Application under Section 73 to vary condition 2 on planning permission 5/59/500 (Extension of Slate Quarry and Realignment of Quarry Roads) so as to extend the time for the winning and working of material to 2048 at Cwt y Bugail Quarry, Cwm Teigl, Llan Ffestiniog
LOCAL MEMBER: Councillor Linda Ann Jones
Decision:
To delegate powers to the Assistant Head of the Environment Department
to approve the application, with conditions relating to the following:
·
The work to come to an
end on 31/12/2048, restore the site by 31/12/2049.
·
Permitted activities
and compliance with the submitted drawing / details / plans / information.
·
Mark the boundary of
the site and mineral extraction zones and tipping areas.
·
Revoke GPDO Part 19
& 21 rights for fixed plant or machinery, buildings and structures and
mineral waste.
·
15,000 tonnes per annum
export limit.
·
Exported material
restricted to existing public highway.
·
Tipping operations to
be directed towards final landform.
·
Updated tipping
capacity.
·
Control of noise
limitations.
·
Restrict blasting 07:00
to 20:00 Monday to Saturday. No blasting on Sundays, bank holidays or public
holidays.
·
Peak particle velocity restricted
to 50mm/s for 95% of overburden blasts over a three-month period and not exceed
60mm/s at any time.”
·
Peak particle velocity
must be measured at the closest point to the blast site within the shaded area
shown in Drawing Reference WCYBG2312 Drawing No.10
·
Monitoring of blasting
operations to record peak particle velocity.
·
Five yearly reviews of
operations.
·
Submit the first report
within 12 months.
·
Detailed Restoration
Plan.
·
Phased/progressive
restoration works.
·
5-year
aftercare/monitoring.
·
Scheme of landform
remodelling shall be applied to North Pole Quarry benches and associated faces
as indicated on plans for creation of stable landform and features to match
surrounding rock buttresses and scree.
·
Following cessation of
works, clearance of quarry plant/machinery/materials/equipment to be cleared
and site to be left in clean/tidy condition, quarry benches prepared, treated
and planted with flora of local provenances, haul roads to be removed.
·
Restrict access of
livestock to restored areas.
·
No plant or machinery
to be operated without appropriate and properly maintained sound deadening
screens, silencers etc.
·
All vehicles
transporting raw material or waste shall be operated in a manner not to
generate excessive noise.
·
No operations to cause raising
of fugitive dust and all areas traversed by vehicles to be watered down.
·
Removal of vegetation,
structural repair or demolition of buildings and working of previously
stripped/quarried/tipped areas shall be undertaken outside of nesting season
for the protection of nesting birds. Qualified ecologist
·
No operations to be
undertaken on surface without stripping and storage of topsoils,
subsoils, and peat.
·
Topsoils and subsoils to be
re-used as soon as possible (In restoration).
·
Topsoils to be stored in mounds
not exceeding 2m in height.
·
Historic building
recording of the art storage facilities and Written Scheme of Investigation.
·
Monitoring and eradication plan of
non-native/invasive species.
Minutes:
An application under Section 73 to vary condition 2 on planning
permission 5/59/500 (Extension of Slate Quarry and Realignment of Quarry Roads)
so as to extend the time for the winning and working of material to 2048 at Cwt y
Bugail Quarry, Cwm Teigl, Llan Ffestiniog
Attention was drawn to the late observations form
which contained observations relating to heritage and transport.
a) The Senior Planning Officer - Minerals and Waste noted that Cwt y Bugail Quarry was located on the Manod
Mawr ridge and comprised the quarries of
Manod, Graig Ddu and Bwlch y Slater. It was reported that
the quarry includes a processing and stocking area located on a plateau
(created with tipped slate waste) on the eastern slopes of the mountain. The
processing area includes cutting sheds, stocking area, fitting sheds, staff car
park, office, and welfare facilities.
For clarity, it was added that the quarry processing area, cutting sheds,
workshops, staff car park and other associated infrastructure to the east of
the quarry void were not included within planning permission 5/59/500. However,
the related Section 106 Agreement was relevant to the whole site and ensured
that restoration proposals were implemented.
It was explained that the accumulated area of
the quarry works (included in the planning application) exceeded 25ha,
therefore exceed the threshold of Schedule 1 developments under The Town and Country
Planning (Environmental Impact Assessments) Regulations 2017. An Environmental
Statement (ES) was submitted as part of an Environmental Impact Assessment
(EIA) in response to this requirement.
In the context of the principle of the development, it was noted that
the current relevant local planning policies were Strategic Minerals Policy P22
and Policy MWYN 3 in the Anglesey and Gwynedd Joint Local Development Plan 2011
(LDP). Policy PS 22 stated that the Council would contribute to the permanent
demand locally and regionally for the supply of minerals in accordance with the
key objectives of sustainable development. It was also noted that Planning
Policy Wales - Edition 12 (PPW 12) incorporated Welsh Government planning
policies for minerals developments in Minerals Planning Policy Wales
(2001). In accordance with PPW 12,
Cyngor Gwynedd, as the Mineral Planning Authority had a duty to ensure that
mineral resources were exploited in a sustainable way so that they could make
an appropriate contribution to the area’s construction materials requirements.
It was added that the application complied with the criteria of Policy MWYN 3
which permitted development proposals for mineral exploration, mining or extensions to existing operations to maintain the
Plan area’s landbank of aggregates, or to meet a need for other minerals.
In the context of the landscape's visual amenities, it was noted that the proposed
development would cause direct impacts to the landscape of the application site
which were unavoidable due to the nature of mineral extraction. As part of the supplementary documents, the
applicant had provided a Landscape and Visual Appraisal (LVIA) which considered
the sensitivity of surrounding landscape designations, residential areas and recreational receptors. Natural
Resources Wales (NRW) had assessed the documents and had provided an analysis
of the visual impacts, and argued that extending operations at
the site would affect the tranquillity and character of the nearby Eryri National Park; the permitted concept restoration for
the area covered by buildings/sheds/stocking areas was relatively vague other
than removal of the structures and profiling of the land/slate tip that would
leave an obtrusive landform.
In response, it was noted that the application was not for a new mineral
development, but rather for physical extensions and / or alterations to the
working area. However, it was acknowledged that planning permission 5/59/500
was relatively lax in terms of restrictions on operations that could have a
significant impact on tranquillity (i.e., noise, air quality, operational
hours) and the buildings/workshops/sawing sheds, staff facilities and car
parking were not covered by this permission but under numerous separate historic
permissions.
It was considered that there was an opportunity here to assess the
visual impact of the current planning policy, by means of an appropriate
condition that could reduce the visual impact of the site following cessation
of the works. This would overcome NRW’s main concerns and ensure compliance
with the policies.
In the context of Hydrology and hydrogeology, it was noted that the excavation
work would continue in a similar manner as was currently undertaken. Run-off
from the quarry was directed into the quarry void and subsequently into the Manod Quarry voids which acted as attenuation ponds for
suspended solids. Water from processing operations was recycled with any foul
water from the works and fed through a filter press prior to being pumped into
the Manod Quarry. Off-site run off was limited to
seepage from the ponds that overflow into Llyn Ministry (located West of the
quarry processing buildings) with any overflow feeding the Afon
Teigl. The quarry currently practices appropriate
measures to mitigate from accidental discharges that will be retained. It was
reported that NRW had reviewed the information submitted and confirmed that
they had no concerns about hydrology with extending the working lifespan of the
quarry subject to compliance with the continued use of pollution prevention
measures and good practice guidelines.
It was therefore considered that the proposed
development would have no adverse impact on hydrological features and flood
risk and complied with the requirements of Strategic Policy PS 19 and Policy
AMG 3, AMG 5, PCYFF 2, PCYFF 3, PCYFF 6 and MWYN 3 of the Anglesey and Gwynedd
Joint Local Development Plan 2011 - 2026.
In the context of ecological and biodiversity matters it was noted that
the Local Authority's biodiversity officer had raised concerns about an area in
the northernmost part of the site's boundary that was in the approved area for
mineral extraction but had yet to excavated/quarried. It was explained that the
area was approximately 0.5ha in size and consisted of upland grassland, heath
and bog, rock outcrops and small pockets of peat and was area of high
biodiversity value. Despite the loss of this land, the biodiversity officer
recommended that mitigation was provided within the restoration scheme.
In the context of archaeology and cultural heritage, it was noted that
concerns were raised by CADW during the initial consultation period about the
adequacy of information presented in relation to cultural heritage as contained
in chapter 9 of the Environmental Statement (ES). These concerns were
specifically in relation to the effects of quarrying operations
(blasting/vibration) on non-designated historical features within the quarry
relating to the storage of nationally important artworks during the Second World
War. It was explained that Manod Quarry had been selected as a suitable location
for a secret and specialist art storage facility, and that the environmental
statement considered that the storage facility was of high value in terms
of evidential, historical and communal value, although there was only a
moderate evidential value in the remains of the built physical remains (a
deterioration in the condition of the facility since the MoD’s relinquishment
of the facility - the generators, lights, picture hanging rack all removed with
little plant equipment left in situ and what remained of the structures in a
poor and deteriorating state. The instability of the cavern roofs also limited
safe physical access to the site).
The report by GWP Consultants, on potential
vibration damage from blasting, concluded that current blasting methods should
modified once works were within 60m of vulnerable parts of the mines. It was
added that CADW, having received additional information, had now concluded that
quarrying operations could be maintained without damaging the art storage
facility. CADW had confirmed that there was no objection to the proposal
subject to the inclusion of relevant conditions on the planning
permission. Conditions would include
restrictions on blasting activities and a requirement for a programme to record
the buildings and the dissemination of findings.
In the context of the economy, it was noted that prolonging mineral
extraction operations at the quarry would directly and indirectly ensure the
retention of the existing workforce and other related jobs/employment (such as
haulage, plant and engineering). It was added that the
company made a direct and substantial contribution to the local economy and
direct/indirect employment as a result of the quarry's
operations. Moreover, retaining local workers had positive effects on culture,
and more specifically, on the status of the Welsh language in the area.
Therefore, it was considered that the proposal made a positive contribution to
the area's economy in accordance with Strategic Policy PS 13 of the Joint LDP
and TAN 23.
b) Taking advantage of the right to
speak, the applicant made the following observations;
·
The planning application
facilitated the continuation of Cwt y Bugail / Manod Quarry, and the continued production of slate in the
quarry until 2048.
·
It the application was
approved, the extended lifespan granted for the quarry would provide a firm
foundation for the Company to make decisions on future capital expenditure at
Cwt y Bugail that would reduce waste, increase the
number of slates produced per tonne of excavated rock, to increase annual sales
in response to the demand, and expand the choice and introduce new and
innovative products.
·
It would also secure 34
skilled jobs at the quarry until 2048.
·
The Company was
grateful to Gwynedd and CADW officers for the opportunity to collaborate to
resolve issues relating to the use of the caverns near the quarry that were
used by the National Gallery during the Second World War.
·
An action plan had been
agreed that would allow the quarry to continue in operation in accordance with
the proposal to ensure that the work would not have an impact on the remains,
and that a full record of those remains would be made public.
·
The Company was very
aware of the value of the quarry in relation to its history and importance in
the community, and was trying to secure a bright
future for the site in addition to its rich past.
·
The development would
be a significant step in reaching this aim.
It was proposed and seconded to approve the application
In response to an
observation that the application had been registered in 2022, a number of observations from the consultation dated from 2022
and whether more recent matters had arisen but had not been given attention, it
was noted that CADW's observations had taken time to resolve, and as a result,
a further consultation period had been held.
RESOLVED:
To delegate powers to
the Assistant Head of the Environment Department to approve the application,
with conditions relating to the following:
·
The work to come to an
end on 31/12/2048, restore the site by 31/12/2049.
·
Permitted activities
and compliance with the submitted drawing / details / plans / information.
·
Mark the boundary of
the site and mineral extraction zones and tipping areas.
·
Revoke GPDO Part 19
& 21 rights for fixed plant or machinery, buildings and structures and
mineral waste.
·
15,000 tonnes per annum
export limit.
·
Exported material
restricted to existing public highway.
·
Tipping operations to
be directed towards final landform.
·
Updated tipping
capacity.
·
Control of noise
limitations.
·
Restrict blasting 07:00
to 20:00 Monday to Saturday.
No blasting on Sundays,
bank holidays or public holidays
·
Peak particle velocity
restricted to 50mm/s for 95% of overburden blasts over a three-month period and
not exceed 60mm/s at any time.
·
Peak particle velocity
must be measured at the closest point to the blast site within the shaded area
shown in Drawing Reference WCYBG2312 Drawing No.10
·
Monitoring of blasting
operations to record peak particle velocity.
·
Five yearly review of operations.
·
Submit the first report
within 12 months.
·
Detailed Restoration
Plan.
·
Phased/progressive
restoration works.
·
5-year
aftercare/monitoring.
·
Scheme of landform
remodelling shall be applied to North Pole Quarry benches and associated faces
as indicated on plans for creation of stable landform and features to match
surrounding rock buttresses and scree.
·
Following cessation of
works, clearance of quarry plant/machinery/materials/equipment and site to be
left in clean/tidy condition, quarry benches prepared, treated
and planted with flora of local provenances, haul roads to be removed.
·
Restrict access of
livestock to restored areas.
·
No plant or machinery
to be operated without appropriate and properly maintained sound deadening screens,
silencers etc.
·
All vehicles
transporting raw material or waste shall be operated in a manner not to
generate excessive noise.
·
No operations to cause
raising of fugitive dust and all areas traversed by vehicles to be watered
down.
·
Removal of vegetation,
structural repair or demolition of buildings and working of previously
stripped/quarried/tipped areas shall be undertaken outside of nesting season
for the protection of nesting birds. Qualified
ecologist
·
No operations to be
undertaken on surface without stripping and storage of topsoil’s, subsoils and peat.
·
Topsoils and subsoils to be
re-used as soon as possible (In restoration).
·
Topsoils to be stored in mounds
not exceeding 2m in height.
·
Historic building
recording of the art storage facilities and Written Scheme of Investigation.
·
Monitoring and
eradication plan of non-native/invasive species.
Supporting documents: