Dewi A Morgan,
CJC Chief Finance Officer, Dafydd L Edwards, CJC Project Lead Officer and Sian Pugh,
CJC Group Accountant to provide the projected expenditure of the Corporate
Joint Committee for 2022/23.
Decision:
To note and
accept the Corporate Joint Committee's projected expenditure for 2022/23 as
submitted in Appendix 1.
To agree
that the underspend at the end of the financial year will be earmarked to a
reserve fund to finance future one-off costs.
Minutes:
The report was presented by Sian Pugh (CJC Group
Accountant).
DECISION
To note and accept the
Corporate Joint Committee's projected expenditure for 2022/23 as submitted
in Appendix 1. To agree that the underspend at the end of the financial
year
will be earmarked to a reserve fund to finance future one-off costs.
DISCUSSION
The report was submitted
noting that it was a financial review from
September
2022. The main points were highlighted, whilst showing the budget and the
estimated position until the end of the year. It was explained that they were
estimating an underspend of £50k under the Employees heading. It was explained
that the budget had been based on employing / seconding two employees in the
field of Transportation from July 2022 and three
employees
in the Strategic Planning field from December 2022, no appointments had been
made to date. Cyngor Gwynedd's Finance Service had also provided projections
for the costs of the Portfolio Director from October onwards, and the Finance
Service would work with the Ambition Board over the coming months on this.
A likely underspend of £2.5k was
highlighted on the Travelling
heading
as well as a £45k underspend on the supplies and services heading. It was
explained that there was a £1k underspend on the miscellaneous supplies
heading, £4k on the engagement and meetings
heading, and £40k on the external consultations heading.
It was expressed that the net underspend of £3.5k was anticipated
on the Support Services heading. It was noted that there was an overspend of
£10k on finance costs since the role of the Project Lead Officer had continued
for longer than originally anticipated.
An £11k of underspend was highlighted on the Corporate Support heading due to a
reduction in the number of formal meetings.
It was explained that there had been a further delay
with legislating to give section 33 status to Corporate Joint Committees and
that this was now unlikely to be in place until 1 March 2023. It was expressed as
a result of this that it would not be possible
to reclaim VAT on any financial transactions attributed to the previous
period and based on the projected overspend during that period, it was
estimated that around £41k of VAT could not
be
reclaimed.
It was expressed that this would leave a projected
position for 2022/23 as an underspend of approximately £60k that would
be
transferred to a reserve fund.
Observations arising from the discussion
·
Enquiries
were made about the budget and levy of the CJC for 2023/24, noting that serious
consideration should be given to all 2023/24
levies, including the Corporate Joint Committee, because the financial
projections for next year looked so poor. It was noted that a discussion would
be held on the budget when the budget would be created. It was noted that this
report referred to this year's money and that it was difficult to find savings
this year since the budget was the least possible but the need to discuss the
next budget was acknowledged.
·
It
was asked why the money was being earmarked to a reserve fund and it was
explained that the Joint Committee only had one reserve fund and therefore the
money would be earmarked for one-off costs in the future.
Supporting documents: