Dylan J
Williams (North Wales Councils’ Lead Chief Executive for the Economic
Ambition Board) to present the report.
Decision:
1. To
note the progress update on work to establish the North Wales CJC and to
respond to the tasks required by its statutory functions.
2. To
note the updated plan and revised timetable for the transfer of the North Wales
Growth Deal to the North Wales CJC.
3. To
approve the extension of the temporary arrangement to release the Portfolio
Director’s time for two days per week to undertake the Interim Chief Executive
role until 31 October 2024.
4. To
agree that a further report would be submitted to the Board should there be a
slippage in the timetable, in order to seek the approval of the Members for an
alternative timetable to transfer the North Wales Growth Deal to the North
Wales CJC.
Minutes:
The report was presented by the Chief Executive of the
Isle of Anglesey County Council.
RESOLVED
1. To
note the progress update on work to establish the North Wales CJC and to
respond to the tasks required by its statutory functions.
2.
To note the updated plan and
revised timetable for the transfer of the North Wales Growth Deal to the North
Wales CJC.
3.
To approve the extension of
the temporary arrangement to release the Portfolio Director’s time for two days
per week to undertake the Interim Chief Executive role until 31 October 2024.
4.
To agree that a further
report would be submitted to the Board should there be a slippage in the
timetable, in order to seek the approval of the
Members for an alternative timetable to transfer the North Wales Growth Deal to
the North Wales CJC.
REASONS FOR THE
DECISION
In December 2021/January 2022, the
Cabinet and Executives in each of the six Local Authorities agreed, in
principle, that the functions of the North Wales Economic Ambition Board should
be transferred by way of a delegation agreement to the CJC. The statutory
framework and the establishment of the CJC meant that the proposed transfer
needed to be progressed. Approval from partner organisations and governments
was required before a transfer could take place.
The 1st July had been identified as the provisional
target date to transfer functions from the Economic Ambition Board to the North
Wales Corporate Joint Committee. However, this date was provisional on the
grounds that it could be affected by several factors, including the need for
partner and government agreement to transfer the Growth Deal; Decision and
timetable requirements; Internal capacity limitations and TUPE considerations.
Key decisions needed to be made to complete the transfer which could lead to some
transfer areas being carried out during the autumn 2024 period. Consideration
was given to whether the proposed transfer date of 1 July 2024 was achievable.
This report and the decisions required set out the revised plan and timetables.
All the officers associated from Ambition North Wales
and the Host Authority were thanked for their work in preparing a clear report
of the current situation. It was acknowledged that it was not an ideal
situation, noting that the Report detailed those challenges that had
contributed towards the current situation. It was also elaborated that
officers' capacity had contributed to the challenges faced.
Attention was drawn to the complexity of the tasks
that needed to be completed, as well as the key arrangement of when all the
tasks should be completed. Details were given on this information by referring
to Appendix 1. Examples of the detail of the tasks were shared by confirming
that all of the region's local authorities and the
Government needed to agree on each step of the processes, as well as develop
robust processes and policies. It was acknowledged that ambiguity regarding
financial matters was also a challenge that had been faced recently. The need
to ensure that each task had been completed and that sufficient processes were
in place before the formal transfer was made, to ensure a reduction in future
risks, was emphasised. It was confirmed that it was key to adapt the date of
the transfer from July to November, with the hope that all processes would be
in place by then.
In response to an enquiry, it was confirmed that it
was not possible to ensure that a transfer would be in place by the end of
October 2024 because there was a possibility that unforeseen matters would
affect the development of those necessary processes, and it was acknowledged
that officers had received criticism for missing deadlines on this subject in
the past. Following a short discussion, it was confirmed that a report would be
presented to the Members, if the need to extend the date of the transfer arose,
noting the reasons why the date of the transfer had slipped. However, it was
emphasised that officers were confident that the target set in the report was
achievable.
It was considered that no detailed discussions had
been currently held with the private sector, in connection with the transfer.
It was ensured that this transfer was an opportunity to develop an innovative
relationship with the private sector for the future, emphasising that the link
with the private sector was essential for success. It was ensured that the role
of the private sector and advisers within the new joint committee would get
continuous attention from officers.
Members expressed their wishes regarding how the
Shared Prosperity Funding would be allocated in the future, following the
general election. Members were reminded that it would come to an end at the end
of March 2025, and any further continuation would depend on the new political
developments.
Supporting documents: