Decision status: Approved
Is Key decision?: No
Is subject to call in?: No
To delegate powers to
the Assistant Head of Department to approve the application, subject to the
following amendment to Condition 1 of planning permission C10D/0487/34/MW so as
to extend the lifespan of a minerals operations involving the operation of three
ancillary silting lagoons and associated works for an additional 4 years:
Extraction,
processing and dispatch of minerals shall cease by 31 December 2024 by which
time all plant and machinery shall have been removed from the site; restoration
shall be completed by 31 December 2025.
Consultation response
from Natural Resources Wales and Welsh Water attached to the decision notice,
advising that they should be contacted direct in respect of the specific
environmental and operational controls within their remit.
Planning conditions
as existing in relation to the following regulatory controls;
• Duration of work,
• Restriction
on permitted development rights, buildings, structures, private ways,
floodlighting and fences,
• Permitted operations and compliance
with submitted Details / Plans,
• Hours of Working,
• Safeguarding Public Rights of Way,
• Soil treatment and husbandry,
• Drainage, measures to prevent the
pollution of local water courses,
• Restore to mixed agricultural use and
nature conservation,
• Reinstatement of field boundaries,
• Archaeological mitigation and
recording,
• After-care measures and annual
meetings for agricultural use,
biodiversity management and control of non-native invasive plant species,
• Dust
controls and noise limitations the same as existing but also, plant machinery
at the working face to be fitted with white noise alarms.
Publication date: 12/04/2021
Date of decision: 12/04/2021
Decided at meeting: 12/04/2021 - Planning Committee
Accompanying Documents: