Full application for the Erection of 8. No. Affordable Dwellings (exception site) and Associated Development to include creation of vehicular access, estate road, landscaping and sustainable surface water drainage area.
LOCAL MEMBER: Councillor Gareth Williams
Decision:
DECISION:
To defer a decision and conduct a site visit.
Reason: To assess the impact of the proposal on the
amenities of the neighbouring residents.
Minutes:
Full application for the
erection of eight affordable dwellings (exception site) and associated
developments to include creation of a vehicular access, estate road,
landscaping and a sustainable surface water drainage area.
Attention was drawn to the late
observations form.
a)
The
Planning Manager highlighted that the proposal includes the construction of
three 2-bedroom bungalows, four 3-bedroom two-storey houses and one 4-bedroom
two-storey houses all to be finished with a mix of render, stone and wood
cladding on the walls and a natural slate roof. It was added that an existing
natural 'clawdd' to the front of the site was
to be relocated to the northern boundary of the site with new hedges to be
planted on the remaining site boundaries.
It
was reported that the site of the proposed development is presently open
agricultural land with boundaries predominantly natural hedges with adjacent
residential dwellings to the north, west and southerly direction with various
elevations in terms of design, form and finishes. The entire site is outside
the current development boundary of the village of Aberdaron and is therefore
in open countryside. The western and southern boundary of the proposed site
partly abut the current development boundary. The class
3 public road is situated adjacent to the western boundary and what would be
the front of the site with access and a right of way into agricultural lands
that runs along the land's northern boundary. The site is within the Llŷn AONB and the Llŷn
and Ynys Enlli Landscape of Outstanding Historic Interest designations and
within a 500m zone from a scheduled monument.
It
was explained that the village of Aberdaron is defined as a rural/coastal
village in the LDP with approximately 95 houses and a few facilities within the
current development boundary. Based on the settlement size a development of
this scale would mean a growth of 7.6% to the settlement, however, we must bear
in mind that recent permission was granted for another exception site for 5
units in this settlement.
With
the site located outside the development boundary all units were expected to be
for local affordable need. For Aberdaron this is defined as people who are in need of affordable housing and who have lived within
the Village, or in the surrounding rural area for five years or more, either
immediately before submitting an application or in the past. A 'rural area' has
been defined in this case as a distance of 6km from
the application site and the whole of the area of any Community Council divided
by the 6km distance, excluding properties within the development boundary of
any settlement other than the settlement within which the application is
located.
Evidence
was submitted in the form of a Housing and Affordable Housing Needs Statement
which refers to a need highlighted on the Social Housing and Tai Teg Register
in Aberdaron and the village of Rhiw, stating that Rhiw is located within 6km
east of Aberdaron and is not included as a designated settlement, including as
a cluster, and therefore it is not possible to provide any new housing
development within the settlement. The combined data from the Social Housing
and Tai Teg Register for Aberdaron and Rhiw was confirmed, and consideration
had been given to the contribution that a recently approved application for 5
self-build units would offer to the area.
The
proposal would provide a neutral scheme in terms of tenure; offers a mix of
social rented housing, intermediate affordable rental housing and shared
ownership to be able to meet a wide range of need and enable households to move
from rented to shared ownership as their circumstances change. This will offer
a completely different local affordable provision to what has already been
allowed on another site on the outskirts of the village such as the recent
5-unit self-build scheme. Based on the information submitted as part of the
application it was considered that the need had been confirmed for the
development, with the proposal to form a logical extension to the village.
The
site is located within the AONB, and although it was recognised as an exclusion
site and extending out into agricultural open land, it was not considered that
it would have a visual adverse impact and would suit the built context of the
existing area and the rest of the village. In the context of general and
residential amenities, following a full assessment, the proposal was considered to be designed to minimise any impact on
neighbouring properties, and was therefore acceptable.
Attention
was drawn to the comments of the Biodiversity Unit, and the potential impact of
pollution reaching the Pen Llŷn and Sarnau
Special Area of Conservation. It was noted that the issue had received relevant
attention, and as a result of imposing pollution
control measures during the building works and of the sustainable drainage
area, it was not considered that the proposal would have a significant impact
on the characteristics of the Special Area of Conservation.
It
was reiterated that issues of drainage, transport, and language had been
addressed and were acceptable subject to relevant planning conditions. It was
considered that the proposal complied with the requirements of local and
national policies and therefore it was recommended that the application be
granted subject to the imposing relevant conditions.
b)
Taking
advantage of the right to speak, the applicant’s Agent noted the following
observations:
·
That
the application would provide eight affordable homes being led by Grŵp Cynefin with the
support of Cyngor Gwynedd to address the Gwynedd Housing Strategy.
·
Consultation
had taken place.
·
That
the scheme was acceptable.
·
Meetings
had been held with the Community Council and the County Council.
·
The
scheme complied with local and national policies.
·
No
objection had been received from the Highways Unit.
·
Attention
had been given to the public footpath.
·
That
the Strategic Housing Unit highlighted that the scheme meets the need.
·
The
proposal would have a positive impact on the language – likely to appeal to
Welsh speakers who have responded to the local demand.
c)
Taking
advantage of the right to speak, the Local Member made the following
observations:
·
That
the village is rural.
·
There
was a lot of opposition to the application locally.
·
That
the proposal was an over-development – the original proposal was for five
houses – this suited the site better.
·
The
proposal would have an impact on the neighbours at Y Ddôl
- it was the nearest property to the site. Looking at the plan, the largest
house within the development would overlook Y Ddôl.
Frustration that there was a lack of consultation about the design and layout
of the development.
·
Despite
discussion with the applicant regarding an amendment to place the two bungalows
to the rear of Y Ddôl, it was disappointing that
there was no change to the plan.
·
Despite
the number of trees in the plans, trees are rare - the Deunant
area is vulnerable to inclement weather and trees are rarely allowed to grow.
·
Suggested
that the Committee visit the site before coming to a decision - this would
provide a better context than a photograph in a report.
·
With
the housing being social and funded by a Welsh Government grant, it was
therefore difficult for the Council to oppose.
·
That
an application by a local person to build six houses outside the development
boundary had been refused - lack of consistency.
·
Was
there a genuine need for these houses? According to the report there are 14
families on the list – this was a high figure and was questioned locally.
·
That
rules needed to be adjusted so that Local Members had access to the waiting
list.
·
That
the Committee needed to consider the concerns of the Community Council and the
residents of the village.
d)
It
was proposed and seconded to conduct a site visit to assess the impact on
residential amenities.
In
response to a question as to whether an individual expert survey had been
completed by a rural housing facilitator for the development, it was stated
that it would be the responsibility of the applicant to request such a survey.
It was reiterated that an individual survey was not necessary, and that the
information and evidence of the Strategic Housing Unit had confirmed that the
need existed. In response, it was noted that data and evidence need to be
provided in reports and not just opinions. Suitable and appropriate information
must be included to highlight the need locally.
ch) During the ensuing
discussion, the following observations were made by Members:
·
Complete
data appropriateness was relevant.
·
That the actual need must be fully considered.
·
That there was an inconsistency in the wording of
the 'size' of the development – clear assurance was needed.
·
A
drop in numbers at Ysgol Botwnnog highlighted that
young people were leaving the area.
RESOLVED: To defer a decision and conduct an inspection
site visit.
Reason: To
assess the impact of the proposal on the amenities of the nearby residents.
Supporting documents: