Decision:
To approve increasing the budget for the development
of the new Ysgol Treferthyr to £8,145,206.
To allow the transfer of £3,261,880 from the
remaining budget of the Sustainable Learning Communities Programme envelope
(Band B) in order to meet a significant increase in the costs of the project,
accepting that it will lead to less budget available to realise other projects
within Band B of the Gwynedd Sustainable Learning Communities Programme.
Minutes:
The report was submitted
by Cllr Beca Brown.
DECISION
To approve increasing the budget for the development
of the new Ysgol Treferthyr
to £8,145,206.
The transfer of £3,261,880 from
the remaining budget of the Sustainable Learning Communities Programme envelope
(Band B) in order to
meet a significant increase in the costs of the project was approved, accepting
that it would lead to less budget available to realise other projects within
Band B of the Gwynedd Sustainable Learning Communities Programme.
DISCUSSION
The report was submitted,
noting the steps that had been completed to date as part of the journey of
building a new school in Cricieth,
but there had been a significant increase in the school's construction costs.
It was noted that the report detailed methods of addressing the financial
deficit and sourcing additional
funds. The steps undertaken since May 2021 were highlighted. It was noted that
Welsh Government at that time had approved the funding of a total budget of
£4.9 million for the construction of the School,
and would contribute 65% towards the cost, with the Council contributing 35%.
It was reported that the significant increase in construction costs over the
past 18 months had led to an increase in the cost to just over £8 million due
to factors such as the increasing cost of materials, energy
and inflation.
It was reported that a bid had been submitted
to Welsh Government to increase the budget for funding the School,
and the Cabinet was asked to approve this increase and transfer the budget from
a band B project in order to
address the significant increase in this project's costs. It was added that
transferring the budget would have a consequential impact on the remaining band
B budget, and less budget available to deliver those projects.
Observations arising from the discussion
·
It was also
highlighted that the existing School site was unsuitable. It was noted that the
solution appeared to be
straightforward, although there were implications to be considered.
·
Support was
expressed for the request, and it was noted that other options were scarce.
·
A question was
asked about the specific impacts on band B.
·
In response, it
was noted that the impact would be £1.1 million, a 35% increase to the £3.2
million as the remainder
had already been identified.
This amount would be diverted from other schemes such as the Post-16
budget; this budget would be reduced in order to
accommodate the additional
funding for this scheme.
·
The request was
welcomed on behalf of the children of Cricieth,
and it was believed that the community would be extremely proud of the new
school. An observation was made that Ysgol Eifionydd
was in dire need of investment, and that the Council should pressurise Welsh
Government to improve this School's resources.
·
In response, it
was noted that Ysgol Eifionydd
was part of the Condition and Suitability
Scheme to upgrade and improve conditions and facilities, although it was not a
significant amount.
·
It was believed,
despite the increase in the School's
construction costs, that the Council was getting value for money in Cricieth.
The completion of the project was eagerly awaited, and it was believed that the
investment would benefit the
education of children within Cricieth
catchment area for many years.
Supporting documents: