Installation
of underground electricity cable in association with Pentir BESS energy storage
scheme (LPA reference: C24/0532/25/LL)
LOCAL
MEMBERS: Councillor Menna Baines and Councillor Elwyn Jones
Decision:
DECISION: To approve in accordance with
the following conditions:
1. Five years.
2. In accordance with the plans/details
submitted with the application.
3. Compliance
with the recommendations of the Preliminary Ecological Evaluation,
Arboriculture Impact Assessment and the Green Infrastructure Statement.
4. Submission
of an Environmental Construction Management Plan to manage impacts on the
natural environment.
5. Submission
of a Construction Management Plan to manage amenity matters.
6. Agree on an Archaeological Work
Programme.
7. Submit
a Site Restoration Plan to restore the site to a condition agreed the Planning
Authority after the development's operational period has ended
8. Submission of a plan for eradicating
Himalayan Balsam from the site.
9. Submit details of the underground drilling
method with launching points outside the tree roots protection areas.
Notes:
Natural
Resources Wales
Gwynedd
Archaeological Planning Service
Minutes:
Installation
of an underground electricity cable in association with Pentir
BESS energy storage scheme (LPA ref: C24/0532/25/LL)
Attention
was drawn to the late observations form.
a)
The
Planning Manager highlighted that it was a full planning application for the
installation of an 830m underground cable between the Pentir
electricity substation and the nearby Battery Energy Storage System facility
which was approved by planning permission in 2024. The installation period was
expected to take a maximum of 10 weeks, with the cable being laid underground
either through trenches dug on the surface and filled back, or through
Horizontal Directional Drilling.
It
was explained that the site is an Open Countryside site and within the Dinorwig
Landscape of Outstanding Historic Interest with a small area within Flood Zone
3 (surface water and watercourses). To the north of the site the adjacent
woodland is a recognised "Regional Wildlife Site" and is listed on
the Ancient Woodlands List as a "Plantation on an Ancient Woodland
Site". It was also noted that the land was classified as 3a, 3b and 5 on
the predictive Agricultural Land Classification Map for Wales.
In
this case, the proposal is located with the intention to connect two sites that
have permission and therefore the rural location is unavoidable. Attention was
drawn to policy ISA 1 which is supportive of proposals for water, electricity,
gas, etc services to improve provision, subject to detailed planning
considerations. The policy states the importance of the infrastructure
provision for a development site being located and designed in a manner that
minimises the impact on the natural and built environment. This development
will be placed entirely underground, and therefore the proposal was deemed to
comply with the requirements of ISA 1.
The
method of laying the cable will be a mix of providing surface dug and
backfilled trenches, or through Horizontal Directional Drilling within areas
where tree roots and tree-dwelling species need to be protected. The areas that
will be subject to the drilling method have been identified, partly because of
Natural Resources Wales' comments. The confirmation
of the use of the drilling method in these specific areas together with
imposing a planning condition for agreeing the launch points of the drilling method
ensures that the trees and species are protected. As a result, the proposal was
deemed acceptable. It was reiterated that Natural Resources Wales had provided
a response on the 14 November stating that they were now satisfied with the
proposal. There will be no above-ground impact following the installation of
the cable and therefore it was not considered to have a long-term impact on any
habitat or agricultural land.
It
was recognised that there will be inconvenience from noise and movement during
the construction phase, but this period was considered to be short, and subject
to conditions dealing with noise, dust and vibration matters, together with the
prior agreement of a Building Control Plan, it was considered that it could
alleviate any impacts and therefore the proposal was acceptable in this
context.
Matters
regarding transport, language, and flooding were referred to, which had
received appropriate attention, and the proposal was acceptable in relation to
these matters. It was noted that Heneb considered the
proposal to be acceptable subject to a planning condition to agree an
archaeological work programme.
Officers
considered the proposal acceptable and compliant with the requirements of
national and local policies and recommended granting the application with
appropriate conditions.
b)
Taking
advantage of the right to speak, the applicant’s Agent noted the following
observations:
·
That
the officer's report was complete.
·
The
cable laying work would be underground and would last for about 10 weeks.
·
That
the work meets Welsh Government targets for energy storage.
·
Work
linking the two sites already had planning permission and this work was
essential.
·
Consultation
work had been completed.
·
Nearby
Ancient Forest - tree survey completed, and mitigation measures agreed.
·
That
a condition had been agreed for the drilling work.
·
There
were mature trees on the cable path – specialist drilling would be required to
avoid impact.
·
Heneb – monitoring and recording work will be
completed during the works.
·
Any
crossings and pollution works will be monitored.
·
No
objections had been received during the consultation period.
The
Chair noted that the Local Members did not object to the application.
c)
It
was proposed and seconded to approve the application.
RESOLVED To approve
in accordance with the following conditions:
1. Five years.
2. In
accordance with the plans/details submitted with the application.
3. Compliance with the recommendations of the Preliminary
Ecological Evaluation, Arboriculture Impact Assessment and the Green
Infrastructure Statement.
4. Submission of an Environmental Construction Management Plan to manage
impacts on the natural environment.
5. Submission of a
Construction Management Plan to manage amenity matters.
6. Agree
on an Archaeological Work Programme.
7. Submission of a Site Restoration Plan
to restore the site to a condition agreed with the Planning Authority after the
development's operational period has ended.
8. Submission of a plan for eradicating
Himalayan Balsam from the site.
9. Submit details of the underground
drilling method with launching points located outside the tree roots protection
areas.
Notes:
Natural Resources Wales
Gwynedd Archaeological Planning Services
Supporting documents: