Full planning
application for the erection of 30 affordable dwellings with a new access,
internal access road and associated works.
LOCAL MEMBERS:
Councillor Sasha Williams and Councillor Iwan Huws
Link
to relevant background documents
Decision:
DECISION: To
delegate powers to the Head of Environment Department to approve the application,
subject to ensuring an acceptable solution regarding archaeological matters and
a 106 agreement for a play area and educational contribution and conditions
relating to the following:
·
Commence
within five years
·
Development to
comply with the approved plans
·
Must submit and
agree on a programme for providing affordable housing
·
Must agree on
external materials including the roofing slates
·
Removal of permitted
development rights
·
Welsh Water
Condition
·
Highways Conditions
·
Biodiversity conditions
·
Need to submit an Environmental Management Plan
prior to commencing work on the development
·
A Welsh name for the
housing estate and individual houses.
·
Restrict the use to
C3 use class only
·
Archaeology
conditions
Note – Welsh Water
Land Drainage Unit
Transportation
Unit
Major
development
Minutes:
Full planning application to erect 30 affordable
dwellings with a new access, internal access road and associated works.
Attention was drawn to the late observations
form that proposed additional information regarding Educational Contribution
matters, Linguistic Matters, Biodiversity, Trees, and Archaeology matters.
a)
The Development Control
Team Leader highlighted, that it was a full application to erect 30 affordable
dwellings with associated works on the site designated under T57 as a site for
housing within the Bethel Service Village development boundary as defined by
the Local Development Plan (LDP). It was explained that the site was located
within the Dinorwig Landscape of Outstanding Historic
Interest and abutted the Pen-yr-Orsedd designated
Wildlife Site which was distinctive for its acidic grassland, marshy grassland,
and acid/neutral wetland. The proposal included erecting the houses, providing
new access to the B4366 (which is a class 2 road), creating an internal access
road, landscaped areas and associated drainage work;
the proposal would include a housing mix:
·
3 two-bedroom bungalows
·
1 three-bedroom wheelchair-accessible bungalow
·
8 two-bedroom houses
·
12 three-bedroom houses
·
2 four-bedroom houses
·
4 one-bedroom flats
In the context of the development’s principle,
it was noted, in accordance with Policy PCYFF 1 ('Development Boundaries') that
proposals would be approved within development boundaries in accordance with
the other policies and proposals in the Plan, national planning policies and
other material planning considerations.
It was highlighted that Bethel, in the LDP, was identified as a Service
Village under policy TAI 4 which supported housing to meet the Plan's strategy
through housing allocations and suitable unallocated sites within the
development boundary based on the indicative provision within the Policy.
It was reported, in accordance with Policy TAI
8, that consideration should be given to the proposed development and whether
it met the demand for housing recorded in a Market Housing Assessment and other
relevant local sources of evidence. It was noted that a Housing Mix Statement
was submitted with the application noting the reasoning behind the housing mix
proposed, and confirmation was received from the Housing Strategic Unit
confirming that the development met the recognised local community needs. It
was reiterated that Policy TAI 15 of the LDP stated that Councils would attempt
to ensure an appropriate level of affordable houses in the plan area. In
Bethel, the threshold was two or more housing units, but as the proposal
prepared 100% affordable units and that the Housing Strategic Unit confirmed
that the proposal met the need in the area, the application satisfied policy
TAI 15. As a result, it was considered that there was justification and need
for the proposal and that it would address the needs of the local community and
realise the objectives of the LDP housing policies.
In the context of the
location, design and visual impact of the proposal, it
was noted that it would form a logical extension to the village, and that the
layout, design and materials of the proposed development would be in-keeping
with the location in an appropriate way. It was considered that the houses had
been designed to a standard quality that suited the nature of the village
without causing significant harm to the site’s-built quality or the local
neighbourhood. As a result, it was considered that the development was
acceptable under Policies PCYFF 2 and PCYFF 3 of the LDP. In addition, although
the site was located within the Landscape of Outstanding Historic Interest, it
was not considered that the proposed development would have any detrimental
effect on the wider historic landscape; the application therefore was
consistent with the objectives of policy AT1 in the LDP.
In the context of transportation and access,
subject to appropriate conditions, the parking and vehicular access were
acceptable by the Transportation Unit, and it was not considered that the
traffic caused by the new development would increase the risk for road users in
a significant manner. In terms of biodiversity and tree matters, an initial
Ecological Assessment and Arboriculture Assessment of the site were submitted.
It was noted that the reports were acceptable by the Biodiversity Unit and were
subject to the acceptable appropriate conditions of the development under
PolicyPS19 of the LDP.
In the context of open spaces, it was
highlighted that the applicant had noted that the area designated as an open
space, was proposed to be used for dealing with sustainable drainage
requirements and therefore wasn't suitable for play equipment. It was
reiterated that another area was also considered unsuitable due to high voltage
electricity cables running above the site and in close
proximity to a neighbouring house. It was highlighted that the current
play area was within 60m of the site and the applicant was willing to
contribute a sum of £5240.00 for improving the facilities and access to that
area, with a planning obligation under Section 106 of the Town and Country
Planning Act 1990.
In the context of financial matters, it was
noted that there was not enough space in the local Secondary School to cope
with the proposal, therefore, in accordance with policy ISA 1 the financial
contribution of £123,028.50 was proposed, through agreement 106, to improve
secondary education provision.
When discussing linguistic matters, it was noted
that a Language Statement was submitted with the application which concluded
that the proposed development would generally have a neutral impact on the
Welsh language and the community in Bethel, by providing 100% affordable
housing which meets the needs found, at a price that was affordable for local
people.
It was considered that the proposal for
developing affordable housing was designed to meet the local housing market
needs and located on a site designated for housing within the village's
development boundary; the plan was acceptable on the grounds of principle and
that it complied with relevant local and national planning policies.
b)
Taking advantage of the right to speak, the
applicant’s agent made the following observations;
·
That the site was
designated for 28 houses, but the developer’s intention was to build 30 which
made better use of the land
·
That all the homes were
affordable housing - this was a higher offer than the Policy requirements
·
Local Need for 2, 3 and 4 bed housing had been evidenced
·
Suitable mixture of housing within the plan that
responded to the need
·
Language Statement submitted with the application
·
Although there was a
request for internal bird nesting boxes, it was noted that providing external
ones was sufficient
·
Despite the request from the Ecology Department
to install an ecology buffer of 10m, that 3m was sufficient or some plots would
lose garden space
·
The additional
archaeology work was provided and that trial trenching
work had been undertaken on the site
·
A contribution was
agreed for the secondary school provision
·
The proposal was
acceptable and complied with local and national policies
c)
It was proposed and seconded to approve the application
ch) During the ensuing discussion, the following observations were
made by members:
·
The Community Council’s
observation for assurance that local, Welsh families would be allowed to live
in the houses in order to protect the language in the village was supported
·
That the development was a large one
·
That lack of response from six consultees was
concerning in considering the size of the proposal
·
That there was a need
to keep an eye on Welsh Water's observation
·
That the amount for the
open space equipment seemed low
·
Welcomed affordable
houses and homes for the people of Gwynedd
·
That the development was a very important one -
which met the need for local housing
In response to the observations, the Assistant
Head of Planning noted that the plot of land was designated for housing in the
LDP and therefore the principle was already established. It was reiterated that
the policies try and ensure that the appropriate level of affordable housing is
built in the plan area; here we can see 100% of affordable housing (not 30% as
expected) being built which also corresponded with one of the Council’s main
priorities. It was noted that neither Welsh Water nor the Transportation Unit
had objected to the application and that the contribution to provide play
equipment was made by using the Fields in Trust benchmark standard (formula).
In response to an observation that work had
previously commenced on the site, the Assistant Head of Planning noted that
machinery was on the field as trial trenching work was being undertaken to
identify any archaeological interest on the site. In terms of commencing the
work, a standard condition would note the need for the work to commence within
5 years and it was presumed that the development would be bound by grant
requirements.
RESOLVED: To
delegate powers to the Head of Environment Department to approve the
application, subject to ensuring an acceptable solution regarding
archaeological matters and a 106 agreement for a play area and an educational
contribution and conditions relating to the following:
1. Commencement within five years
2. Development to comply with the approved plans
3. Affordable homes provision programme must be submitted and agreed
4. External materials, including the roofing slates, must be agreed
5. Removal of permitted development rights
6. Welsh Water condition
7. Highways conditions
8. Biodiversity conditions
9. A Construction Environmental Management Plan needed to be submitted prior
to the development work commencing
10. A Welsh name for the housing estate and individual houses
11. Restrict the use to C3 use class only
12. Archaeology conditions
Note - Welsh Water
Land Drainage Unit
Transportation Unit
Major development
Supporting documents: