Application to
amend condition 1 of planning permission reference C21/0934/15/AC for
installation of underground 132KV grid connection cables between the Glyn
Rhonwy Storage Facility and Pentir Substation so as to extend the development
commencement period for an additional 2 years.
Local Members: Councillors Kim Jones, Elfed Williams, Menna Baines, Elwyn
Jones,
Sasha Williams, Iwan Huws and Berwyn Parry Jones
Decision:
DECISION:
To delegate powers to the Senior Planning Manager to approve the
application subject to the following conditions:
1.
5 years
2.
Complete the development in accordance with the
conditions attached to permission C16/0886/15/LL and any details agreed through
the condition release requests.
Minutes:
Application to amend condition 1 of planning
permission reference C21/0934/15/AC for the installation of underground 132kV
grid connection cables between the Glyn Rhonwy Pumped
Storage Facility and Pentir Substation to extend the
development commencement period for an additional 2 years.
Attention was drawn to the late observations
form which included an update to the relevant planning history.
The Development Control Team Leader highlighted
that an application to amend the condition relating to the commencement period
of the development was granted in January 2022 under reference C21/0934/15/AC
so as to provide an additional two years, i.e. until
10/1/2024.
It was explained that the principle of the
development of installing an underground cable to connect the Glyn Rhonwy pumped storage generating station with the Pentir substation had already been established by the Local
Planning Authority by means of planning permission C16/0886/15/LL and the application
before them involved extending the development's operating period by an
additional 2 years by amending condition 1 of application C21/0934/15/AC. It was confirmed that there were no changes
to the plan and that the process of releasing conditions associated with the
original planning permission continued. However, the importance of considering
whether local and national planning policy circumstances or the policy position
had changed since the application was originally granted was highlighted. Only if there was evidence of a significant
change in position could the proposal be considered differently in the context
of local relevant policies relating to the acceptability of the principle of
this latest application - Policy ISA 1 'Infrastructure Provision' and policy PS
7 'Renewable Technology'. Policy ISA 1 of the Local Development Plan (LDP)
states
It was reported that the proposed cable path
runs through the 'North-Western Fringes of Snowdonia' Special Landscape Area,
the 'Dinorwig' Landscape of Outstanding Historic
Interest and borders the 'North-West Wales Slate Landscape' World Heritage
Site; the intention was to lay an underground cable in line with the guidance
in policy PS 7.
It was reiterated that the principle of creating
a pumped storage generating station at Glyn Rhonwy
quarry had already been accepted and approved by the Secretary of State for
Business, Energy and Industrial Strategy granting a Development Consent Order
in 2017. Permission for a non-material amendment to the Development Consent
Order was granted by Welsh Ministers to extend the operational period. The work
of creating a grid connection could usually be considered as an Associated
Development but here in Wales it could not be approved as part of the process;
therefore, a separate formal application for permission must be submitted in
line with the Planning Act. The
principle was deemed acceptable and that this element
was a necessary follow-up step to the planning permission already granted by
ensuring a link between the electricity generating site and the distribution
site.
In the context of visual, general
and residential amenities it was accepted that this type of work, particularly
given that it would be undertaken on the verges of busy public roads, would be
likely to affect local amenities and the amenities of residents living close to
the path and those affected directly should it cross a section of private land.
It is also likely to occasionally have an impact when traffic control needs to
be installed when working on more restricted/narrow sections.
Although there was no objection from the
Transportation Unit, it was highlighted that the developer needed to submit
applications for relevant permits to carry out the work within highway lands.
This will ensure that the restoration work is carried out to appropriate
standards.
When considering biodiversity issues, it was
noted that a revised Initial Ecological Assessment Report had been submitted
with the application and in response to the statutory consultation period the
Council's Biodiversity Unit had no objection to the application although
excavation work under afon Rhyddallt
meant that it would cross a section of the Llyn Padarn Site of Special
Scientific Interest.
In the context of archaeological and heritage
issues, it was highlighted that CADW had stated that while there would be
potential for temporary impacts on the setting of the World Heritage Site, it
was considered that this would not be significant, and the Gwynedd
Archaeological Planning Service (GCAG) had confirmed that the application would
not have an impact on archaeological matters (in accordance with its
observations on the original application).
In accordance with the instructions in appendix
5 of the Supplementary Planning Guidance (SPG): Maintaining and Creating
Distinctive and Sustainable Communities, the applicant had concluded that a
'Welsh Language Statement' was not required. It was therefore
considered that the proposal continued to be in accordance with policy PS 1 and
would not cause harm to the Welsh language.
Having considered all the relevant matters, it was not considered that the proposal of extending the
time given under permission number C21/0934/15/AC to commence the development
was contrary to the relevant local and national policies or guidance. It was
considered that the proposal continued to be acceptable subject to including
relevant conditions as included within the previous planning permissions. The
observations objecting to the proposal were acknowledged regarding the delay in
commencing the work, but having fully assessed the proposal, there was no valid
planning reason to reject the application.
The Local Members (Councillors Kim Jones, Elfed
Williams, Menna Baines, Elwyn Jones, Sasha Williams, Iwan Huws and Berwyn Parry
Jones) highlighted via emails, that they agreed with the recommendation, and
although the work caused temporary inconvenience, undergrounding was the best
option.
It was proposed and seconded to approve the
application.
To delegate powers to the Senior Planning Manager to
approve the application subject to the following conditions:
1. 5
years
2. Complete
the development in accordance with the conditions attached to permission
C16/0886/15/LL and any details agreed through the condition release requests.
Supporting documents: