To note the
outcome of the reports to the Corporate Joint Committee (CJC) held on 23rd
January 2026 and the next steps for the Strategic Development Plan.
Decision:
To note the outcome of the reports to the Corporate Joint Committee
(CJC) held on 23rd January 2026 and the next steps for the Strategic
Development Plan.
Minutes:
The report was submitted by the Regional Strategic
Development Planning Officer.
RESOLVED
To note the outcome of the reports to the Corporate
Joint Committee (CJC) held on 23rd January 2026 and the next steps for the
Strategic Development Plan.
REASONS FOR THE DECISION
Responsibility to prepare the draft Delivery
Agreement rests with the Strategic Planning Sub-Committee. The sub-committee
has co-ordination and planning functions regarding each step towards delivery
of the SDP.
DISCUSSION
The Regional Strategic Development Planning Officer
presented a report summarising the outcome of the Corporate Joint Committee
meeting held on 23 January 2026 and the steps leading to the recommendation to
formally submit the Strategic Development Plan Delivery Agreement to Welsh
Government for ministerial approval. It was explained that the report sets out
a comprehensive audit trail which brought the Sub-Committee up to date and
evidenced the stages the Delivery Agreement had progressed through. Reference
was made to the background section of the report, which included signposts to
the meetings at which the Sub-Committee had previously considered the Delivery
Agreement and the basis on which recommendations had been made.
It was reported that September 2025 had been a key
milestone, as the Sub-Committee had considered a draft version of the Delivery
Agreement and its appropriateness to be submitted to Welsh Government for
formal approval, subject to confirmation that the Corporate Joint Committee
could set the 2026 to 2027 budget and identify the additional funding required
to commence the Strategic Development Plan and sustain delivery across the five
year programme. It was noted that the Corporate Joint Committee had subsequently
endorsed the same conditional position on the 19th of September 2025,
recognising the financial concerns raised, and that the Delivery Agreement
could not progress further until the 2026 to 2027 budget had been set.
It was explained that, through the autumn
budget-setting process, work had been undertaken with the Chief Finance Officer
and finance officers to identify options which aligned with the previously
stated requirements, namely that the additional resources required for the
Strategic Development Plan should, where possible, be found from within
currently available resources and should not place a substantial additional
burden on local authority budgets through a significant increase to the levy.
It was reported that the budget-setting process had identified a means of
meeting the year one funding requirement without creating an additional levy
pressure attributable to the Strategic Development Plan, and it was noted that
the levy increase for 2026 to 2027 had been limited to an inflationary uplift
of 3.5%.
It was stated that the estimated average annual
funding requirement for delivery of the Strategic Development Plan over the
five-year programme was approximately £655,000 per year. It was noted that the
year one budget had been set at £597,000, reflecting the anticipated
requirement for the first year rather than seeking the full average amount, and
that the budget would be reviewed and set annually through the normal budget
cycle.
It was reported that the ability to set the year one
budget without a significant levy impact had been achieved through the use of
internal resources, including an underspend against the Strategic Development
Plan revenue budget in 2025 to 2026 and the securing of a Welsh Government
performance grant of £200,000 during the year. It was noted that these elements
had mitigated potential cost pressures on the constituent authorities and could
provide similar mitigation into year two, and potentially beyond, depending on
future circumstances.
In discussion, it was questioned whether Welsh
Government grant funding would be available in the coming year to support the
Strategic Development Plan. In response, it was noted that no prescriptive
information had been issued by Welsh Government, and it was noted that
certainty regarding future grants was unlikely given the proximity to the
election period. It was stated that, despite there having been no funding
available nine to ten months earlier, a performance grant of £200,000 had been
secured, which formed part of a £400,000 allocation across the four Corporate
Joint Committees, and this demonstrated the benefit of demonstrating good
progress with the plan. It was further noted that the Strategic Development
Plan was one of the areas of Corporate Joint Committee work which did not
automatically attract an annual grant supplement. It was noted that
representations to Welsh Government would continue, with progress being used to
strengthen future cases for funding, particularly post-election depending on
policy priorities.
It was questioned whether interest on funds held
could be used to support the Strategic Development Plan and reduce levy
pressures. In response, the Chief Finance Officer reported that this had been
considered within the corporate plan and budget process. It was noted that the
Corporate Joint Committee remained a relatively young body and that some posts
had not been filled as quickly as expected, resulting in underspends accruing.
It was reported that this position had enabled the levy charged on the six councils
and the National Park Authority to be kept down for 2026 to 2027. It was noted
that, whilst the underspend had not been planned, the position had allowed a
significant portion of funds to be applied to Strategic Development Plan
delivery, helping to minimise levy increases in a context where future Welsh
Government funding could not be guaranteed.
It was emphasised that the significance of
submitting the Delivery Agreement to Welsh Government was not only the ability
to fund year one, but the commitment to fund delivery across the full five-year
programme. It was noted that the Corporate Joint Committee had held a detailed
discussion regarding balances and reserves, and it was reported that
maintaining reserves was a prudent approach which mitigated future financial
risk and provided assurance in the event of variable funding year on year. It
was noted that this approach supported a positive recommendation to proceed
with formal submission, and it was reported that the financial position was
considered sufficiently robust for at least the first two to three years,
noting that underspends would not necessarily arise every year.
It was questioned whether a significant levy
increase should be anticipated the following year if there was no further
underspend and no additional Welsh Government funding. In response, it was
reported that no guarantees could be provided but no large increase was
expected in the levy the following year. It was noted that the approach taken
created flexibility and mitigation, as the £200,000 grant would either fund
revenue expenditure in-year or flow into balances as an underspend, with either
route supporting the subsequent budget-setting position. It was reiterated that
the Strategic Development Plan was a statutory requirement, and it was noted
that funding would need to be identified through the Corporate Joint
Committee’s budget process rather than relying on grants, alongside ongoing
efforts to secure additional external funding. It was emphasised that the
project was in the best position possible financially at the start of a project
of this nature.
Further information was requested in relation to the
Welsh Government Strategic Performance Grant of £200,000. In response, it was
clarified that the Welsh Government Performance Grant of £200,000 related to
2025 to 2026, was claimed in arrears, and it was noted that approximately
£50,000 had been claimed to date with the remaining claim to be submitted at
the end of the financial year. It was noted that this income would appear in
the 2025 to 2026 accounts and within the strategic planning income lines in the
relevant revenue monitoring information, and it was further noted that any
associated underspend could be carried forward into reserves for use in 2026 to
2027.
It was reported that a mid-term financial plan
covering a three-to-five-year forecast would be brought forward around
September 2026 and it was noted that this would provide clearer visibility of
anticipated funding and likely levy changes, with the intention that future
impacts would be understood in advance of the annual budget-setting stage.
A member acknowledged that, where possible, unspent
money would ordinarily be recovered given the financial strain placed on many
local authorities, but it was noted that carrying funds forward into reserves
to support the five-year Strategic Development Plan programme was appropriate
given the statutory nature of the work, the need to minimise levy impacts, and
the benefit of having mitigation available for future years. In response, it
was reported that, over time, a Strategic Development Plan should reduce
duplication and lead to a more streamlined and efficient approach to local
development plan reviews and begin to accrue financial savings in the longer
term.
Supporting documents: