Variation of condition 1 (timeframe to start work) on planning permission C17/0772/36/LL to extend the period for starting the work for a further 5 years
LOCAL
MEMBER: Councillor Stephen Churchman
Decision:
DECISION: To approve with conditions
1. Five years
2. Ensure
that the development is completed in accordance with the plans and documents
submitted in application C17/0772/36/LL together with the amended plan for
diverting the public footpath which was approved in application C18/0168/36/LL
and the Ecological Evaluation Report and the Flood
Consequence Assessment Report submitted with the current application.
3. Finish to be agreed (including the
colour of the fence)
4. Agree on a scheme to dispose of foul and
surface water
5. Agree on a construction environmental
management plan
6. Agree
on a construction traffic management plan and receive the approval of the Welsh
Government's Trunk Roads Unit on access matters (and any relevant additional
conditions).
7. Complete
the landscaping within the first planting season following proposal
completion.
8. Ensure the diversion /safeguarding of
the public footpath.
9. Archaeological conditions.
10. Working hours.
Welsh Water Note and the Water and Environment
Unit at YGC
Minutes:
Vary condition 1
(work commencement period) on planning permission C17/0772/36/LL to extend the
period for commencing the work for a further 5 years
a)
The Development Control Team Leader highlighted that this was an application to vary condition 1 of
planning permission reference C17/0772/36/LL for a new sub-station and
associated infrastructure in order to extend the
development commencement period for an additional 5 years. It was stated that
the substation compound was required to provide space for the single electrical
transformer that would 'reduce' the 400kv voltage of the Pentir-Trawsfynydd
circuit to a voltage of 132kv. When application C17/0772/36/LL had been submitted, the work was
associated with the proposed Wylfa Newydd.
When the plans for Wylfa Newydd fell through, the work associated with
the electricity substation was not undertaken.
By now, the same work was needed to connect to offshore wind farms, so
that they could connect to the wider electricity network.
The application was submitted to the
Committee as it involved a site measuring over 0.5 hectares.
It was explained that the purpose of the
application was to extend the development commencement period for a further
five years, and that there was no proposed change to the plan. It was added
that the principle of this proposal had already been accepted and established
by the Local Planning Authority by means of planning permission C17/0772/36/LL.
The Committee was therefore asked to consider whether the circumstances or the
planning policy situation had changed since the application was originally
approved.
It was noted that Policy ISA 1 was relevant to the
provision of new infrastructure and stated that proposals for water,
electricity, gas services etc. to improve the provision, were permitted subject
to detailed planning considerations. It was added that Strategic Policy PS5 in
the current LDP supported development proposals where it could be shown that
they were consistent with sustainable development principles. In respect of
this development, the obvious need for the proposed sub-station was demonstrated
and although it was located outside any specific development boundaries; the
sub-station had been through the design appraisal process, and the preferred
option was located near the existing 400Kv Pentir - Trawsfynydd overhead line.
In the context of biodiversity, flooding
and drainage matters, it was noted that no objections had been received from
Natural Resources Wales, the Biodiversity Unit of the Water and Environment
Unit of YGC.
It was not considered that the proposal to extend the period of time given under permission number C17/0772/36/LL
for commencing the development was contrary to the relevant local and national
policies or guidance, and the proposal was considered to still be acceptable
subject to the inclusion of relevant conditions as had been imposed on the
previous permissions.
b)
Taking
advantage of the right to speak, the Local Member made the following comments:
·
The plan
was simple and clear
·
The need
for the compound remained
·
No
objections had been received
·
He had
consulted with local residents during the original
application
·
The only
'impact' would be by the main road during the construction work
·
The
Community Council had no objection
c)
It was
proposed and seconded to approve the application.
RESOLVED:
To approve with conditions
1. Five years
2. Ensure
that the development is completed in accordance with the plans and documents
submitted in application C17/0772/36/LL together with the revised plan for
diverting the public footpath which was approved in application C18/0168/36/LL
and the Ecological Evaluation Report and the Flood
Consequence Assessment Report submitted with the current application.
3. Finish to be agreed
(including the colour of the fence)
4. Agree on a scheme to
dispose of foul and surface water
5. Agree on a construction
environmental management plan
6. Agree
on a construction traffic management plan and obtain the approval of the Welsh
Government's Trunk Roads Unit on access matters (and any relevant additional
conditions).
7. Complete
the landscaping within the first planting season following proposal
completion.
8. Ensure the diversion /
safeguarding of the public footpath.
9. Archaeological
conditions.
10. Working hours.
Welsh Water Note and the Water and Environment Unit at YGC
Supporting documents: