Hedd
Vaughan-Evans, Operations Manager to present the Quarter 3 (October-December) Growth Deal report and
updated Portfolio Risk Register.
Decision:
To note the Quarter 3 Performance Report and updated
Portfolio Risk Register.
To approve the submission of the Quarter 3 Performance Report to Welsh Government and UK Government as well as the local authority scrutiny committees.
Minutes:
The report was submitted by Hedd Vaughan-Evans
DECISION
To note the Quarter 3 Performance Report and updated Portfolio Risk
Register. To approve the submission of the Quarter 3 Performance Report to
Welsh Government and UK Government as well as the local authority scrutiny
committees.
REASONS FOR THE DECISION
In
December 2020, the NWEAB and the Welsh and UK Governments agreed the Final Deal
Agreement for the North Wales Growth Deal. Regular reporting on progress
against the North Wales Growth Deal is one of the requirements of the Final
Deal Agreement.
DISCUSSION
The report was submitted, noting that reporting on progress over the
last quarter against the Growth Deal was one of the requirements of the Final
Deal Agreement. It was explained that, following the Board's consideration, the
reports would be shared with Welsh Government, UK Government as well as the
local authority scrutiny committees.
The quarter highlights were explained, noting that the Growth Deal's
first Full Business Case had been approved back in December, namely the Digital
Signal Processing Centre with Bangor University. It was noted that two other
projects had completed their Gateway 2 assurance reviews successfully, namely
the Former North Wales Hospital, Denbigh project and the Llysfasi
Net Zero Farm.
It was noted that an update on the 2021 Portfolio Business Case had been
submitted to both Governments as part of the annual award of funding process.
It was outlined that the new 'Ambition North Wales' brand had been launched
together with the new website. It was noted that recruitment activities had
been completed also, with the last three posts in the team filled from January
2022.
Members were guided through the projects, giving an update on the work
that had been carried out over the last quarter. It was noted that the risk
register had been updated in full with a number of adaptations recorded in the
document which included amended risk descriptions, scoring and amended
mitigation measures. Attention was drawn to three residual risks which had
changed, the first - capacity risk, had reduced now that the PMO's recruitment
activities had been completed, the second - public sector investment, and third
- expenditure objectives. It was explained that the second and third had
increased as a result of a number of project change requests being considered.
Observations arising from the discussion
¾
It was noted that
phosphate was having an impact on a number of specific projects in Flint and
Wrexham and it was asked what impact this would have on other projects. It was emphasised
that a number of projects were under threat, and it was noted that it needed to
be identified as a risk for the portfolio and a further discussion would be
needed at the next meeting.
¾
It was also noted that
there was a need to look at flood risks, as there were implications for all
projects, and as a result there was a need to map out all the projects.
¾
Thanks were given for the
good work undertaken by Bangor University pushing the Digital Signal Processing
Centre forward.
Supporting documents: