To provide
an introduction for the Strategic Planning Sub-Committee on progress with
preparing a Delivery Agreement (DA) for the Strategic Development Plan (SDP)
for North Wales, as well as highlighting the broad programme for development of
the SDP, and some of the key matters it needs to consider.
Decision:
To accept
the report.
Minutes:
The report was submitted by the North Wales Corporate Joint Committee Chief Executive and Regional Strategic Development Planning Officer.
RESOLVED
To accept the
report.
REASONS FOR THE
DECISION
To ensure that the Strategic Planning
Sub-Committee is fully aware of the approach to be taken with the SDP and the
main steps involved in the process of drafting plans.
DISCUSSION
It was explained that the purpose of the
report was to provide the Sub-Committee with an initial overview of the
process, outlining the current position and the reasons why progress had
already been made ahead of this first meeting. It was hoped that members would
appreciate the value of doing so, particularly as this CJC was one of only four
across Wales, with only the Cardiff region having progressed far enough to
develop and consult on a draft Delivery Agreement. It was noted, therefore,
that this region was approximately 9 to 10 months behind Cardiff, although it
was acknowledged that progress in other CJC areas had proven even more
challenging.
It was noted that the report included the
legislative background as well as the broader context for producing a SDP,
which dates back to the Planning and Compulsory Purchase Act 2004 but was not
enacted through regulation until 2021 under the Local Government and Elections
(Wales) Act. It was emphasised that the principal driver for commencing work on
a draft Delivery Agreement was the requirement set by Welsh Government for all
CJCs to submit such an agreement by the end of 2024.
It was noted that a seven-point timeframe
existed for producing, agreeing, and submitting the Delivery Agreement, and
that the current stage fell between points two and four. It was confirmed that
this remained broadly in line with the indicative timeline. It was explained
that the draft Delivery Agreement had already been produced and submitted to
Welsh Government, and that it would be circulated to key stakeholders within
the coming weeks. It was noted that this would be followed by a wider
consultation during May and June, with the intention of seeking approval to
submit the agreement, subject to funding and resource considerations, by July.
It was further noted that the proposed timetable indicated submission to Welsh
Government in August.
It was noted that two key meeting markers
had been identified within the forward work programme: the first in late June
or early July, to coincide with the feedback received from the consultation on
the Delivery Agreement; and the second in October or November, when a further
update would be provided regarding Welsh Government approval and the initiation
of the SDP production process.
It was highlighted that the report included
a broad overview of the eight-stage programme for developing the plan, which
was shaped by the relevant regulations that govern the production of SDPs. It
was also noted that the report identified a number of positive aspects and
opportunities available to the Sub-Committee through producing the SDP
collaboratively as a region, over a longer timeframe and at a higher strategic
level.
It was questioned, in relation to the formal
examination of the soundness of the SDP, whether this process would be public
in nature, similar to that of LDPs. In response, it was confirmed that this was
correct. It was explained that the process would follow the same procedures as
those applied to an LDP.
Supporting documents: