Application
under Section 73 to vary condition 1 and 3 of planning permission
C16/1164/16/MW (Application under the Environment Act 1995 for the
determination of conditions under periodic review) so as to extend the time for
winning and working of material to 2035, extend time to restore site to 2037
and amend drawings so as to accommodate a proposed extension to extraction area
LOCAL MEMBER: Councillor Beca Roberts
Link
to relevant background documents
Decision:
DECISION: To delegate powers to the Assistant Head of the Environment Department
to approve the application, with conditions relating to the following:
1. Duration of working period 31/12/2035 and restoration up to 31/12/2037.
2. Permitted operations and compliance with submitted
details/plans/drawings (including extension area).
3. Mark boundary of site and mineral extraction zones.
4. Working Hours.
5. Apply to extend the closure and diversion of Public Rights Of Way
numbers 46 and 50.
6. Hours of Working at the working face
7. Method of working and blast limitations
8. Restoration and detailed habitat creation and restoration plan in
accordance with the application details
9. Restoration scheme for the plant site by 31 December 2030.
10. Five yearly review of operations
11. Control of external lighting
12. Control of daytime and night time noise limitations
13. Control of fugitive dust and provision/maintenance of a weather station
14. Soils and storage of restoration materials
15. Restriction on permitted development rights
16. Restriction on vegetation clearance at specific times of the year unless
it can be proven in writing that the work will not disturb birds and reptiles;
17. Updated lichen monitoring
18. Moorland habitat management plan for the ecological compensation area in
accordance with the details provided
19. Long-term monitoring plan of the leat.
20. Gwaen Gynfi
habitat monitoring
21. Archaeological recording and mitigation
22. Protection of nesting birds.
23. Lichen management plan.
24. Reptiles protection measures.
25. Restrict access of livestock to restored areas.
26. Monitoring of invasive species
Minutes:
Breedon, Penrhyn
Quarry, Bethesda, Bangor, Gwynedd, LL57 4YG
Application under Section 73 to vary condition 1 and 3 of planning
permission C16/1164/16/MW (Application under the Environment Act 1995 for the
determination of conditions under periodic review) so as to extend the time for
winning and working of material to 2035, extend time to restore site to 2037
and amend drawings so as to accommodate a proposed extension to extraction area
Attention was drawn to the
late observations form.
a)
The Senior Planning Manager – Minerals, highlighted that this was an application under Section 73 of the 1990 Planning Act
to vary conditions 1 and 3 of planning application C16/1164/16/MW (Review of
Old Mineral Planning Consents under the 1995 Environment Act (ROMP)) to extend
the slate excavation work and associated operations for three years, allow more
time to restore the site and amend plans to make room for a proposed extension
to the area that was currently being worked.
It was explained that the application
site included the quarry as a whole and its operations; excavating for minerals
(including the area of the proposed extension), mineral waste tips, processing,
stockpiling, removal of historical mineral waste tips, site office/welfare
facilities, weighbridge and restored areas. Under this current planning consent
(ROMP), condition 1 stated that all operations could continue up to 31/12/2032,
with the final restoration to be completed by 31/12/2034. The proposed change
to this condition would change the date when operations would cease to
31/12/2035, and the restoration work to be completed by 31/12/2037.
It was noted that the
principle of extending works at the quarry on the site was based on Strategic
Minerals Policy PS22 and Policy MWYN 3 of the LDP where it was noted that the
Council would contribute to the permanent demand locally and regionally for the
supply of minerals by sustaining a land-bank of at least seven years of Sand
and Gravel, and a ten-year reserve land-bank of crushed rock aggregate in
accordance with national guidance.
In the context of traffic
matters, public rights of way and common land, it was reported that the
proposal did not include an intention to increase the HGV movements from the
site. Observations were received from the Council's Transportation Unit, noting
no objection to the proposal since it was unlikely to have any impact on the
highways network.
In addition, it was noted
that the Public Rights of Way Unit had confirmed that a permitted path had been
established and that it followed the path used to transport customers to the
highest zip-wire in Zip World. This path had been agreed with the Council and
it currently was the subject of some work in order to be able to open the path
to the public. Therefore, it was considered that although the original Public
Rights of Way that crossed the quarry had been impacted for a substantial
period of time, the permitted path agreed upon provided a safe access between Llandygai and the slopes that ascended above the quarry. It
was reiterated that steps to secure the closing period and agreement for a
permitted path to coincide with the date of the quarry's cease of operations
were included as conditions on this permission. It was considered that these
steps would be an acceptable method to secure a path for the public and that
the proposal did not cause unacceptable harm to Public Rights of Way in order
to comply with policy TRA of the LDP.
When discussing hydrology and hydro-geology matters,
attention was drawn to the water management methods that were currently being
implemented on the site, which included; drainage and open channels, pumped
drainage, surface water attenuation, stilling lagoons and an interception leat that were implemented as a part of the extension in
2012. It was noted that the leat ran along the
boundary of the quarry void and the boundary of the proposed extension,
capturing surface water and re-directing it to the Gwaun
Gynfi wetland and peat-land.
It was reiterated, although Natural Resources Wales (NRW) had stated that they
accepted the majority of the findings, they were however dubious about the
efficiency of the leat and had therefore stated that
a condition should be imposed on any planning consent to ensure a long-term
monitoring plan.
In the context of the economy, it was noted that the
proposals that the application related to were essential to the company's
future economic contribution. It was
noted that the company made a direct and substantial contribution to the local
economy and direct/indirect employment as a result of the quarry's
operations. In addition, retaining local
workers would have positive impacts on the culture, and more specifically, on
the status of the Welsh language in the area. Therefore, it was considered that
the proposal made a positive contribution to the area's economy in accordance
with Strategic Policy PS 13 of the LDP and TAN 23.
It was considered that the
proposed development complied with all relevant planning policies and
considerations and it was recommended that the planning application should be
approved with appropriate conditions.
b)
The Chair noted that Cllr Beca Roberts (Local Member) had noted in an
e-mail that she was in favour of the proposal
c) It was proposed and seconded
to approve the application in accordance with the recommendations
RESOLVED: To delegate powers to the Head of the
Environment Department to approve the application, with conditions relating to
the following:
1. Duration
of working period 31/12/2035 and restoration up to 31/12/2037.
2. Permitted operations and compliance with submitted
details/plans/drawings (including extension area).
3. Mark
boundary of site and mineral extraction zones.
4. Working
Hours.
5. Apply to extend the closure and diversion of Public Rights Of Way numbers 46 and 50.
6. Hours
of Working at the working face.
7. Method
of working and blast limitations.
8. Restoration and detailed habitat creation and restoration
plan in accordance with the application details.
9. Restoration
scheme for the plant site by 31 December 2035.
10. Five
yearly review of operations.
11. Control
of external lighting.
12. Control
of daytime and night time noise limitations.
13. Control
of fugitive dust and provision/maintenance of a weather station.
14. Soils
and storage of restoration materials.
15. Restriction
on permitted development rights.
16. Restriction on vegetation clearance at specific times of the
year unless it can be proven in writing that the work will not disturb birds
and reptiles.
17. Updated
lichen monitoring.
18. Moorland habitat management plan for the ecological
compensation area in accordance with the details provided.
19. Long-term
monitoring plan of the leat.
20. Gwaun Gynfi habitat monitoring.
21. Archaeological
recording and mitigation
22. Protection
of nesting birds.
23. Lichen
management plan.
24. Reptiles
protection measures.
25. Restrict
access of livestock to restored areas.
26. Monitoring of invasive species.
Supporting documents: