The Committee is asked to note the position and any risks
relating to the Council’s capital programme, consider the Cabinet’s decision and comment
as necessary
Decision:
To accept the report
To note the relevant risks
To support the Cabinet's decision (14 June
2022)
Minutes:
The Senior Finance Manager highlighted
that the main purpose of
the report was to present
the revised capital programme at the end of the financial year (31 March 2022 position), and to approve the relevant financing sources. The analysis per Department
of the £139.3 million capital
programme for the 3 years 2021/22 - 2023/24 was referred
to together with the sources available to fund the net increase of approximately £11.0 million since the previous review.
The main findings of the review
was that the Council had managed to spend £37.1m in 2021/22 on capital
schemes, and £29.9m (81%)
of it funded through specific grants.
It was reported that
the impact of the Covid-19 emergency
and the lockdown period on the capital
programme was evident and in addition
to the £31.2m reported in
the previous reviews, a further £26.8m of proposed expenditure had been re-profiled, namely slippage from 2021/22 to 2022/23,
and the main plans included:
·
£7.6 million in Housing Strategy
and Homelessness Plans
·
£7.2
million in Flood Prevention and Land Drainage
Schemes
·
£6.5
million in 21st Century Schools Plans and Others
·
£4.0
million in Welsh Government New Grants in the Housing field (slippage replaced resource)
·
£3.2 million in Additional General
Capital Grant for 21/22 (received in the last quarter of the year with allowance
for slippage to 22/23)
In addition, the Council had managed to attract further grants since the last review (over 11 million) these included;
·
£3.2 million - Additional General Capital Grant 21/22 - permission for slippage to 22/23
·
£3.1
million - Grants from the Land and
Buildings Development Fund that allowed
replacing current funding for expenditure
in 22/23.
·
£1.3
million - Intermediate Care
Fund Grant - adapting adults establishments as well as facilitating joint working arrangements with other agencies
in the care field.
·
£1.1 million - Free School Meals
Capital Grant - allowing
the replacement of current funding for expenditure
in 22/23 on adaptations to school kitchens.
The Cabinet's decision
(14 June 2022) was to accept all the recommendations and:
·
To accept the report
·
To note the expenditure of £37,054,000 on the
capital programme during the 2021/22 financial year, which would
be used as a basis for the statutory financial statements for 2021/22.
·
To approve the revised funding:
Thanks
were expressed for the report.
In response to a question regarding the assurance of receiving grants or that grants had been lost due
to slippage, it was highlighted
that some grant terms meant replacement
whilst others gave permission to continue
In response to a question
regarding identifying the risk of an increase
in building costs and the cost of living and for
this to be considered within the application / grant sum, it was noted in general that
it was necessary to receive
some grants and to maximise their use, however,
with others an additional application
was made to the Welsh Government. It was added, in response to an increase in
costs, that decisions were made to defer some
plans.
RESOLVED
To accept the report
To note the relevant risks
To support the Cabinet's decision (14 June 2022)