• Calendar
  • Committees
  • Community Councils
  • Consultations
  • Decisions
  • Election results
  • ePetitions
  • Forthcoming Decisions
  • Forward Plans
  • Library
  • Meetings
  • Outside bodies
  • Search documents
  • Subscribe to updates
  • Your councillors
  • Your MPs
  • Your MEPs
  • What's new
  • Agenda item

    STRATEGIC DEVELOPMENT PLAN TIMETABLE 2026/27 AND KEY TASKS

    • Meeting of North Wales CJC Strategic Planning Sub-committee, Monday, 26th January, 2026 2.00 pm (Item 6.)

    To note the content of this report and that the task list presented will inform the development of the Sub-Committee work programme and co-ordination of meetings.

    Decision:

    To note the content of this report and that the task list presented will inform the development of the Sub-Committee work programme and co-ordination of meetings.

     

    Minutes:

    The report was submitted by the Regional Strategic Development Planning Officer.

     

    RESOLVED

     

    To note the content of this report and that the task list presented will inform the development of the Sub-Committee work programme and co-ordination of meetings.

     

    REASONS FOR THE DECISION

     

    Responsibility to implement the SDP Delivery Agreement rests with the Strategic Planning Sub Committee. The Sub-Committee has co-ordination and planning functions regarding each step towards delivery of the SDP.

     

    DISCUSSION

    A timetable of the Strategic Development Plan work programme for 2026 to 2027 was presented, and it was explained that the purpose of the report was to provide an early forward look, on the assumption that Welsh Government approval of the Delivery Agreement would be received, setting out the key tasks and milestones in year one of the five-year programme. It was reported that the first five or six actions in the table related mainly to procedural steps following approval of the Delivery Agreement, including approval, commencement and publication arrangements. It was also noted that recruitment formed part of these early steps, and it was reported that the approved Strategic Development Plan budget enabled the recruitment of at least one additional planner to support delivery in year one. It was emphasised that adding capacity within the Corporate Joint Committee was important to maintaining deadlines within the overall timetable.

    It was reported that the later items within the timetable, particularly points seven to ten, represented more substantive stages in the year one process and would be the areas most likely to require reports to the Sub-Committee for consideration, discussion and steer, prior to matters being reported onwards to the Corporate Joint Committee. It was explained that an early substantive output would be the preparation of a Main Issues Report. It was noted that preparatory work had already commenced to put a consultancy contract in place to assist in developing the evidence base, and it was reported that this would begin with an audit of existing evidence bases that supported local development plans within each constituent authority area. It was noted that the approach was intended to avoid duplication and avoid reinventing the wheel, recognising that local authorities had already invested significant time and money in developing evidence bases, and that where evidence remained current it would be utilised rather than repeated.

    It was reported that the audit would also identify evidence gaps and areas requiring updating, particularly where evidence was dated, and that this would inform where limited funding might need to be targeted to ensure a consistent regional picture. It was noted that the approach would include working with authorities who were already planning to refresh evidence bases, in order to align activity and secure best value from limited public resources. It was reported that the Main Issues Report would draw out the regionally significant issues emerging from this evidence audit, to inform the scope and direction of the Strategic Development Plan.

    It was noted that, alongside assembling the evidence base, work would also be undertaken to test emerging issues with local and regional preferences. It was reported that this would include the development of an issues vision and strategic objectives, and it was noted that this would require facilitated engagement with Sub-Committee members and other stakeholders to identify what was considered most significant for North Wales and what the Strategic Development Plan should prioritise. It was stated that this was an important conversation and that it was likely to be most effective if held face to face, although it was noted that this would be progressed in whichever format was most practical. It was further noted that the same discussions would also take place officer-to-officer with planning policy leads within each authority to understand local priorities, where local development plan reviews were progressing, and how locally significant issues combined to form a regional perspective.

    It was reported that work would also be required to define a settlement hierarchy and to develop growth and spatial options. It was explained that this would include consideration of the appropriate scale of growth for North Wales over a 25-year period, including housing requirements, employment land needs, and other development considerations such as town centre retail, alongside the infrastructure needed to support growth. It was noted that the approach would seek to align with what was emerging through local development plan reviews to avoid early conflicts, and it was explained that, rather than assessing every settlement within local hierarchies, a high-level regional settlement structure would be developed, identifying the most important settlements regionally and their strategic role. It was noted that options would be developed and discussed to establish areas of agreement and consensus.

    It was reported that candidate sites would be an early stage of the Strategic Development Plan process and that this would require the development of a clear methodology to define what would constitute a strategic site. It was noted that this would need to cover, for example, thresholds for strategic housing sites, mixed-use sites, employment land sites and other regionally significant forms of development. It was reported that this would lead to a call for candidate sites, with an indicative six-to-eight-week window for submissions supported by evidence, enabling landowners and parties with an interest in land at the relevant scale to put forward sites for consideration.

    It was noted that, taken together, the timetable represented a full and ambitious year one programme. It was reported that the intention was for the substantive stages identified to inform a sequence of Sub-Committee meetings through the year, potentially on a quarterly basis, although it was noted that dates had not yet been set. It was also reported that meeting dates would need to be arranged in a way that dovetailed with the Corporate Joint Committee timetable, so that Sub-Committee consideration and recommendations could feed into subsequent Corporate Joint Committee decisions. It was noted that the Corporate Joint Committee meeting calendar was awaited before finalising the Sub-Committee schedule. It was reported that a formal work programme would follow, to be drafted and circulated, with an intention to settle meeting dates as early as possible.

    It was questioned whether any risks had been identified which could impact on the timetable, with specific reference to recruitment and retention difficulties affecting local authorities and potential implications for the Strategic Development Plan programme. In response, it was reported that recruitment had been deliberately limited to mitigate pressure on the North Wales pool of experienced senior planners, and it was noted that, although the delivery programme referenced an internal team of four additional planners, a single additional senior support officer was being pursued for year one to balance resource needs with the risk of drawing staff from local authorities. It was reported that significant reliance would therefore be placed on consultancy support to mitigate risk and to enable progress against ambitious timescales. It was noted that the year one budget included provision of nearly £300,000 for consultancy support, and it was reported that this was intended to secure a virtual team rather than creating direct recruitment impacts on local authorities. It was further noted that a flexible approach would be maintained, including the possibility of future secondment opportunities where appropriate, recognising both the potential benefits to the Corporate Joint Committee and the professional development opportunities for planners.

    Concerns were raised regarding sustainability of consultancy use given the cost, and the risk of competing recruitment activity across authorities and the Corporate Joint Committee within the same labour market. In response, reassurance was provided that the consultants engaged were Arup, described as a national multidisciplinary consultancy, and it was noted that they had already undertaken substantial work for the Corporate Joint Committee in support of the Regional Transport Plan, including early work to build an evidence base which could also support the Local Development Plan. It was reported that this meant the programme was not starting from a blank position, and it was noted that the brief issued was to build on that earlier evidence rather than revisiting or duplicating it. It was reported that this existing dataset and prior engagement with authorities would support more efficient progress, enabling the evidence audit and Main Issues Report to move forward more quickly. It was also noted that evidence developed through this work would not be closed to the Corporate Joint Committee, and that the intention was for relevant evidence outputs to be available to local authorities to support their own work, enabling potential efficiencies and reducing the need for duplicated local consultancy commissions.

    It was questioned whether the Strategic Development Plan would impose policy changes on individual councils and the National Park Authority, and whether it could be used to support specific local challenges, with an example raised in relation to managing holiday homes and second homes and the use of thresholds across different communities compared to an area-wide approach. In response, it was noted that the Strategic Development Plan should be viewed as an opportunity to shape regionally relevant and, where appropriate, sub-regional policies through discussion and agreement. It was reported that the approach would not be for the Corporate Joint Committee to impose policy on authorities, but to work collaboratively to develop policies that worked positively for relevant areas and could be interpreted and applied through local policy contexts once the Strategic Development Plan was adopted. It was noted that the type of issue raised would be an example of a matter to bring forward into those discussions, to inform how an effective policy could be developed.

    Following the discussion, additional proposals were raised to support effective working arrangements: -

    1.     It was agreed that the meeting scheduled for 9th March 2026 be held in person to facilitate more informal discussion and strengthen working relationships.

    2.     It was proposed that a member training programme be developed in the background alongside the formal meeting cycle, potentially delivered virtually four to five times per year, to build understanding of process, context and key topics. It was suggested that an initial session could include input from Welsh Government by inviting the head of the development plans branch to provide an overview of the Strategic Development Plan process and the role of members, potentially scheduled ahead of the in-person meeting in March. It was noted that a library of materials could be maintained so that sessions could be revisited and accessed by those unable to attend. Agreement was indicated that training would be beneficial, and it was requested by members that the training be flexible and responsive to topics arising through the programme, rather than fixed too far in advance.

    3.     It was proposed that regular informal updates be provided outside formal meetings, for example through a short monthly email update or newsletter-style or blog format, to keep members sighted on progress and next steps, and to create an accessible audit trail of updates over time. Support was indicated for receiving such updates.

     

    Supporting documents:

    • Covering Report - Strategic Development Plan Timetable 202627 and key tasks, item 6. pdf icon PDF 198 KB