To consider the information and the risks regarding the Capital Programme, and scrutinise the Cabinet’s decisions
Decision:
·
To accept the report and
note the relevant risks in the context of the capital programme of the Council
and its Departments.
·
To accept the Cabinet's
decision 18/01/2022
Minutes:
A
report was presented by the Senior Finance Manager on the amended capital
programme (position as at end of November 2021) and approval of relevant
funding sources. Attention was drawn to the impact of the Covid-19 crisis on
the capital programme, and it was highlighted that only 37% of the budget had
been spent up to the end of November 2021, compared with 31% over the same
period last year and 51% two years ago (2019/20 before the interruption of
Covid19). It was added that an analysis per Department of the £127.7 million
capital programme for the 3 years 2020/21 - 2023/24 had been included in the
report.
Reference
was made to the sources to fund the net increase of approximately £3.7 million
since the last review, and it was added that the main conclusions were that the
Council had specific plans in place to invest approximately £52.1 million this
year, with £27.4 million of it, namely 53%, funded by attracting specific
grants.
It
was explained that £22.1 million in proposed spending had been re-profiled from
2021/22 to 2022/23 and 2023/24, with the main plans including
·
£6.2
million in Housing Strategy Plans
·
£5.8
million in Flood Prevention Schemes
·
£5.4
million in 21st Century Schools Plans and Others (21st century).
Attention
was drawn to the main plans, as well as the additional grants list that the
Council had succeeded in attracting since the last review, including:
·
£2.3
million School Maintenance Grant
·
£1.4
million Welsh Government Grant towards Flood Prevention
·
£0.4
million Economic Stimulation Fund Grant
·
£0.3
million Ysgol Treferthyr Childcare Grant.
At
the meeting of the Cabinet (18 January 2022), it was resolved to accept the report
and approve all the recommendations.
Thanks were expressed for the report
During
the ensuing discussion, the following observations were made by members:
·
The
report reflected good news
·
The
staff who found and succeeded in attracting additional funding should be
congratulated - it was a significant sum and was an investment in the Council's
capabilities.
In
response to a question regarding 2022/23 schemes that had been re-profiled
since the original budget (and that the figure was the same from year to year),
and whether the implications of increasing costs / prices had been built into
the likely plan or slippage, it was noted that inflation was at its highest for
many years and therefore, while there was a specific sum in the budget for
capital items, there were limitations on how far the funding would stretch.
Reference was made to a discussion in the Cabinet in October 2021 on the end of
August capital budget review where the Chief Executive noted that an intentional
decision had been made to try to slip some capital schemes, in order to wait
for the prices of some commodities, such as timber, to stabilise. It was added
that a reflection of these slippages had been included in the figures.
RESOLVED
·
To accept the report and note the relevant risks in the context of the
capital programme of the Council and its Departments.
·
To accept the Cabinet's decision 18/01/2022
Supporting documents: