Application for a new substation and associated
infrastructure and ancillary works, including a new access road from the A487
and the upgrading of an existing agricultural access track, and new underground
132 kV cables to connect to the existing Electricity Networks overhead line.
LOCAL MEMBERS: Councillor Stephen Churchman and
Councillor Rhys Tudur
Decision:
DECISION:
To approve with conditions subject to receiving positive observations from the
Trunk Roads Unit in accordance with the recommendation
1. 5 years.
2. In accordance with the approved plans.
3. Footpath conditions.
4. Public Protection conditions.
5. Biodiversity conditions.
6. Trunk Road conditions.
7. Heneb
conditions.
8. Language conditions
Minutes:
Application for a new sub-station and
associated infrastructure and ancillary works, including a new access road from
the A487 and the upgrading of an existing agricultural access track, and new
underground 132 kV cables to connect to the existing Electricity Networks
overhead line; the proposal also included permanent diversion of Public Right
of Way Dolbenmaen No. 18 and build a new landowner
access track, as well as a temporary construction compound.
Attention was drawn to the late observations
form - the applicant to prepare further information to include traffic
information and mitigation measures
a)
The
Planning Manager highlighted that the proposal was part
of a wider project that encompassed reinforcing overhead lines and cables on
the existing circuits between the Pentir and Trawsfynydd substations in north-west Wales. It was
explained that the Project was part of the wider network transmission upgrades
that were required to facilitate the work of connecting 50 Gigawatt of offshore
wind energy by 2030 - increasing the capacity on the current transmission line
between Pentir and Trawsfynydd
substations which had been noted as a required step to take immediately to
provide more transmission capacity. It was elaborated that this had been
acknowledged by Ofgem, who noted that the necessary work was an Accelerated
Strategic Transmission Investment (ASTI).
It was reported that the site was located on
relatively flat ground that mainly consisted of grazing fields, with an area of
marshy grassland. It was highlighted that a similar proposal had previously
been approved under reference C17/0772/36/LL (and a subsequent permission to
extend the period of time to commence the work under
C22/1102/36/AC), and this continued to be 'live', but the permission no longer
fulfilled the needs of the project.
It was noted, as the proposed work was part
of the wider Project, and part of it included the approved re-installation of
high voltage electricity cables under the Glaslyn (which was the subject of a
separate application), that an Environmental Statement (ES) had been prepared
for the entire project. Due to the size of the site, the application was
defined as a major development, and a pre-application consultation report was
accepted as part of the application.
The proposed work would be an essential
element of the Pentir to Trawsfynydd
Reinforcement project; the additional capacity would support an effective
transfer of renewable energy across the region, contributing to reducing Net
Zero targets and carbon. Without the new sub-station and the associated 132 kV
infrastructure, this part of the plan would restrict the network and prevent
the project objectives from being fulfilled; the proposed development was
acceptable in principle and was supported by Local and National Planning
Policy.
With the proposal being significant, it was
acknowledged that any new infrastructure within a rural location could lead to
visual change, however, in this case it was considered that the Impact
Assessment on the Landscape and the Visual Impact had highlighted that such a
change would not be of a sufficient size to cause significant harm to the
character or appearance of the surrounding landscape. Significant emphasis was
also given on the clear need for the development which would be part of an
energy infrastructure of national importance and would be supported by local
and national planning policy objectives related to energy safety and
decarbonisation.
Attention was drawn to the intention to
landscape, as well as the fall-back position represented by the current
planning permission for a sub-station on the site. That approved plan would
lead to a similar level of visual impact, but with a different design and
orientation. In this context, the proposed development would not significantly
worsen the visual baseline conditions and, from assessing them cumulatively, it
was considered that the advantages noted were clearly more that any temporary
limited detrimental impacts.
It was acknowledged that the work period for
the proposal could impact the amenities of nearby residents, and it was
considered that those impacts could be managed effectively by imposing a
planning condition to ensure that an Environmental Impact Management Plan was
agreed beforehand.
It was noted that the proposal included
changing the existing farm entrance from the A487, which was a Trunk Road, to
provide suitable means of access for construction traffic. The entrance will
then be maintained and used for maintenance purposes. It was highlighted that the Highways Unit's
response asked for more details to assess the suitability of the entrance as it
was a different plan to the usual standards. It was elaborated that the
applicant was preparing further information to include traffic information and
mitigation measures with the intention of submitting their proposal to the
panel in June. (A positive response is expected from the Highways Unit
following the panel meeting). As a result, the application recommendation to
delegate the right to approve with conditions subject to receiving a positive
response from the Highways Unit continued as a result to this update.
In the context of matters relating to
diverting a footpath, hydrology, biodiversity, archaeology and the Welsh
language, it was considered that these matters were acceptable subject to
planning conditions. It was considered that the proposal was acceptable and
complied with the requirements of national and local policies. It was
recommended to delegate the right to approve the application with conditions
subject to receiving a positive response from the Highways Unit regarding the
entrance.
ch) The approval of the application was proposed and seconded
In response to an observation that the Intergovernmental Panel on
Climate Change (IPCC) 'plays down' the RCP8.5 presumptions that were planned as
the worst possible emissions scenario, and what impact this would have on
policies associated with a reliable supply of energy, the Assistant Head of the
Department noted that the policies that were relevant to this application
complied with local and national policies; there was already an extant
permission on the development and that development complied with the relevant
policies.
RESOLVED: Delegate the right to approve with conditions subject
to receiving positive observations from the Highways Unit, in accordance with
the recommendation
1. 5 years
2. In accordance with the approved plans
3. Footpath conditions
4. Public Protection Conditions
5. Biodiversity conditions
6. Trunk Road Conditions
7. Heneb
conditions
8. Language Conditions
Supporting documents: