Decision:
·
That the process of
identifying the savings had been challenging
·
That reasonable steps, under
challenging circumstances, have been taken to draw up the Savings Plan
·
That the savings proposed are
reasonable and achievable
·
That the risks and
implications of the decision are clear
·
That the report is adequate to
enable the Cabinet to make a decision on the entire Savings Plan
·
To
present observations from the discussion on the report to the Cabinet for their
consideration when discussing the 2023/24 Savings in its meeting on 14/2/23
Note:
·
The risk of not achieving
schemes needs to be better highlighted
·
We need to highlight that the
impact of the savings will not have a disproportionate effect across the County
Minutes:
a)
Submitted – the report of
Councillor Dyfrig Siencyn, Council Leader, asking the Committee to consider the
propriety of the process of identifying the savings, and submit observations to
the Cabinet to consider before coming to a decision at their meeting on
14-02-23. It was reported that it was not the Committee's role to express an
opinion on the size of the savings or the features of individual proposals
recommended as savings, but rather to ensure that the Cabinet was clear on the
facts that were presented to it, so that the decisions made were based on
robust information.
When presenting the background to the work, it was noted, despite
receiving a better settlement than projected from the Welsh Government, that
the sum was insufficient to meet costs, and that there was a financial deficit
of £12.4m in order to achieve a balanced budget.
In order to
identify savings, 320 proposals were received from Council Departments (with a
value of approximately £23m). Every proposal had been assessed by the Chief
Executive or by one of the Corporate Directors and they were placed in four
categories to assist Members to prioritise with an awareness of what the level
of risk would be from implementing any individual proposal.
It was
reiterated that a legal assessment and high-level financial assessment had been
completed on every individual scheme in order to
ensure that they were achievable. When submitting their proposals, the
Departments had included an assessment of the impact of each proposal on the
residents of Gwynedd as well as an initial consideration of equality
considerations.
Over a three-day period, every Head of Department had submitted
their proposals to workshops comprising of Cabinet Members, Scrutiny Chairs and
Vice-chairs, as well as the Leaders of the Council's Political Groups.
Throughout the process, the main aim was to seek to identify proposals that
would have the least impact on the residents of Gwynedd should they be implemented.
The outcome of the process was identifying around £6.4m of efficiency savings
that could be implemented.
Considering that the Council was facing a financial deficit of
around £12.4m over the next two years, it was reported that the first phase of
savings (£6.4m) would not be sufficient to address this, and that the proposal
was to revisit the remaining proposals submitted by the departments over the
coming months. Based on the current financial projections, a total of between
£8m and £8.6m would need to be found towards a financial deficit of £12.4m -
between £1.6m and £2.2m would need to be found in additional savings before
setting the 2024/25 budget. It is anticipated that this would push the Council
into the territory of cuts instead of efficiency savings that are recommended
in the report, and the need for more support by the individual Scrutiny
Committees to face this challenge was noted.
The
officer was thanked for the report.
In response to a question regarding how the Adults, Health and
Well-being Department would cope, considering that they have an overspend and
slippage in current savings plans, it was noted that some of the schemes were
now historical and that new plans and ideas were
needed. It was reiterated that current circumstances were very different to the
situation in 2015 and therefore there was a need to consider the situation
realistically. It was noted that a sum for the failure to deliver had been
earmarked.
In response to a question that substantial plans within the Adults,
Health and Well-being Department and the Children's Department had existed for
some time and if the proposals submitted were aspirations (which needed to be
completed in two years!), it was noted that the proposals were more than
aspirations, and that there were no definitive plans at present as business
cases had not been drawn up for every scheme. Consequently, a risk figure would
have to be included. (It was reiterated that the 'Child Placement Plan' was
progressing, with a business case completed and a grant identified).
In response to an observation regarding bridging the deficit to
complete the proposal / plan, and the allegation that this could reduce the
effort of completing within the budget, it was accepted that some schemes were
more complicated than others and that this needed to be highlighted to the
Cabinet.
In response to a question about asking all Departments to offer savings
of 20% and that this had not been realised, it was noted that Schools and some
Corporate Schemes had not had to propose 20% since they were under direct
control.
In response to a comment that there was a need to ensure that the
schemes would not have a harmful impact on work in the future, it was noted,
indeed, that the proposals had not been considered as temporary measures.
In response to an observation regarding giving consideration to
carbon emissions and the need to reach net zero by 2050, it was noted that some
of the revenue savings were climate schemes, e.g. £3m
of solar panels on 80 Council sites.
During
the ensuing discussion, the following observations were made by members:
·
That the process had been thorough
·
That the work had been completed
in an orderly way - every Department had had the opportunity to contribute and that the guidance had been very professional
·
It was good to see that two
years were being considered, and they welcomed savings instead of cuts.
In
response to a question about the process of raising income, it was noted that a number of factors had been considered and that it was not
possible to set the same percentage for every Department since some services
competed with the private sector. It was reiterated that the proposal, in some
departments, such as YGC, was to extend units of work to generate an income. It
was reiterated that an annual income review was being implemented as a part of
setting the budget.
In
response to a question regarding the £1.6m fund for risk and if the usual
accounting practice was to reach this amount or another rationale, it was noted
that a combination of what was accepted in the field of accountancy, project
management and practice had been considered.
It was reiterated that the amount was higher than what had been used in
the past, but that this was a combination of good practice and experience.
In
response to a question regarding equality impact assessments and the
consideration that savings and cuts would have an unbalanced impact across the
County, it was noted that no scheme proposed a specific change in one part of
the County. It was reiterated that there was no intention to offer different
services in different parts of the County, but a warning was given that this
may be a possibility in the second phase. In a supplementary comment, it was
suggested that this needed to be included on the impact assessment form.
The
Leader took the opportunity to give thanks for the valuable comments submitted.
He reiterated that the process had been beneficial and that it should possibly
be considered as an annual process. He
noted that any cut would be likely to affect the County's residents but that
the first phase would not be proposing cuts to services or provisions. The main
aim was to achieve a balanced budget by having the least possible impact on the
residents of Gwynedd.
RESOLVED
·
That the process of identifying
the savings had been challenging
·
That reasonable steps, under challenging circumstances, have been taken to draw up the Savings Plan
·
That the savings proposed
are reasonable and achievable
·
That the risks and implications of the decision are clear
·
That the report is adequate
to enable the Cabinet to make
a decision on the entire Savings Plan
·
To present
observations from the discussion on the report to the Cabinet for its consideration when discussing the 2023/24 Savings in its
meeting on 14/2/23
Note:
·
The risk
of not achieving schemes needs to be better highlighted
·
We need
to highlight that the impact of the savings will not have a disproportionate effect across the County
Supporting documents: