) with Councillor Robin Williams
deputising. ·
Professor Joe Yates
(Wrexham University) with Richard Day deputising. ·
Professor Edmund Burke
(Bangor University) with Paul Spencer deputising. ·
Dafydd Gibbard (Cyngor
Gwynedd) with Sioned Williams deputising. ·
Ian Bancroft (Wrexham County Borough Council) with David Fitzsimon
deputising. ·
Gareth Ashman (UK
Government Observer) with John Hawkins deputising. ·
Wendy Boddington (Welsh
Government) ·
Mark Pritchard (Wrexham
County Borough Council). ·
Yana Williams (Coleg
Cambria). ·
Alwen Williams
(Ambition North Wales Portfolio Director). The Chair welcomed the deputies to the meeting. Councillor Dave Hughes was congratulated on being
elected Leader of Flintshire County Council recently and welcomed him to his
first Board meeting. |
|
DECLARATION OF PERSONAL INTEREST To receive any declarations of Personal Interest Minutes: A statement of personal interest was received from
Aled Jones-Griffith (Grŵp Llandrillo
Menai) for Item 9. It was noted that it was a prejudicial interest
and he withdrew from the meeting for the item. |
|
URGENT BUSINESS To note any
items that are a matter of urgency in the view of the Chairman for
consideration. Minutes: No urgent matters were raised. |
|
MINUTES OF THE PREVIOUS MEETING PDF 158 KB The Chair
shall propose that the minutes of the meeting held on 19 July 2024 be signed as
a true record. Minutes: The Chair signed the
minutes of the previous meeting held on 17 July 2024 as a true record. |
|
2024/25 REVENUE AND CAPITAL BUDGET - END OF AUGUST 2024 REVIEW PDF 528 KB Dewi Morgan
(Host Authority Head Of Finance and Statutory Finance Officer) and Sian Pugh
(Host Authority Assistant Head of Finance) to present the report. Additional documents:
Decision: 1. To
note and accept the NWEAB's end of August 2024 revenue review. 2. To
note and accept the NWEAB’s reserves update. 3. To
agree the NWEAB’s revised capital expenditure profile. Minutes: The report was presented by the Host Authority's Head
of Finance Department. RESOLVED 1. To
note and accept the NWEAB's end of August 2024 revenue review. 2.
To note and accept the
NWEAB's reserves update. 3.
To agree the NWEAB's revised
capital expenditure profile. REASONS FOR THE
DECISION ·
To note a forecast underspend of £5,966 against the
revenue budget in 2024/25. · To note a further slippage on the capital
programme, with an estimate of £14.28m expenditure in 2024/25 compared with the
approved budget of £24.67m for the year.
DISCUSSION It was
explained that the report noted the actual revenue position to the end of
August 2024 and also estimated the position up to the
current financial year. An underspend of £6,000 was projected by the end of the
2024/25 financial year and various elements of the budget were detailed as
follows: · Net
overspending of £9,368 for the 'Portfolio Management Office' was forecast as a result of overspending on supplies and services. It was
noted that this overspend derived from systems costs
and it was explained that this budget heading would need to be reviewed for the
future. · It
was explained that the £20,000 underspend of 'Cyngor Gwynedd's Finance Services
Support' would be used to fund the spending on external financial support which
formed a part of the 'Projects' heading. · It
was confirmed that spending under the 'Joint Committee' heading was expected to
be within the budget for 2024/25. · It
was noted that the 'Projects' heading indicated a net overspend of £70,000. It
was explained that this was mainly due to external legal support that was
required for several capital programme projects. ·
It
was explained that the 'Grants' heading included expenditure on local Area
Energy projects and the Shared Prosperity Fund. It was confirmed that an
extension until March 2025 had recently been received on the Local Area Energy
grant, therefore, this overspend would be funded by the grant. Reference
was made to principal income streams for the 2024/25 financial year. It was
noted that these included partner contributions, the 'North Wales Growth Deal
Grant' revenue allocation of the Welsh Government Energy grant, the North Wales
Corporate Joint Committee, the Shared Prosperity Fund
and the reserve fund. The
position of the Board's funds was reported stating that there was an estimated
balance of nearly £211,000 in the general reserve fund. There was an estimated
balance of £152,000 in the projects fund and £7.2 million in the interest fund.
It was explained that the interest fund had been earmarked to fund future
borrowing costs. It was noted that high interest currently meant that the Board
received a significant amount of interest on the balances with an estimated
interest of £2.5 million for 2024/25. The latest position of the capital programme was shared stating a net reduction of £10.39 million in projected expenditure for 2024-25. It was explained that this was due to delays on four projects, namely 'Smart Local Energy', 'Deeside Fuel to Waste', 'Holyhead Port' and the 'Former North Wales Hospital ... view the full minutes text for item 5. |
|
NORTH WALES ECONOMIC AMBITION BOARD JOINT COMMITTEE - DETAILED AUDIT PLAN 2024 PDF 594 KB To present
the Detailed Audit Plan for the NWEAB Joint Committee provided by Audit Wales. Decision: To
accept the Audit Wales report which highlighted the NWEAB's Audit Plan for
2024. Minutes: The report was submitted by the Audit Wales
representative. RESOLVED To accept the Audit
Wales report which highlighted the NWEAB's Audit Plan for 2024. REASONS FOR THE DECISION To examine the financial statements of the
North Wales Economic Ambition Board Joint-committee to
ensure that public funds are properly accounted for. The Joint Committee must put in place
arrangements to get value for money for the resources it uses, and the Auditor
General must be satisfied that it has done this. Committee members were guided through the Detailed
Audit Plan 2023-24 outlining the fee, recognised risks, information about the
audit team and the time taken to complete the audit. It was announced that the material level had been
noted as £83,000. It was explained that this figure had been calculated by
finding 2% (percentage relevance) of gross expenditure during the 2023-24
financial year (£4.159 million). It was noted that this fee was higher than the
previous year due to an increase in gross expenditure. It was elaborated that a
lower relevance level had been set for some areas of the accounts as they could
be more important to the users of the accounts. It was explained that those
areas were 'Senior officer remuneration' and 'Related party disclosures'. Attention was drawn to one significant risk that had
been identified following an assessment of inherent risk. It was confirmed that
the risk was that Managers could override controls. It was explained that the
risk had been identified for Exhibit 1: significant financial statement risk,
and that it was identified in all audit plans for each Body in Wales. It was
emphasised that this was not a risk that had been identified for this Board
alone. It was assured that Audit Wales ensured that their procedures responded
to this risk. It was explained that 'Valuation of pension fund net
liability' had been noted as a risk within Exhibit 2: other areas of focus, as
an Audit Risk. It was noted that this risk was general in nature and would be
found in a number of recent audit plans. It was
stressed that this risk had not been identified for this Board alone. The audit timetable was detailed noting that the
Detailed Audit Planning work had been completed in July 2024 and the audit work
had been completed in August 2024. It was noted that it was intended to submit
a further report to the Board in November. It was highlighted that fees for 2024-25 had increased
by 6.4% as a result of inflation. It was estimated
that the audit fee total would be £26,754, stressing that a refund would be
submitted to the Board if the actual fee was lower, as Audit Wales was unable
to make a profit. The officers who had been collaborating with Audit
Wales to respond to any queries throughout the audit process, were thanked. |
|
ADVANCED WIRELESS - OUTLINE BUSINESS CASE PDF 377 KB Stuart
Whitfield (Digital Programme Manager) to present the report Additional documents:
Decision: 1. To
approve the Outline Business Case for the Advanced Wireless project subject to
Welsh Government and UK Government approval of the assurance process
undertaken, subject to the Portfolio Management Office addressing the
outstanding issues set out in Section 7 of the report, and request that a Full
Business Case is prepared for the Board to consider. 2. To
delegate to the Portfolio Director, in consultation with the Chair and Vice
Chair, final approval of the procurement specification and social value
criteria prior to project funders commencing procurement. 3. To
authorise the Portfolio Director in consultation with the Host Authority
Section 151 Officer and Monitoring Officer to agree draft terms in accordance
with this report for approval by the NWEAB as a basis for the final funding
arrangements for the project which will form the basis of the Grant Offer
Letter which will be agreed by the Board at the Full Business Case stage. Minutes: The report was
submitted by the Digital Programme Manager. DECISION 1. To approve the Outline Business Case for the Advanced
Wireless project subject to Welsh Government and UK Government approval of the
assurance process undertaken, subject to the Portfolio Management Office
addressing the outstanding issues set out in Section 7 of the report, and
request that a Full Business Case is prepared for the Board to consider. 2. To delegate to the Portfolio Director, in consultation
with the Chair and Vice Chair, final approval of the procurement specification
and social value criteria prior to project funders commencing procurement. 3. To authorise the Portfolio Director in consultation
with the Host Authority Section 151 Officer and Monitoring Officer to agree
draft terms in accordance with this report for approval by the NWEAB as a basis
for the final funding arrangements for the project which will form the basis of
the Grant Offer Letter which will be agreed by the Board at the Full Business
Case stage. REASONS FOR THE
DECISION To seek the Board's approval for the Advanced Wireless
Project Outline Business Case. As a project delivered by Ambition North Wales,
approval was required by the Board to establish the frameworks that will
deliver the project. DISCUSSION It was explained that the
project would support businesses and public bodies to invest in the latest
wireless technology, including 5G and state-of-the-art Wi-Fi across the North
Wales region. It was hoped that this would increase efficiency and productivity.
It was noted that there was evidence to support that this kind of investment
led to business development, commercial sustainability and created more jobs.
Attention was drawn to the fact that several large companies had taken
advantage of this type of technology and the project hoped to reduce the
commercial risks to companies as they newly approached the development. It was
considered that sectors that would benefit the most from this technology
included manufacturing, transport, logistics, agriculture
and tourism. Examples were shared of potential investments within these areas
such as providing equipment for production lines in factories, 5G private
networks, upgrading networks to support logistics operations in transport hubs
as well as Smart Towns applications to improve monitoring and communication in
our town centres. It was reported that this
project was the second part of the 'Connected Campuses' project. It was
explained that the first project was a LPWAN project, which extended Low Power
Wide Area Network provision to support innovative 'Internet of things' applications
across public and private sectors through LoRaWAN
wireless technology. Members were reminded that this project had already been
approved by the Board. It was explained that the main spending objective of the project was to 'Enable 100-200 businesses and public sector users in all North Wales counties to take advantage of advanced wireless connectivity by 2030'. It was hoped that this would lead to the creation of between 130-200 jobs within the region and the creation of an additional net GVA of between £41 million and £62 million by 2036. It ... view the full minutes text for item 7. |
|
EXCLUSION OF PRESS AND PUBLIC The Chair shall
propose that the press and public be excluded from the meeting during the discussions on the following items due to the likely disclosure of exempt information as defined in Paragraph 14 of Schedule 12A
of the Local Government Act 1972 Information relating to the financial or business affairs of any particular person (including the authority holding that information). There is an
acknowledged public interest in openness
in relation to the use of public resources
and related financial issues. It is also acknowledged that there are occasions,
in order to protect the financial and commercial interests that matters related
to such information need to be discussed without being publicised.
The reports deal specifically with financial and business matters and related discussions. Publication of such commercially sensitive information could adversely affect the interests of the
bodies and the Councils and undermine
the confidence of other Growth Deal participants
in sharing sensitive information for consideration. This would be contrary
to the wider public interest of securing the best overall outcome. Minutes: RESOLVED to exclude the press and public from the
meeting during the discussion of Item 9 as it is likely that exempt information
will be disclosed as defined in Paragraph 14 of Annex 12A of the Local
Government Act 1972 - Information regarding the financial or business
transactions of any particular person (including the
authority holding such information). There was an acknowledged public interest in
being open about the use of public resources and related financial issues. It
was recognised, however, that there were occasions in order
to protect public financial and commercial interests, where such
information must be discussed without being publicised. The reports related
specifically to financial and business matters and related discussions.
Publication of such commercially sensitive information could adversely affect
the interests of the bodies and the Councils and undermine the confidence of
other Growth Deal participants in sharing sensitive information for
consideration. This would be contrary to
the wider public interest of securing the best overall outcome. |
|
TOURISM TALENT NETWORK - FULL BUSINESS CASE Dafydd Owen
Jones (Agri-food and Tourism Project Manager) and ColinDavid Mathews (Growth
Deal and and Property Programme Manager) to present the report. Decision: 1.
To approve the Full Business
Case for the Tourism Talent Network project. 2.
To authorise the Portfolio
Director, in consultation with the Chair, Vice Chair, Section 151 Officer and
Monitoring Officer to agree and enter into a funding agreement with Grŵp
Llandrillo Menai for the delivery of the project, on the basis that Grŵp
Llandrillo Menai satisfactorily addresses the 'outstanding issues' set out in
section 7.1 of the report. 3. To
delegate final approval of the remaining procurement in Phase 1 to the
Portfolio Director, in consultation with the Chair, Vice Chair, Section 151
Officer and Monitoring Officer where expenditures and benefits are within the
parameters of the Full Business Case presented. 4. To
delegate authority to the Portfolio Director, in consultation with the Chair,
Vice Chair, Section 151 Officer and Monitoring Officer to approve the
subsequent Business Justification Case for Phase 2 of the project, the fourth
spoke, where expenditure and benefits are within the parameters of the Full
Business Case presented. Minutes: The report was
submitted by the Agri-Food and Tourism Project Manager and the Growth Deal's
Land and Property Programme Manager. DECISION 1.
To approve the Full Business Case for the Tourism
Talent Network project. 2.
To authorise the Portfolio Director, in consultation
with the Chair, Vice Chair, Section 151 Officer and Monitoring Officer to agree
and enter into a funding agreement with Grŵp Llandrillo Menai for the delivery of the project, on the
basis that Grŵp Llandrillo
Menai satisfactorily addresses the 'outstanding issues' set out in section 7.1
of the report. 3. To delegate final approval of the remaining
procurement in Phase 1 to the Portfolio Director, in consultation with the
Chair, Vice Chair, Section 151 Officer and Monitoring Officer where
expenditures and benefits are within the parameters of the Full Business Case
presented. 4.
To delegate authority to the Portfolio Director, in
consultation with the Chair, Vice Chair, Section 151 Officer and Monitoring
Officer to approve the subsequent Business Justification Case for Phase 2 of
the project, the fourth spoke, where expenditure and benefits are within the
parameters of the Full Business Case presented. REASONS FOR THE DECISION To seek the Board's approval of the Outline Business
Case for the Cydnerth project. DISCUSSION The report was
discussed. |