Henry Aron
to
seek agreement for Ambition North Wales to deliver Local Area Energy Plans (LAEPs)
in North Wales.
Decision:
1. To agree to adopting a coordinated, regional approach to delivering the
Local Area Energy Plans across north Wales local authorities led by the
Portfolio Management Office (via Gwynedd Council as Accountable Body).
2. To agree to the recruitment of a project manager and two project
officers to deliver the LAEPs to be funded by Welsh Government and delegate
authority to the Portfolio Director in consultation with the s151 Officer and
the Monitoring Officer, to agree the grant funding agreements with Welsh
Government and implement the proposal.
3. To note that, subject to a grant funding agreement, Welsh Government
will provide grant funding to cover the costs of delivering the plans and for
the project management resource.
4. To
note that the appropriate project governance arrangements will be implemented
in all local authorities to submit and approve the plans.
Minutes:
The report was submitted by Henry Aron (Energy
Programme Manager).
DECISION
(1) To
agree to adopting a coordinated, regional approach to delivering the Local Area
Energy Plans across north Wales local authorities led by the Portfolio
Management Office (via Gwynedd Council as Accountable Body).
(2)
To agree to the recruitment
of a project manager and two project officers to deliver the LAEPs to be funded
by Welsh Government and delegate authority to the Portfolio Director in
consultation with the s151 Officer and the Monitoring Officer, to agree the
grant funding agreement with Welsh Government and implement the proposal.
(3)
To note that, subject to a
grant funding agreement, Welsh Government will provide grant funding to cover
the costs of delivering the plans and for the project management resource.
(4)
To note that the appropriate
project governance arrangements will be implemented in all local authorities to
submit and approve the plans.
REASONS FOR THE
DECISION
To seek
the agreement of Ambition North Wales to deliver Local Area Energy Plans
(LAEPs) in North Wales.
Welsh
Government had made a commitment to support Local Area Energy Planning (LAEP)
across Wales and had proposed a coordinated regional approach to delivery. North Wales’ local authority Chief Executives
had confirmed their support for this approach and for delivery to be
coordinated by Ambition North Wales’ Portfolio Management Office.
DISCUSSION
Details were provided about the background and relevant
considerations and the consultations held.
With reference to the decisions sought, the Energy
Programme Manager asked the Board to consider making the following additional
decision, following engagement with the chief executives:-
“To note that the
appropriate project governance arrangements will be implemented in all local
authorities to submit and approve the plans."
The Monitoring Officer asked the Board to consider
adapting decision 2 as follows, in order to allow the establishment of grant arrangements
between Gwynedd and the individual councils also, should they be needed.
"To agree to
the recruitment of a project manager and two project officers to deliver the
LAEPs to be funded by Welsh Government and delegate authority to the Portfolio
Director in consultation with the s151 Officer and the Monitoring Officer,
to agree the grant funding agreement and implement the proposal.
The following matters were raised by members:-
·
It
was noted that Conwy Council had gone through the process, and that the
feedback showed that the exercise had been beneficial, was a benchmark of where
we had reached, and had set a pathway for where we needed to be. It was believed that it was sensible to
operate regionally, because, although some things were relevant to specific
counties, the main schemes, such as hydrogen, tidal lagoons and transport,
would have to be undertaken regionally.
·
In
response to a request for more clarity regarding the amendment to decision 2,
the Monitoring Officer explained that, although grants were received by the
Board, an element of their implementation was in the hands of the individual
authorities, therefore, there was a need to secure the mechanism for
establishing the accountability line between implementing and signing the
grant, should that be needed.
Supporting documents: