Dafydd Gibbard, CJC Lead Authority Chief Executive for the Corporate Joint Committee and Alwen Williams, Ambition North Wales Portfolio Director, and Interim Chief Executive of the North Wales CJC to present a further update on progress to establish the Corporate Joint Committee (CJC), and to respond to its statutory functions and undertake the proposed transfer of the North Wales Economic Ambition Board’s functions into the CJC.
Decision:
1. To accept the report
on the progress update on work to establish the North Wales Corporate Joint
Committee and respond to the tasks that are required by its statutory functions
(Appendix 1 to the report).
2. To accept the
updated plan along with the proposed date
from 1 November for transferring the North Wales Growth Deal to the North Wales
Corporate Joint Committee.
3. To approve the
interim arrangements to release the Portfolio Director’s time for two days per
week to undertake the Interim Chief Executive role until 31 October 2024. (All
employment and associated costs would continue to be covered by the North Wales
CJC).
4. Ask for a further
report on progress in the transferring and monitoring proses of the timetable.
Minutes:
The report was submitted by Alwen Williams, Interim CJC Chief Executive.
RESOLVED:
1.
To accept the report on the
progress update on work to establish the North Wales Corporate Joint Committee
and respond to the tasks that are required by its statutory functions (Appendix
1 to the report).
2.
To accept the updated plan
and the revised date of 1 November for transferring the North Wales Growth Deal
to the North Wales Corporate Joint Committee.
3.
To approve the interim
arrangements to release the Portfolio Director’s time for two days per week to
undertake the Interim Chief Executive role until 31 October 2024. (All
employment and associated costs would continue to be covered by the North Wales
CJC).
4.
To ask for a further report
on progress in the transfer process and monitoring of the timetable.
DISCUSSION
It was questioned whether the resources and funding of the Corporate
Joint Committee went into the procurement work for progressing the Investment
Zone for Wrexham and Flintshire. In
response, it was noted: -
·
That an agreement had
already been reached to set aside £100,000 of the Joint-committee's budget to
facilitate the work of going through the Gateways to deliver the Investment
Zone.
·
As we faced a General
Election on 4 July, there was an additional arrangement in place and an
agreement by Flintshire Council and Wrexham Council to provide up to £25,000
each of funding for any work directed towards the development of the scheme
should the new government not follow through on the Investment Zones process.
It was further questioned whether there was any doubt
about the future of these policies. In
response, it was noted: -
·
No government had given an
indication that there would be a new arrangement in place, but assurances were
needed on this once the government was in place.
·
As a result of following
the process of going through the Gateways to prepare the application to confirm
the Investment Zone, a proportion of the £160 million being provided for the
Investment Zone would be a proportion that could be used for administrative
costs, so it would be possible to apply for the development costs from those
funds once the Investment Zone was approved.
The Leader of Flintshire Council noted that he was
disappointed that the Investment Zone was coming through the Corporate Joint
Committee and would prefer that there was a body set up between Flintshire and
Wrexham and their partners, such as Airbus, to manage the project. He further noted that it had been asked at
two meetings of the Joint-committee where the resources would come from, as
this was an Investment Zone for Flintshire and Wrexham, and he suggested to perhaps
look at the costs of various projects located in specific geographical areas.
It was noted that it was understood that the operating
resource for the Joint Committee by secondment from the Welsh Government had
now come to an end, and it was questioned how much of a blow this was to our
ability to proceed with the establishment of the Joint Committee. In response, it was noted:-
·
That the secondment was
terminated earlier than planned due to a personal decision to return to the
Welsh Government which was why they were now revisiting the structures to have
a more sustainable structure in place to support the transition work.
·
That the Executive Project
Board met every Monday and the different work streams met separately as well,
and this had set some structure around the work and the tasks that needed to be
accomplished.
·
That work was underway to
see if either permanent or additional temporary resources could be obtained to
fill the operational gap.
The Monitoring Officer explained that any decisions
regarding the transfer of staff to the Corporate Joint Committee were entirely
subject to the date of transfer of the Growth Plan to the CJC. As such, if the transfer date progressed to
the 1st of November, that was the first date the staff could also
transfer.
Supporting documents: