Cabinet Member – Councillor Dyfrig Siencyn
To consider
a report on the above.
Decision:
To accept the report and to note the
observations.
Minutes:
The
Leader and Ambition North Wales officers were welcomed to the meeting.
Submitted
– the report of the Leader on the Quarter 3 2022-23 performance of the North
Wales Growth Deal, following the committee's request.
The
Leader outlined the context by providing a brief update on the work of the
Growth Deal, some of the background of establishing the North Wales Economic
Ambition Board, along with details of different schemes that were relevant to
Gwynedd. The Operations Manager then
provided an overview of the Growth Deal and the main highlights of 2022-23.
Members
were given an opportunity to ask questions and offer observations.
It was
enquired how the Ambition Board intended to draw up a language policy for the
Trawsfynydd project to ensure that the development and the workforce would not
Anglicise the area. In response, it was
noted:-
·
That this was a project that wholly relied on UK
Government investment, and that there was no certainty on that.
·
In terms of a language policy, the Egino company would
soon hold a workshop to examine the social benefits, including the linguistic
benefits.
It was
noted that the greatest risk in terms of delivering the objectives of the
Growth Deal was ensuring public and private sector investment, and it was
enquired what steps it intended to take should the capacity of those sectors to
invest reduce over the next few years due to the current financial
situation. In response, it was noted:-
·
That economic circumstances had changed immensely
since the Growth Deal was agreed in 2010, and that the financial crisis was a
challenge that faced us on a regular basis where there was a contribution from
the private sector.
·
The Business Delivery Board, which had representatives
from the private sector, was meeting to discuss projects regularly, under the
guidance of Askar Sheibani, who ran his own global digital business and who was
very enthusiastic for the whole of north Wales.
·
The only assurance that could be given at present was
that this was a matter that was being addressed, and it was believed that there
was a desire among the private sector to invest, provided that the
circumstances were right.
·
The North Wales Ambition Programme Office worked very
closely with the private sector on specific projects, and that the sector was
currently looking to invest.
·
It was acknowledged that there was a risk that the
capacity to invest could change over coming years, and the Programme Office
worked very closely with both Governments on this. More public sector investment would possibly
be required should the private sector investment not be there but, at present,
the situation seemed quite positive.
·
The Programme Office was developing a strategy with
the Business Delivery Board to ensure that it was possible to bring this
strategy forward, and one of the specific things that had been undertaken as
part of the demand for new projects to the £30m fund was to place a strong
emphasis on the ability of businesses to invest as part of this process.
·
This was a large percentage of what the assessment
would be so that it was possible to ensure that any projects coming forward
could proceed quickly to deliver. It was
hoped that this would reduce some of the risks, but the greatest risk to be
able to deliver the benefits of the Growth Deal was bringing the funding
forward to invest in these projects, and this would be a risk during all of the
deal’s period.
It was
suggested that the Growth Deal seemed to be the A55 Deal and it was enquired
whether Meirionnydd would benefit from any schemes, with the exception of the
Trawsfynydd project.
In
response, it was noted:-
·
It was certainly not the A55 Deal and the fundamental
aim was that any wealth generated from the Growth Deal would be shared across
the whole region.
·
Although some schemes were geographical and that a
number of these projects were digital, and that this was essentially important
to rural areas in terms of easy access to digital services.
·
There were no other specific schemes in Meirionnydd
under the Growth Deal, but there were other more local funds that rural areas
could take advantage of, such as the Community Energy Fund.
It was
noted that the Leader would certainly ensure and fight to obtain jobs for
Dwyfor and Meirionnydd and best wishes were extended to every project.
Referring
to the Tracker Table - Overview of delivery (December 2022) on page 32 of the
agenda, a request was made for more details and more certainty regarding
exactly how many jobs had been created thus far.
In
response, it was noted:-
·
That the table indicated the individual targets for
the projects that created the new jobs towards the target of 4,200.
·
The only live project so far was the Digital Signal
Processing Centre, which had led to six new posts in Bangor University.
It was
noted that one of the greatest risks facing the Ambition Board was that project
costs increased and it was enquired how much of the additional funding to this
£30m would be realised in north-west Wales.
It was suggested that there was an opportunity for Gwynedd to propose
innovative projects as a result of withdrawing the Bodelwyddan Key Strategic
Site and the Llysfasi Net Zero Farm projects from the Growth Deal, and it was
enquired whether a discussion was being held about this.
In
response, it was noted:-
·
After the application submission period ended on 27
March, the Programme Office Team would score the projects based on
practicality, how soon they could be implemented and how many jobs would be
created.
·
It was already known that one or two projects would be
submitted for Gwynedd and more would certainly become apparent by the closing date.
·
The method of assessing applications did not refer to
their geographical site. It was hoped
that the projects would span all counties in north Wales, but the tension
between the regional benefit and the locally specific benefit was part of a
difficult discussion that the six Leaders would have to hold in order to reach
some political consensus on the matter.
The fact
that the Bryn Cegin Park Bangor project was finally progressing was welcomed,
but as hopes had been raised so many times during the past twenty years, it was
enquired whether there was now a real plan to attract good jobs to the units
that would be constructed on the site.
It was also enquired whether the entire plan was now at risk in light of
the recent announcement about establishing a Free Port in Holyhead.
In
response, it was noted:-
·
It was frustrating that there had been no development
at Bryn Cegin Park so far, but good progress was being made with the Welsh
Government in terms of the joint venture.
·
The financial risk had been mitigated with provisions
in the agreement that the Welsh Government would make an additional financial
contribution should the construction costs exceed a specific level.
·
The Welsh Government would go out to tender within the
next week to appoint a professional team to lead the work.
·
It was anticipated that there would be planning
permission on the site by the end of the year, with the Final Business Case on
the way to be finally approved by the Board.
·
It was expected that the main contractor would be on
the site by the end of Quarter 1 in 2024, or possibly early in Quarter 2 of
2024, with the construction work being completed towards the end of 2024 or
early in 2025.
·
It was believed that there was considerable demand for
this type of units by local businesses and small and medium enterprises mainly
in the north-west Wales area. It was
believed that there is demand from companies that wished to expand, therefore,
on the whole, many of the jobs that would be created would be high value jobs.
·
It was aimed to create jobs that would offer good
salaries and good training opportunities, with benefits from the construction
work and the jobs created on the site mainly focused in the Bangor area.
·
£6m of Growth Deal funding was being invested in Bryn
Cegin Park but as construction costs had been so unsettled during the past two
years, and to mitigate the financial risk to all partners, it had been provided
in the agreement that the Welsh Government would make an additional
contribution towards capital funding.
·
It was currently difficult to anticipate what impact
the announcement about the Free Port would have, but it was not expected that
this would be a direct threat to existing businesses in the Bangor area, as it
was more likely to affect external investment.
·
Although we had supported the Free Port bid, the
question regarding losing businesses to Anglesey, due to the improved
environment that would be there, was a clear question and a matter that needed
to be monitored.
On a
point of clarity, a request was made for confirmation that the total
expenditure in Bryn Cegin Park was £6m, and that there was no match funding,
with the exception of additions should the costs be more than expected. Also, although it had been noted that it was
not believed that the Free Port would be a threat to existing businesses in
Bangor, there was concern that any new investment would go to Anglesey. It was also asked whether the expenditure
profile of the Growth Deal had been examined and what were the implications for
councils regarding payments to serve any loans that would have to be given.
In
response, it was noted:-
·
That the UK Government would pay over ten years,
rather than over the 15-year period originally agreed. This greatly assists the expenditure profile,
and is a matter that comes up when discussing the finance of the Ambition
Board.
·
£6m was the contribution of the Growth Deal to the
developments in Bryn Cegin Park and one of the greatest risks seen in recent
years was the increase in cost. It was
hoped that those costs were now beginning to settle but it had been a
substantial threat to a number of projects, and this was why additional funding
had to be given to three projects.
·
The expenditure and loans profile of councils was
reviewed annually and there was a number of factors that could affect the
borrowing costs for partners.
·
The costs would be divided between the councils and
other partners, and also the universities and colleges.
·
We were financially benefiting from the situation at
present as there had been a delay in the expenditure profile. The funding that
had come from both Governments was earning interest, which would help with the
risk of increasing costs over the coming years. While moving from a situation
where we have money in the bank to a situation of needing a loan, we would feel
this in terms of higher costs but the situation was currently slightly more
positive than what had been modelled at the beginning of the Growth Deal in
2020 as the funding was received sooner from the UK Government, and due to the
delay and accumulated interest. The situation was being reviewed annually with
the intention, if possible, to keep any borrowing costs for our partners as low
as possible.
Referring
to the Smart Energy Scheme, it was noted that much more investment was needed
in infrastructure before being able to implement such projects.
In
response, it was noted:-
·
It was agreed that the restrictions in terms of the
grid, or costs to connect to the grid, were one of the main obstacles to enable
such schemes to be brought forward.
·
In theory, the investment made here could be used to
provide infrastructure to enable projects to happen in a method similar to what
was being invested in the Morlais Project to support the infrastructure that
enabled the tidal energy to be captured.
It was
enquired to what extent it could be comfortable that the density of jobs
deriving from the Growth Deal would be jobs for local people, rather than
providing opportunities for a population from beyond the area. It was also
suggested that training and career paths needed to be planned on a micro level,
so that we almost examine the careers of individuals here.
In
response, it was noted:-
·
That the indigenous community were full of entrepreneurs
despite the general tendency to think that rural Welsh speakers could not
innovate themselves and be enterprising.
·
There was a need to create the opportunities for those
entrepreneurs to thrive, and from a skills' viewpoint, that this almost came
down to the micro, and was being provided by people who were very local. There
would be no people here to speak Welsh if opportunities were not given to
people. There was a need to be confident for the future and it was hoped that
our indigenous people would seize the available opportunities.
It was
noted that there was no mention of the Ambition Board anywhere, e.g. Business
News of the Daily Post, Golwg, Gwynedd News etc. and it was suggested that
Ambition North Wales needed to do more to market itself to Gwynedd
residents. It was also enquired whether
there was a panel of successful business people objectively examining the
Board's plans to provide a professional opinion on the viability of schemes.
In
response, it was noted:-
·
That the Business Delivery Board challenged the
projects in detail.
·
It was difficult to gather the opinions of micro
businesses and that maybe more innovative ways of contacting those small
businesses should be considered.
At the
end of the discussion, the Leader noted:-
·
That Cyngor Gwynedd accommodated the work of the
Ambition Board, but the work of the Board would soon transfer to the Corporate
Joint Committee, and he greatly hoped that the work of the Board would not be
impaired in any way as a result of that statutory move.
·
The role of Ambition Board Chair was more than
chairing Board meetings only, and that he/she was seen as the representative of
north Wales at regional and national meetings.
The Chair
thanked the Leader and officers noting that everyone was pleased to see some of
the projects beginning and coming to fruition.
He also noted that it would be interesting to see what new projects
would be submitted before the Programme Management Team next week, and he
expressed his hope that there would be schemes of benefit to Gwynedd, and to
South Meirionnydd.
RESOLVED to accept the report and to note the
observations.
Supporting documents: