• Calendar
  • Committees
  • Community Councils
  • Consultations
  • Decisions
  • Election results
  • ePetitions
  • Forthcoming Decisions
  • Forward Plans
  • Library
  • Meetings
  • Outside bodies
  • Search documents
  • Subscribe to updates
  • Your councillors
  • Your MPs
  • Your MEPs
  • What's new
  • Agenda item

    REPORT BY NETWORK RAIL

    • Meeting of Cambrian Coast Railway Liaison Committee, Friday, 20th May, 2016 1.00 pm (Item 7.)

    To receive a report by Mr Dylan Bowen, Network Rail.

    Minutes:

    Sam Hadley, Public Affairs Manager and Sian Lewis, Commercial Scheme Sponsor (Network Rail), were welcomed to the meeting.

     

    (A)         Sam Hadley explained that he would be attending the meetings of this committee in future and Members were encouraged to contact him directly with any matters of concern.  He responded to the formal questions submitted and noted as follows:

     

    (a)          Talwrn Bach, Llanbedr level crossing - what is the latest regarding the installation of bars on the level crossing bearing in mind that transport increases over this crossing daily and there would be even more transport as the village hall is re-located (temporarily) to the airfield site.

     

    Several members supported the same concerns as Councillor Annwen Hughes, local member for Llanbedr, and that it was a matter that had been raised by this committee for many years and that there was a real need to solve the matter once and for all.   

     

     

    In response, it was explained that a site inspection would be undertaken at the end of the year and it was promised that the Member Support Officer would be informed and that a comprehensive report would be submitted as well as a development timetable.   

     

     

    (b)          Litter on the railway in the Cricieth area, specifically on the eastern side of the town from Black Rock to Morannedd.

    (c)          A number of trees and shrubs had overgrown along the railway - what were Network Rail's plans to cut/manage growth and to eradicate Japanese Knotweed?

     

    In response, it was explained that Network Rail was getting rid of litter but there was a need to prioritise e.g. there was currently a huge clear-up project in Flintshire in light of the fact that the Urdd National Eisteddfod had been held there with the local authority providing skips and staff to assist. 

     

    In terms of a vegetation programme, if any growth was problematic it was confirmed that it would be prioritised.  In terms of Japanese Knotweed, Network Rail had a legal responsibility to get rid of it if it spread on third party land. The local member was asked to provide details of specific locations where Japanese Knotweed was problematic and it would be followed up without delay.

     

    (ch) Litter between Penychain and Pwllheli.

     

    Again, the officer confirmed that he would deal with the above and that Network Rail was much more responsive in north Wales and any collaboration with local Councils was welcomed.

     

    Resolved:       (a) To thank the officer for the response and to ask him to follow-up without delay.

     

                            (b) That Councillor Eirwyn Williams provided details of specific locations where Japanese Knotweed was spreading on third party land so that the Operational Maintenance Co-ordinator could address the problem. 

     

     

    (B)         A presentation in the form of a slide-show was received from Sian Lewis, Commercial Scheme Sponsor (Network Rail), on the background of the Barmouth Viaduct, the work so far, the scope of the work programme as well as risks and challenges associated with the repair work on an iconic listed (Grade II) viaduct.  

     

    Work undertaken to date was outlined namely:

     

    ·         Site visits during summer 2015 to determine the current condition of the viaduct

    ·         Production of a report of high level options for metallic and timber structures

    ·         Meeting with stakeholders such as the Barmouth Viaduct Access Group (B-VAG)

    ·         Meetings with CADW, Gwynedd Council and Snowdonia National Park

     

    It was noted that the work had been divided into two parts namely Urgent Work and Development Work and the scope of the work was outlined as follows:

     

    Urgent Work:

     

    ·         Development plan to undertake repairs on the steel structure

    ·         Work included replacing rivets and other similar materials

    ·         An initial design was expected by the end of May

    ·         It was aimed for it to be submitted to CADW and local authorities in June / July

    ·         Approval of initial design during the summer

    ·         Detailed design to be developed in October 2016

    ·         Commence on the site in Spring 2017

     

    Development Work:

     

    ·         Develop and produce an options report during the summer

    ·         Submit it to CADW and local authorities in September 2016

    ·         Further meetings with CADW and local authorities were anticipated during the Autumn to agree on a preferred option, and it was hoped that it would be held by the end of the year.

    ·         Currently, it was estimated that the design would take a year or more due to the sensitive nature of the structure.

    ·         Actual work on the site to follow sometime in 2018

    ·         Each one of the above would depend on the initial design stages and on consultation with the stakeholders

     

    In the context of the challenges faced, it was noted that these would include:

     

    ·         Consulting with the stakeholders

    ·         Permissions / conditions for a listed structure

    ·         Ecological / environmental requirements

    ·         Unsure of the duration of the work and how much disturbance it would cause on the railway

     

     

    Members were given an opportunity to ask questions to the officer and the following points were highlighted:

     

    (a)  An appeal was made by the Chairman and the Member of Parliament - Dwyfor/Meirionnydd to be realistic with the work programme bearing in mind the previous difficulties with the delay that derived from repair work on Briwet Bridge, Penrhyndeudraeth and it was hoped that lessons had been learnt from this.  Also, the importance of collaboration with Arriva Trains Wales was noted and an appeal was made for Network Rail to do so.  

    (b)  Importance of informing the public of what is taking place

    (c)  Assurance was requested that the footpath near the bridge would remain open and collaboration with Gwynedd Council was encouraged to this end.

    (d)  The A496 was a very busy highway and dangerous in light of the number of accidents that had occurred recently and that a 40 m.p.h speed limit for the road should be considered. Should there be an accident on the road in question, this would mean having to divert passengers for approximately 60 miles.

     

    Resolved:       To accept, note and thank the officer for the presentation