Hedd Vaughan-Evans
(Head of Operations) to present the report.
Decision:
1.
That the Board approve the
streamlined approval route for Full Business Cases (FBC) as set out in
Paragraph 4.10 of this report where:
Ø There
has been no change in the scope of the project since the approved Outline
Business Case (OBC) or any subsequent change request that was approved.
Ø Spending
objectives targets (e.g. jobs) have not reduced by more than a 10% tolerance
since the approved Outline Business Case (OBC) or any subsequent change request
that was approved by the Board.
Ø There
is no additional financial ask of the North Wales Growth Deal since the approved
Outline Business Case (OBC) or any subsequent change request that was approved
by the Board.
Ø No
further delegated authority is required from the Board.
2.
In all other cases the normal FBC approval process would apply.
Minutes:
The report was submitted by Alwen Williams
(Portfolio Director).
RESOLVED
1.
That the Board
approve the streamlined approval route for Full Business Cases (FBC) as set out
in Paragraph 4.10 of this report where:
Ø There has been no change in the scope of the
project since the approved Outline Business Case (OBC) or any subsequent change
request that was approved.
Ø Spending objectives targets (e.g. jobs) have
not reduced by more than a 10% tolerance since the approved Outline Business
Case (OBC) or any subsequent change request that was approved by the Board.
Ø There is no additional financial ask of the
North Wales Growth Deal since the approved Outline Business Case (OBC) or any
subsequent change request that was approved by the Board.
Ø No further delegated authority is required
from the Board.
2.
In all other
cases the normal FBC approval process would apply.
REASONS FOR THE
DECISION
To set out a proposal to streamline the approval process for Full
Business Cases (FBC) to ensure final investment decisions by the Board can be
made in a timely and effective manner.
DISCUSSION
In response to a request for an explanation of the 10%
tolerance in the second bullet point of recommendation 1, it was explained that
the tolerance was set to recognise that there were usually minor changes as
projects went through this process, particularly through procurement, and that
10% was generally recognised as a logical and proportional reduction that
provided flexibility, yet not a substantial figure. As such, if 1 or 2 jobs changed during the
process, that wouldn't necessarily mean having to restart the process.
It was asked whether the refined process would apply
to projects currently undergoing the Final Business Case (FBC) development
process, and whether the new regime would be operational immediately.
In response, it was noted that it was intended to
implement this immediately, if the Board agreed with the recommendation, so it
would apply to projects that were in the process of developing a Final Business
Case (FBC). It was also explained that
the refined process would benefit those projects as delays could mean cost
increases.
In response to a comment regarding transparency and
the Board's accountability, it was made clear that the refined process involved
streamlining the back office assurance functions that took place before
bringing business cases to the Board, and could take several months. It was added that this would not happen in
all cases, however.
It was asked whether there were real-world examples of
cases where the reduction in the amount of time tender prices were valid led to
a situation of having to re-procure.
In response, it was noted:-
·
That
this had not happened within the Growth Deal itself, but that our partners had
expressed concern that they had live projects where the tender prices were only
valid for a maximum of 30 days, or 60 days, and therefore there was no time to
go through the assurance and project approval process before the tender price
expired.
·
If
a project could not be approved in time, there was a risk that the partners and
project sponsors would either go back to their contractor of choice, which
would mean cost increases, or in the worst-case scenario, re-procurement.
·
While
the Growth Deal had yet to experience this, we were not far from having to face
those challenges ourselves as projects neared Final Business Case approval.
Bangor University's Digital Signal Processing Project
(DSP) was cited as an example of a project that came to within days of the
tender price expiring, and the Engineering Centre at Coleg Llandrillo's Rhyl
campus, as an example of a scheme where it had to re-tender at an additional
cost of £1m, as a result of the Welsh Government's failure to approve the final
project quickly enough.
It was suggested that the Business Delivery Board
should be involved in assessing projects as that would create more credibility
from a private sector perspective, and would not add to the timetable.
In response, it was noted:-
·
That
the Business Delivery Board had a key role in the approval process of Outline
Business Cases as they made recommendations to the Ambition Board.
·
That
the report did not fully consider the role of the Business Delivery Board in
the process of approving Final Business Cases, which could be discussed further
with their representative on this Board.
·
That
adding more meetings to the process added to the schedule, but if the Business
Delivery Board and Ambition Board meetings could be effectively aligned, then
it should be possible to include both, without extending the timetable.
It was suggested that the Business Delivery Board
could be consulted over email, rather than holding formal meetings, and
therefore everyone would still feel included.
We agreed to hold a conversation with the Business
Delivery Board representative to see how best to engage with the body.
Supporting documents: