To submit the report of the Maritime and Country Parks Officer.
Minutes:
The Maritime and Country Parks Officer noted that the harbour staff had
been busy in terms of work over the winter, with the severe weather being a
factor.
The representative from the Pwllheli and District Boat Owners
Association thanked the Pwllheli Harbour Manager and the staff for replacing
ropes and a buoy on his boat therefore ensuring its safety.
The Pwllheli Marina Berth Holders' Association noted his appreciation of
the work of the harbour staff on behalf of the Association.
The Maritime and Country Parks Officer guided the members through the
report, drawing attention to the following main points:
·
The report of the
Coastguard Agency's inspectors on their thorough inspection of the the current
safety arrangements and systems of Gwynedd municipal harbours in order to
ensure compliance with the Ports' Safety Code had been included in the agenda.
The inspectors noted that the Council complied with the requirements in general
but that some aspects relating to recording duties and noting the Duty Holder
and Designated Person needed to be amended.
·
That the inspectors had
noted that the lack of width in the harbour's navigation channel although it
was not technically a part of the inspection.
·
An external company had
been commissioned to carry out a full hydro-graphic survey of the navigation
channel; the entrance of the inner harbour; and the marina basin including the
basin of Plas Heli's pontoon moorings. An electronic copy of the report, along
with paper copies, were available to members at the Hafan office.
·
The work of levelling
the channel bed would be completed in May and the basin dredging work would be
completed during the winter months of 2018/19.
·
Gwynedd Consultancy had
been commissioned to undertake detailed design work on the Crib Groyne.
Hopefully, the work of restoring the Crib Groyne would be completed before October
2018;
·
The work of dredging the
harbour entrance would be undertaken in April. This would be the last campaign
before moving the material from the bund to the Carreg y Defaid beach area.
·
High speed zone buoys in
the South Beach area and Abererch beach area would be installed in their
correct positions before Whitsun.
·
Attention was drawn to
the fact that the maintenance work list for the Hafan and the Harbour was
included in the agenda. Members were asked to note any further work that should
be considered.
·
That the Hafan's mobile
crane had deteriorated beyond the point where it was worth investing
substantial money to maintain it. As a mobile crane service was available from
local companies in Pwllheli, the Service would consider selling the crane and
hiring a crane service by local companies as needed. This would be more cost
effective.
·
That harbour staff had
collaborated with the Sailing Club to clear and tidy the old Sailing Club site.
·
That work had been
completed on the day of the meeting to fill the potholes in Glandon Beach car
park. Discussions would be held with Plas Heli in relation to a plan to tarmac
a section of the car park.
·
That changes had been
introduced to the terms of some Hafan staff members who had decided to transfer
from TUPE protection to the Council's employment contract. Three Hafan staff
members remained under the protection of TUPE employment terms. Following the
changes to the contracts, the service had reviewed the opening hours of the
Hafan office to ensure that these changes did not affect the continuity of
service for Pwllheli harbour customers. Attention was drawn to the fact that
the office would not be open between 07:00 and 08:00 or between 18:00 and
19:00.
·
A copy of the Harbour
and Hafan's budget summary for 2018-19, up to the end of February 2018, was
shared at the meeting. Its content was elaborated upon and it was noted that
the situation was challenging in terms of income targets and thanks was
expressed for the staff's commitment.
·
Although inflation rates
for the Harbour and Hafan had increased since the 2018/19 spreadsheet of fees
had been submitted to the previous meeting, it was recommended to the Cabinet
Member that the fees and payments should continue to increase by 2% on average
for the 2018/19 financial year because the service had already corresponded
with the Harbour and Hafan's customers.
In response to a query regarding difficulties in entering the harbour
with a boat, the Maritime and Country Parks Officer stated that he shared those
concerns. He added that a form was available at the Hafan Office so that users
could record incidents where boats had struck the seabed and that he encouraged
everyone who struck the seabed to submit a form.
The Pwllheli Sailing Club and Plas Heli representative noted that it was
timely to inform users that the work of levelling the channel bed was moving
ahead, considering that individuals would be deciding in April whether or not
to continue to keep a mooring.
In response to a question, the Maritime and Country Parks Officer noted
that 25,000m3 of material would need to be dredged from the harbour
entrance, it was also acknowledged that more material came in at all tides. He
anticipated that approximately 15,000m3 would be dredged in the next
attempt. He warned that it would not be possible to dredge more material as
there was no adequate space available for storage. He noted that it was not
currently possible for two boats to pass each other and that the work would
improve the existing circumstances. In
response the Pwllheli Harbour Berth Holders' Association Representative noted
that consideration should be given to dredging twice the amount of material
intended to be dredged and that he was of the opinion that dredging the amount
intended would not make a difference.
During the subsequent discussion, the following main points were noted
by members:
·
That a positive message
needed to be sent out to people regarding the work done as part of the Dredging
Strategy.
·
That the work of
levelling the channel bed intended to be carried out would not be effective
enough.
·
That the tide moved a
considerable amount of material over the breakwater to the channel; the
material had to be prevented from moving up the channel. Last year had been a bad year in terms of
access and it was estimated that if the situation worsened, then the owners of
approximately 50 boats would consider leaving Hafan.
·
That users needed to be
informed immediately without delay about the detail of the work currently being
carried out, along with a timetable of the work involved with the Dredging
Strategy, using simple terms.
·
Acknowledge that it was
difficult to carry out work to dredge more than what was intended from the
harbour entrance in April due to the tide, but would it be an option to
continue with the dredging work in May?
·
That there was a need to
include details on the website of the dredging work being carried out in order
to confirm the actual situation. If users left, it would take years to get them
to return.
·
That it was difficult to
pass within the entrance and that something needed to be done urgently.
·
Would it be possible to
carry out the dredging work in April in two shifts, in order to increase the
total amount of material being dredged?
·
Would it be possible to
pump sand over the breakwater?
·
Welcomed the fact that
something was being done.
·
Would jetting be an
option?
·
That there was a need to
question the baseline noted that the level of particulates in the material
dredged had to be less than 15% if it was to be returned to the sea.
·
Would the work of
levelling the channel bed be monitored?
In response to the above observations, the officers noted:
·
That there was a need to
work within the tide window and there would not be enough time to dredge more
material.
·
The further necessary
dredging work to be carried out in the 2018/19 Winter months, would be assessed
in detail.
·
That the Hafan was
essential to the local economy and that ensuring that the harbour entrance and
channel were functioning properly was vitally important.
·
Fully agreed regarding
access and were aware of the difficulties. The recent high winds had had an
impact. The members would be invited to view the situation once the work of
levelling the channel would be completed.
·
Confirmation was
received that finance was in place to dredge the harbour entrance in April, to
level the channel bed in May, to dredge the basin during the Winter 2018/19 and
to carry out repairs on the Crib Groyne.
Consideration would also be given to the possibilities of acting within
the powers of the Harbour Act to pump material to Abererch without the need for
a marine licence.
·
The situation was not
ideal but positive steps were being taken for the future.
·
That tenders for the
dredging work in April/May had been sent out; however, consideration could be
given to see whether there was any scope to extend the work.
·
Should there be an
intention to carry out work outside the permitted hours, there would be a need
to consult with nearby residents. There was also a need to consider lack of
capacity in the bund to accommodate more material.
·
Natural Resources Wales
could be consulted with to see whether it would be acceptable to pump sand over
the breakwater.
·
Jetting would not be
sustainable in the short-term or long-term. Agitate and jetting work had been
carried out around the fuel pontoon but the material had not moved out enough
and consideration had been given to environmental matters in terms of moving
material to the sea.
·
Agree to verify the
level of particulates in the material dredged allowed to be returned to the
sea.
·
Confirmed that the
Pwllheli Harbour Manager would monitor the work on the channel bed. In
addition, a further hydro-graphic survey would be undertaken after the work was
completed.
In terms of the opening hours of the Hafan office, the Pwllheli Berth
Holders' Association Representative suggested that consideration should be
given to starting and finishing the night security officer's working hours an
hour earlier in order to bridge the gap in the Hafan office's opening
hours.
In response, the Pwllheli Harbour Manager noted that this would be
considered.
The Maritime and Country Parks Officer noted that following the damage
in Holyhead Harbour as a result of the inclement weather, he had corresponded
with the Isle of Anglesey Council and Holyhead Harbour to note that there was
capacity at Hafan. He asked for the views of the Consultative Committee in
terms of offering a mooring in Hafan to the users of Holyhead Harbour for the
same fee as Holyhead Harbour for one year only. He added that the offer was
intended as a goodwill gesture; however he wished to receive the consent of
members.
Members noted their support for the proposal for one year only and it
was assumed that the majority of users would support the proposal in order to
assist their fellow mariners.
The Pwllheli and District Boat Owners Association suggested that a
letter should be sent on behalf of the Consultative Committee to Holyhead
Harbour to sympathise with their situation following the inclement
weather.
The Pwllheli Sailing Club and Plas Heli representative noted that the
Hafan's facilities were to be praised and that the sheltered location of the
harbour had prevented damage from being caused by the inclement weather. He
emphasised that such a case showed the importance of the work of inspecting
chains.
RESOLVED:
(i) to note and accept the
report
(ii) to support the proposal
to offer a mooring in Hafan to the users of Holyhead Harbour for the same fee
as Holyhead Harbour for one year only;
(iii) that the Maritime and
Country Parks Officer send a letter on behalf of the Consultative Committee to
Holyhead Harbour to sympathise with their situation following the inclement
weather.
Supporting documents: