Proposed development for the change of use of
the former Waterloo Inn Public House (A3 use) and part of the former WH Smiths
& USC units (ancillary A1 use) to form 13 no. self-contained residential
flats (C3 use) along with internal alterations and reconfiguration to combine
two existing retail units to provide stalls for retail purposes on the ground
floor.
LOCAL MEMBERS:
Councillor Dylan Fernley and Councillor Nigel Pickavance
Link to relevant background documents
Decision:
DECISION:
To approve subject to conditions:
1. Time - Five years
2. In accordance with the plans
3. Restrict the use class to C3 residential
dwellings only
4. Restrict the construction hours
5. The
objectives of the Green Infrastructure Statement must be implemented
6. Affordable housing condition
7. Welsh name
Note:
Dŵr Cymru
Minutes:
Proposed
development for the change of use of the former Waterloo Inn Public House (A3
use) and part of the former WH Smiths & USC units (ancillary A1 use) to
form 13 self-contained residential flats (C3 use) along with internal
alterations and reconfiguration to combine two existing retail units to provide
stalls for retail purposes on the ground floor.
a)
The Senior Planning Officer highlighted that it was a full application
for a property located within the boundary of the Sub-Regional Centre and
therefore the principle of developing the site had to be considered against
Policy TAI 1 of the LDP. It was reported that the indicative housing supply
level for Bangor over the LDP period was 969 units. During the period between
2011 and 2025, it was noted that a total of 821 units had been completed in the
city and the windfall land bank i.e. sites with extant planning permission on
sites not designated for housing, stood at 164 units in April 2025. While the
provision was already being addressed through the sites in the land bank, in
such circumstances consideration would be given to the units that had been completed
thus far within the Main Centres tier. Policy PS 17 of the LDP stated that 53%
of housing growth would be located within the Sub-Regional Centre and Urban
Service Centres with a shortfall of 135 units in terms of windfall provision
within this tier.
By adding
13 residential units to the housing stock, this development would help to
contribute towards the LDP's housing targets in a way that responded positively
to the requirements of the local housing market and, therefore, it was believed
that the proposal could be accepted under TAI 1 and PS 17 of the LDP. It was
noted that Policy TAI 9 of the LDP approved the sub-division of existing
properties into self-contained flats provided they conformed to a number of criteria discussed in the report. It was believed
that the proposal was acceptable based on the requirements of Policy TAI 9.
Reference
was made to the Housing Mix assessment, which was part of the Welsh Language
Impact Assessment submitted, which noted that the projections of the Gwynedd
Local Housing Market Assessment 2018-2023 showed a continuous growth in the
number of 1 and 2 people households against a consistent shortage of suitable
property. It was highlighted that the assessment indicated that while there was
good provision for the student accommodation market in Bangor, there was a
significant shortage in the young professionals' market for high-quality units.
It was considered that sufficient evidence had been submitted that there was a
local demand for the size and type of units proposed here and, therefore, that
the housing mix was appropriate and complied with policy TAI 8.
The site was
located in a mixed-use area, which included residential uses as well as
commercial and business uses. It was not considered that there would be a
significant impact on the residential amenities of nearby properties in terms
of over-looking or loss of privacy. Following a conversation with the
Conservation Officer and amendments to the plans, it was concluded that the
development would not be detrimental to the built quality of the Conservation
Area and therefore, it was acceptable under policy AT 1. While concerns had
been raised by the Public Protection Service regarding the potential impact of
noise on residents, it was noted that ensuring adequate insulation was a matter
for Building Control. Given the mixed nature of the area, it was not considered
that general noise levels were unacceptable, and any incidents of unusual noise
would be treated as a nuisance; it was considered that the proposal was
acceptable in terms of residential amenities and complied with policies PCYFF
2, PCYFF 3 and TAI 9 of the LDP.
Although there was no provision for
on-site parking, the proposal was considered acceptable given its central
location, accessibility to alternative transport and adjacent parking provision
and therefore, it complied with policies TRA 2 and TRA 4. The building was
located in Bangor City centre and within a site that could be described as
sustainable; Bangor bus station was within a 5 minute walk of the site with a
frequent public transport service, shops were within comfortable walking
distance of the site and the train station was approximately 10-15 minutes
walking distance which was also served by public transport and taxis; the
proposal complied with the requirements of Policies PS 4 and PS 5 of the LDP.
Reference was made to Policy TAI 15
which assessed the provision of affordable housing for developments of two or
more units in Bangor, and in this case, three affordable units out of a total
of 13 would be required. However, given the size and value of the flats, their
prices were not expected to rise out of the reach of local residents and all
the flats would be "affordable by design", but it was noted that
there was an intention to impose a condition to ensure three affordable units
in case there was a change in market values, in compliance with Policy TAI 15.
With the development being one for
more than 10 living units, a Language Impact Assessment was submitted to
support the application. It was considered that the proposal would have a
neutral linguistic effect, by meeting local demand for flats and the needs of
the community. With appropriate
conditions, it was considered that the application would meet the requirements
of Policy PS 1 of the LDP.
The site
was located within the boundary of Bangor City Centre
and the Main Shopping Area and national and local policies seek to protect and
enhance the vitality and viability of town centres and their retail, service
and social functions. In this case, commercial use would continue
on the ground floor, retaining an active front facing shop window. It
was not considered that the development would undermine the role of the Town
Centre as it would carry out business activity that would contribute to the
viability of the high street; the application was acceptable under the
requirements of policies PS 15, MAN 1 and MAN 2 as they related to the
protection of the role of town centre retail.
It was
considered that the proposed use was acceptable and would not impair the area's
character or cause unacceptable harm to amenities. It was recommended that the
application be approved with conditions.
b)
It was proposed
and seconded to approve the application.
c)
Taking
advantage of the right to speak, an agent on behalf of the applicant noted the
following observations:
·
The flats responded to the need for self-sufficient dwellings.
·
The retail units and pub had been marketed since 2022 - there had been
no interest or viewings to the pub.
·
It would be good to get the building back into use - it would add to the
vibrancy of the high street and the city centre.
·
The proposal
offered 1-, 2- and 3-bedroom mixed units.
·
Good links with employment, amenities, shops and public transport.
·
Three affordable units were proposed in accordance with policy
requirements.
·
Multi-agency units would not be self-sustaining.
·
It would meet the need for housing locally.
·
The retail
units on the ground floor would be smaller and affordable.
·
A local consultation had been carried out - there were no objections to
the proposal, subject to conditions.
·
Research had
been received which examined the loss of community properties and large retail
units.
·
A positive
investment for the city.
ch) During the ensuing
discussion, the following observations were made by Members:
·
Disappointed
that an iconic pub was closing in the County.
·
The high street was fast becoming a street of bed-sits.
·
The proposal was an acceptable use of a vacant building – flats and
protected a retail site.
·
There was a
need to regenerate the High Street.
In
response to a question about a lack of response again from Bangor City Council,
the Assistant Head of Department stated that he had contacted Bangor City
Council directly noting the Committee's concern that the City Council was not
offering a response to planning applications in the city. He highlighted that
he had not received a response to his request and added that while there were
no legal implications for offering comments, he stated that if the Committee
wished him to contact again, that he would be happy to do so.
In
response to a question about concerns that there was insufficient information
in the report about the pub's viability, and it was sad to see another pub
closing in the County, it was noted that the pub had closed since 2022 and that
evidence of the pub's marketing had been included in the report.
In
response to a question regarding black plates (x5) which appeared to provide
structure and maintenance to the building, it was noted that the application
did not state that they were retained or not, but that this would be an issue
to be considered as a safety issue by building control.
RESOLVED: To approve subject to
conditions:
1. Time
- Five years.
2. In
accordance with the plans.
3. Restrict
the use class to C3 residential dwellings only.
4. Restrict
the construction hours.
5. The
objectives of the Green Infrastructure Statement must be implemented.
6. Affordable
housing condition
7. Welsh
name
Note:
Welsh Water
Assistant
Head of Department to contact Bangor City Council again.
Supporting documents: