To note the
content of this report and that the task list presented will inform the
development of the Sub-Committee work programme and co-ordination of meetings.
Decision:
To note the content
of this report and that the task list presented will inform the development of
the Sub-Committee work programme and co-ordination of meetings.
Minutes:
The report was
submitted by the Regional Strategic Development Planning Officer.
RESOLVED
To note the content of this report and that the
task list presented will inform the development of the Sub-Committee work
programme and co-ordination of meetings.
REASONS FOR THE DECISION
Responsibility to implement the SDP Delivery
Agreement rests with the Strategic Planning Sub Committee. The Sub-Committee
has co-ordination and planning functions regarding each step towards delivery
of the SDP.
A
timetable of the Strategic Development Plan work programme for 2026 to 2027 was
presented, and it was explained that the purpose of the report was to provide
an early forward look, on the assumption that Welsh Government approval of the
Delivery Agreement would be received, setting out the key tasks and milestones
in year one of the five-year programme. It was reported that the first five or
six actions in the table related mainly to procedural steps following approval
of the Delivery Agreement, including approval, commencement and publication
arrangements. It was also noted that recruitment formed part of these early
steps, and it was reported that the approved Strategic Development Plan budget
enabled the recruitment of at least one additional planner to support delivery
in year one. It was emphasised that adding capacity within the Corporate Joint
Committee was important to maintaining deadlines within the overall timetable.
It
was reported that the later items within the timetable, particularly points
seven to ten, represented more substantive stages in the year one process and
would be the areas most likely to require reports to the Sub-Committee for
consideration, discussion and steer, prior to matters being reported onwards to
the Corporate Joint Committee. It was explained that an early substantive
output would be the preparation of a Main Issues Report. It was noted that
preparatory work had already commenced to put a consultancy contract in place
to assist in developing the evidence base, and it was reported that this would
begin with an audit of existing evidence bases that supported local development
plans within each constituent authority area. It was noted that the approach
was intended to avoid duplication and avoid reinventing the wheel, recognising
that local authorities had already invested significant time and money in
developing evidence bases, and that where evidence remained current it would be
utilised rather than repeated.
It
was reported that the audit would also identify evidence gaps and areas
requiring updating, particularly where evidence was dated, and that this would
inform where limited funding might need to be targeted to ensure a consistent
regional picture. It was noted that the approach would include working with
authorities who were already planning to refresh evidence bases, in order to
align activity and secure best value from limited public resources. It was
reported that the Main Issues Report would draw out the regionally significant
issues emerging from this evidence audit, to inform the scope and direction of
the Strategic Development Plan.
It
was noted that, alongside assembling the evidence base, work would also be
undertaken to test emerging issues with local and regional preferences. It was
reported that this would include the development of an issues vision and
strategic objectives, and it was noted that this would require facilitated
engagement with Sub-Committee members and other stakeholders to identify what
was considered most significant for North Wales and what the Strategic
Development Plan should prioritise. It was stated that this was an important
conversation and that it was likely to be most effective if held face to face,
although it was noted that this would be progressed in whichever format was
most practical. It was further noted that the same discussions would also take
place officer-to-officer with planning policy leads within each authority to
understand local priorities, where local development plan reviews were
progressing, and how locally significant issues combined to form a regional
perspective.
It
was reported that work would also be required to define a settlement hierarchy
and to develop growth and spatial options. It was explained that this would
include consideration of the appropriate scale of growth for North Wales over a
25-year period, including housing requirements, employment land needs, and
other development considerations such as town centre retail, alongside the
infrastructure needed to support growth. It was noted that the approach would
seek to align with what was emerging through local development plan reviews to
avoid early conflicts, and it was explained that, rather than assessing every
settlement within local hierarchies, a high-level regional settlement structure
would be developed, identifying the most important settlements regionally and
their strategic role. It was noted that options would be developed and
discussed to establish areas of agreement and consensus.
It
was reported that candidate sites would be an early stage of the Strategic
Development Plan process and that this would require the development of a clear
methodology to define what would constitute a strategic site. It was noted that
this would need to cover, for example, thresholds for strategic housing sites,
mixed-use sites, employment land sites and other regionally significant forms
of development. It was reported that this would lead to a call for candidate
sites, with an indicative six-to-eight-week window for submissions supported by
evidence, enabling landowners and parties with an interest in land at the
relevant scale to put forward sites for consideration.
It
was noted that, taken together, the timetable represented a full and ambitious
year one programme. It was reported that the intention was for the substantive
stages identified to inform a sequence of Sub-Committee meetings through the
year, potentially on a quarterly basis, although it was noted that dates had
not yet been set. It was also reported that meeting dates would need to be
arranged in a way that dovetailed with the Corporate Joint Committee timetable,
so that Sub-Committee consideration and recommendations could feed into
subsequent Corporate Joint Committee decisions. It was noted that the Corporate
Joint Committee meeting calendar was awaited before finalising the
Sub-Committee schedule. It was reported that a formal work programme would follow,
to be drafted and circulated, with an intention to settle meeting dates as
early as possible.
It
was questioned whether any risks had been identified which could impact on the
timetable, with specific reference to recruitment and retention difficulties
affecting local authorities and potential implications for the Strategic
Development Plan programme. In response, it was reported that recruitment had
been deliberately limited to mitigate pressure on the North Wales pool of
experienced senior planners, and it was noted that, although the delivery
programme referenced an internal team of four additional planners, a single
additional senior support officer was being pursued for year one to balance
resource needs with the risk of drawing staff from local authorities. It was
reported that significant reliance would therefore be placed on consultancy support
to mitigate risk and to enable progress against ambitious timescales. It was
noted that the year one budget included provision of nearly £300,000 for
consultancy support, and it was reported that this was intended to secure a
virtual team rather than creating direct recruitment impacts on local
authorities. It was further noted that a flexible approach would be maintained,
including the possibility of future secondment opportunities where appropriate,
recognising both the potential benefits to the Corporate Joint Committee and
the professional development opportunities for planners.
Concerns
were raised regarding sustainability of consultancy use given the cost, and the
risk of competing recruitment activity across authorities and the Corporate
Joint Committee within the same labour market. In response, reassurance was
provided that the consultants engaged were Arup, described as a national
multidisciplinary consultancy, and it was noted that they had already
undertaken substantial work for the Corporate Joint Committee in support of the
Regional Transport Plan, including early work to build an evidence base which
could also support the Local Development Plan. It was reported that this meant
the programme was not starting from a blank position, and it was noted that the
brief issued was to build on that earlier evidence rather than revisiting or
duplicating it. It was reported that this existing dataset and prior engagement
with authorities would support more efficient progress, enabling the evidence
audit and Main Issues Report to move forward more quickly. It was also noted
that evidence developed through this work would not be closed to the Corporate
Joint Committee, and that the intention was for relevant evidence outputs to be
available to local authorities to support their own work, enabling potential
efficiencies and reducing the need for duplicated local consultancy
commissions.
It
was questioned whether the Strategic Development Plan would impose policy
changes on individual councils and the National Park Authority, and whether it
could be used to support specific local challenges, with an example raised in
relation to managing holiday homes and second homes and the use of thresholds
across different communities compared to an area-wide approach. In response, it
was noted that the Strategic Development Plan should be viewed as an
opportunity to shape regionally relevant and, where appropriate, sub-regional
policies through discussion and agreement. It was reported that the approach
would not be for the Corporate Joint Committee to impose policy on authorities,
but to work collaboratively to develop policies that worked positively for
relevant areas and could be interpreted and applied through local policy
contexts once the Strategic Development Plan was adopted. It was noted that the
type of issue raised would be an example of a matter to bring forward into
those discussions, to inform how an effective policy could be developed.
Following
the discussion, additional proposals were raised to support effective working
arrangements: -
1.
It was agreed that the meeting scheduled for 9th March 2026
be held in person to facilitate more informal discussion and strengthen working
relationships.
2.
It was proposed that a member training programme be developed in the
background alongside the formal meeting cycle, potentially delivered virtually
four to five times per year, to build understanding of process, context and key
topics. It was suggested that an initial session could include input from Welsh
Government by inviting the head of the development plans branch to provide an
overview of the Strategic Development Plan process and the role of members,
potentially scheduled ahead of the in-person meeting in March. It was noted
that a library of materials could be maintained so that sessions could be
revisited and accessed by those unable to attend. Agreement was indicated that
training would be beneficial, and it was requested by members that the training
be flexible and responsive to topics arising through the programme, rather than
fixed too far in advance.
3.
It was proposed that regular informal updates be provided outside formal
meetings, for example through a short monthly email update or newsletter-style
or blog format, to keep members sighted on progress and next steps, and to
create an accessible audit trail of updates over time. Support was indicated
for receiving such updates.
Supporting documents: