Replacement of existing underground cables and installation of new cross site underground cables in the existing Pentir substation and ancillary works
LOCAL MEMBER: Councillor Menna Baines
Decision:
DECISION:
To approve with conditions
Minutes:
Replacing existing underground cables and the installation of new
cross-site underground cables at the current Pentir
sub-station as well as associated works.
Attention was drawn to the late observations form - guidance to impose a
condition by the Assembly's Transport Unit.
a)
The Planning Officer highlighted that the proposal was part of a wider
project to reinforce overhead lines and cables on the existing circuits between
the Pentir and Trawsfynydd
sub-stations; the Project was part of the wider network transmission upgrades
needed to facilitate the work of connecting 50 Gigawatt of offshore wind energy
by 2030.
It was explained that the proposed works will be fully incorporated
within the existing footprint of Pentir Sub-station
and will utilise the existing access road, storage areas, welfare facilities,
office spaces, and staff car park. Reference was made to the Environmental
Statement which provided an overview of the Project, the main alternatives
considered in the development of the Project (where appropriate), information
about the current environment, and an assessment of the likely significant
impacts of the Project. Where appropriate, it was noted that mitigation
measures have been included to avoid, prevent, reduce or offset significant
adverse environmental impacts.
Increasing capacity on the existing transmission line between Pentir and Trawsfynydd
sub-stations has been identified as a step that urgently needs to be taken to
provide more transmission capacity, and is
acknowledged by Ofgem.
Reference was made to policy ISA 1 which was supportive of proposals
regarding water, electricity, gas services, etc. to improve the local
provision, subject to detailed planning considerations. In the context of
policy ADN 3, although the development is not a renewable energy scheme, it
would form part of the support network that could be used in managing the
renewable supply. To this end, it could be considered part of the renewable
energy network. A thorough assessment was conducted of the relevant criteria,
and it was considered that the proposal was acceptable in terms of principle
and complied with Criterion 1 Policy ADN3 in terms of the fact that all impacts
had been sufficiently mitigated. Similarly, it was noted that policies PCYFF 5,
PS 5, PS 6 and PS 7 are supportive of schemes for the development of renewable
technologies that contribute to protecting the environment and mitigating
climate change and this plan therefore met the objectives of these policies.
In the context of transport and access matters, once it is operational,
there will be no demand for additional vehicular access to the site and there
will be no long-term impacts on highway safety deriving from the development.
It was noted that the Assembly's Transport Unit was happy with the development
subject to conditions and, consequently, it was considered that the proposal
complied with the requirements of Policy TRA 2 and TRA 4 of the LDP in terms of
highway safety and convenience.
In terms of archaeology and heritage matters, it was highlighted that
there were many Scheduled Monuments in the site's vicinity. Heneb
noted that the desk assessment was very thorough and had been written well and
they agreed with the conclusion of the Assessment of the Environmental Impact
(AEA); the application was therefore acceptable under policies PS 20 - impact
on heritage features and AT 4 of the LDP - the protection of sites of
archaeological importance from harm.
A Welsh Language Statement was submitted as part of the application
which had considered the potential impacts of the Pentir
proposed work on the use of the Welsh language in the local community. Although
no adverse effects were identified in the assessment, measures were proposed to
ensure that the use of the Welsh language was maintained. An Environmental
Statement was also submitted which assessed the impact on the environment and
it was concluded that, with the imposition of planning conditions, the impacts
of the development could be satisfactorily mitigated and environmental features
protected.
The visual and landscape impacts were considered acceptable as the works
were within an already developed site and the development protected the
amenities of residential properties around the site satisfactorily.
It was reported that the proposed development would extend and improve
electricity connections across north Wales with the economic benefits
acknowledged. Having considered all the relevant planning matters including the
local and national policies and guidance, the officers recommended to approve
the application with conditions.
b)
Taking advantage of the right to speak, the applicant's representatives
made the following observations:
·
The application included work that would occur within the existing Pentir National Grid Sub-station and part of the Pentir to Trawsfynydd Project
that would reinforce and
restore the existing line between Pentir and Trawsfynydd.
·
The work would
provide more capacity in the network and allow the network to be safer whilst
allowing more clean energy to supply homes and businesses.
·
The work forming part of the application normally would be considered as
an 'approved development'. However, because the work forms part of the Pentir to Trawsfynydd Project,
with planning applications being submitted to the Planning Committee in the
coming months, planning permission was required for the work.
·
The work proposed as part of the application will occur within the
existing boundaries of the Pentir Sub-station site
and include replacing the existing underground cables, as well as installing
new underground cables across the site.
·
The planning officers expressed that the work was acceptable and
recommended to approve with conditions.
·
He asked the Committee kindly to support the application, which formed a
key part of the work to reinforce the network between Pentir
and Trawsfynydd.
c)
The
Monitoring Officer noted that the Local Member (Councillor Menna Baines) had
noted in an e-mail that she had no objection to the recommendation.
ch) It was
proposed and seconded to approve the application
RESOLVED to approve with conditions
1. 5 years
2. In accordance with the plans, all
recommendations in the documents and assessments, and the approved
Environmental Statement.
3. Public Protection Conditions
4. Trunk Road Conditions
5. Compliance with the Green Infrastructure
Statement along with future maintenance work.
6. Ensure bilingual signage with priority
given to the Welsh language.
7. The applicant must submit to the Local
Planning Authority a Construction Traffic Management Plan (CTMP) which will
satisfy the Welsh Government, as the Overseeing Organisation for the Strategic
Road Network (SRN).
Supporting documents: