To eceive the information,
consider the general risks arising from
the savings slippages
Decision:
DECISION:
1.
To accept the report and note the situation
and relevant risks in the context of the Savings Overview
2. To
recommend to the Cabinet that detailed challenge is required on unrealised
schemes – need to ensure regular review of those schemes that are slipping and
refer the schemes to the relevant Scrutiny Committees’ work programme
Minutes:
a) A report was submitted
by the Cabinet Member for Finance, which summarised the Council's savings position. He asked the committee to note the situation and relevant risks
in the context of the Savings Overview and offer observations on the situation for the Cabinet to consider as they approved the report on 25 October
2022. It was also explained
that the departments had presented the savings schemes and that
the finance officers were merely reporting
on the situation.
The Senior Finance Manager
reiterated:
·
Since 2015/16, as part of the Council's financial strategy, savings to the value of £35.4m
had been approved to be realised during the 2015/16 -
2022/23 period. It was noted
that a total of £33.4 million of savings had been realised, which was 94% of the required amount over the period.
·
That the impact
of Covid seemed to have contributed to the slippage in the savings programme in some fields.
·
The main schemes that were
yet to be achieved were schemes those
in the Adults, Health and Well-being Department and the Highways and Municipal Department.
·
That there
was a need, when preparing the 2022/23 budget, to acknowledge that the situation had changed so much that
there was no way to achieve the savings that had been planned originally, and therefore, almost £500k of plans were removed from
the budget and the delivery profile was moved for plans
to the value of £1.3 million
for 2023/24 and subsequent years.
·
That it was inevitable that realising savings to the value of £33.4m (out of a total of £35.4 million) since April 2015, had been challenging. With a delay and
risks to delivering some of the remaining schemes, there was a need to review the plans by the end of the financial year.
Gratitude was expressed for
the report and it was expressed that the positive elements in the report needed
to be congratulated -
b)
During the ensuing
discussion, the following observations were made by members:
·
That 94% of the schemes had been
completed - this was encouraging
·
That the departments
themselves had proposed the
savings and they were not something
that had been forced on them
·
That some
of the schemes were historical
·
That pressure needed to
be placed on those departments that were unable to achieve savings to reconsider plans or plan again
·
That there was a need to
encourage more detailed information - if there was no movement
on schemes, then better schemes
were needed
·
When planning new savings, there was a need to consider elements that were
beyond control - the impact of making cuts today leading
to greater expenditure in the future, e.g. road maintenance
·
Suggestion to highlight
clearly that appendix 4 features slipping savings
·
That savings
schemes needed to be challenged in more detail in the future
·
Eager for plans that were slipping
schemes to be addressed and be scrutinised
c) In response
to a question regarding the
intention to set more ambitious
targets for the departments to contribute to the savings scheme, it was noted that this
will be inevitable and that work
is underway to develop an appropriate procedure. It was reiterated that different processes had been followed to meet the savings to date and that difficult
decisions would need to be made in the future.
In response to a comment regarding a £25,000 slippage (Finance Department - delay to a 'Generating Income through Fraud Prevention' plan), the Head of Finance highlighted that the scheme had been established and staff had been trained in the field, but that
the Covid period had prevented formal interviews from being held and
so the scheme had not commenced. It was reiterated that this was slippage
and not a failure and unless it would
be possible to deliver in the future, then alternative arrangements would need to be considered.
In response to a comment that the waste field was transferring to the Environment Department and whether this
was going to recommence the
process of responding to
the savings scheme, it was noted that the Environment Department was aware of the need to realise the savings and that discussions
had been held between both departments
to ensure that the effort to deal with the financial situation continued.
RESOLVED:
1. To accept
the report and note the situation and relevant risks
in the context of the Savings Overview
2. To recommend
to the Cabinet that detailed
challenge is required on unrealised schemes
- need to ensure regular review of those schemes that
are slipping and refer the schemes
to the relevant Scrutiny Committees' work programme.
Supporting documents: