Hedd
Vaughan-Evans, Portfolio Director to present report.
Decision:
To agree to establish a Cost Inflation Reserve
for 2026/27 and provide an initial £3.96m of Growth Deal funding to this
reserve.
To approve the criteria set out for the Cost
Inflation Reserve and the delegated decision matrix.
Minutes:
The report was
presented by the Portfolio Director.
DECISION
To agree to establish a Cost Inflation Reserve for 2026/27 and provide
an initial £3.96m of Growth Deal funding to this reserve.
To approve the criteria set out for the Cost Inflation Reserve and the
delegated decision matrix.
REASONS FOR THE DECISION
To propose the
establishment of a Cost Inflation Reserve to support approved projects
(Business Justification Case or Full Business Case approval) with increased
costs that cannot be mitigated in order to ensure that
projects move into delivery during 2026-27. An initial £3.96 would be allocated
to the Cost Inflation Reserve (to be reviewed in six months' time) leaving £28m
of unallocated funding available to Reserve List projects.
DISCUSSION
It was explained that
the purpose of the report was to establish a Cost Inflation Reserve to assist
the development of projects throughout the financial year, following
affordability challenges as noted earlier within this meeting. It was
considered that setting up this fund would ensure that the pace of delivery for
projects could be maintained and momentum gained into the future as more
Business Cases were approved. It was noted that the establishment of this fund
stemmed from experiences gained when projects had been delayed following the
war in Ukraine, and to prevent such a delay in future.
It was proposed that
£3.96 million of unallocated funding from the Reserve be allocated to establish
the fund, with this to be reviewed in six months. It was emphasised that £28
million would remain available for the Reserve List.
It was confirmed that
specific criteria would be used to determine if projects were eligible for a
budget. It was noted that the fund targeted projects that were already
partially developed, with procurement phases completed and a supplier
identified. It was elaborated that projects would be required to conduct
negotiations with suppliers to reduce costs where possible, in
order to qualify for funding from this reserve. It was emphasised that
any allocation from the reserve to a project must directly lead to the
successful delivery of that project.
It was reported that
the Growth Deal contribution towards the additional funding would be capped at
the existing percentage intervention rate, where the Growth Deal was a minority
funder in the project. In contrast, where the Growth Deal was the majority
funder in a project, the Growth Deal contribution towards the additional
funding from this reserve would be capped at 50% of the additional funding
required. It was emphasised that these constraints had been very valuable in
the past to ensure that project costs were shared with project sponsors, and were a successful means of ensuring that
projects developed effectively.
It was explained that
procedures would be in place to delegate decisions on the expenditure of the
reserve to officers, in cooperation with the Chair, Vice-Chair and statutory
officers.
During the discussion, the following
observations were made:-
There was concern that the use of this reserve
would lead to the extension of projects that might have been rejected within a
better economic climate, noting that this would remove budgets from those
projects where there was a certainty they would become operational. It was
noted that risk management was necessary to ensure that money was not wasted.
Comments were
received from the Non-Executive Adviser who highlighted that acting quickly in
times where the economic climate was challenging, as cost inflation occurred
gradually over time, would negate its effects.
The members expressed
their thanks for the report.
Supporting documents: