Temporary
operation of a meteorological mast and ancillary structures for a period of up
to five years.
LOCAL
MEMBER: Councillor Elwyn Edwards
Decision:
DECISION: To
approve
To
delegate powers to the Senior Planning Manager to approve the application,
subject to the following conditions:-
Conditions
1.
The development must commence within five
years of the date of this decision.
2.
The development must be undertaken in
accordance with the following approved plans and documents.
3.
The mast hereby approved must be taken down
and the land restored to its previous condition within 5 years to the date of
commission. The applicant must inform the Local Planning Authority of the
commission date within 3 months of that date.
4.
Prior to the commencement of the development
(including the land work and clearance of vegetation), a detailed Method
Statement that describes how the site will be returned to its original
condition will be submitted to the Local Planning Authority, and it must be
approved in writing. The approved
measures should be adhered to and implemented in full.
5.
No development, including site clearance,
will commence until a Construction Environmental Management Plan (CEMP) has
been submitted to the Local Planning Authority and approved in writing by it.
6.
No development or phase of the development to
commence until a Breeding Bird Protection Plan (BBPP) has been submitted to the
Local Planning Authority and approved by it.
7.
No development shall be permitted until a
biodiversity enhancement plan has been submitted to the Local Planning
Authority and approved in writing by it. The development will be carried out in
accordance with the approved details.
8.
No clearance of vegetation, land work or
building activities will be permitted during the bird nesting season (1 March
to 31 August inclusive) unless this has been agreed in writing beforehand with
the Local Planning Authority. When work
is required during this period, a survey of the site must be undertaken by a
competent ecologist no more than 48 hours prior to commencing the work. Any
recommendations given must be fully implemented, and if operational nests are
found, an appropriate protection zone must be established and maintained until
the chicks have fledged.
9. Devices to divert birds must be installed on each external supporting
wire of the mast at a distance of no more than 2
metres in length along them all prior to the mast becoming operational. These
devices must be maintained throughout the development's lifespan. Any damaged,
removed or disconnected devices must be replaced within one month of finding
them.
10. Prior to commencement
of building any meteorological masts, or using any building equipment or
temporary structure(s) of 50 metres or more in height (above ground level), the
developer must submit an aviation lighting scheme to be approved by Cyngor Gwynedd
jointly with the Ministry of Defence, noting how the development will be
illuminated throughout its lifespan to maintain the requirements of civil and
military flying as determined necessary by the Ministry of Defence.
This should include:
a) The details of any building equipment and
temporary structures with a total height of under 50 metres or more (above
ground level) that will be used during the construction of the meteorological
mast, together with the details of any aviation warning lights that will be
installed on them; and
b) Location and height of every
meteorological mast within the development, noting those with aviation warning
lights, location of the lights on the mast, the type of lights to be used, and
the lighting performance specifications.
Then the developer must install the lights as
noted in the approved aviation lighting plan, and the lights will continue to
be operational throughout the development's lifespan.
11. The developer must
inform the Ministry of Defence in writing, at least 14 days prior to the
commencement of the work, of the following information:
a) the commencement date to erect the
meteorological mast(s);
b) the maximum height of any building
equipment used when erecting the mast;
c) date when any meteorological mast comes
into use;
d) latitude, longitude and maximum height of
each meteorological mast.
12. The
Ministry of Defence must also be informed of any changes to this information
and following the completion of the construction work.
Minutes:
Temporary operation
of a meteorological mast and associated structures for a period of up to five
years.
Attention was drawn to the
late observations form that included observations from Natural Resources Wales
(NRW) agreeing with the conclusion of the Habitat Regulations Assessment.
a)
The
Senior Planning Officer - Minerals and Waste highlighted that the application
related to the erection and operation of a temporary anemometer mast for a
period of five years on an upland near the summit of Pen y Bwlch Gwyn. The mast
would be a steel lattice structure up to 100m high, supported by guy wires and
equipped with meteorological monitoring equipment, including anemometers and
weathervanes. It was noted that many important landscape and conservation
designations were relatively close - Eryri National Park, the proposed boundary
of Glyndŵr National Park and the Clwydian Range and Dee Valley AONB; this site was also
within the vicinity of several designated European sites, such as the SAC, SPA
and RAMSAR sites - River Dee and Llyn Tegid, Migneint-Arenig-Dduallt and Berwyn.
In the context of the
principle of the proposal, it was noted that there was no specific policy in
the LDP relating to meteorology masts. However, the purpose of the proposed
mast was to collect meteorology data to assess the viability of the potential wind
energy development in the future, and therefore the proposal was considered as
a type of infrastructure associated with a renewable energy development against
Strategic Policy PS 7 of the LDP; a policy that supported renewable energy
technologies, as well as Policy ADN 1 that related to wind energy developments
on land.
It was reported,
since adopting the LDP, the Strategic Search Areas noted in TAN 8 had been
replaced by the Pre-assessed Areas noted in Future Wales: The National Plan
2040. Reference was made to Policy 17 of Future
Wales which established presumptions in favour of wind energy developments on a
large scale within those areas, whilst Policy 18 provided the relevant criteria
to assess such proposals.
It was reiterated
that the site in question had been located outside of the nearest Pre-assessed
Area for wind energy. However, Future Wales and Planning Policy Wales did not
prevent wind energy developments or associated infrastructure outside those areas.
Instead, the Pre-assessed Areas stated where the Welsh Government had assessed
that large-scale wind developments could be accepted in principle, without
preventing consideration of proposals in other locations.
In addition, Planning
Policy Wales stated that energy-generating projects on the land with a capacity
of between 10MW and 350MW were determined by Welsh Ministers through the
Developments of National Significance (DNS) process and assessed against the Future
Wales policies. To this end, it was noted that a notice of intention had been
submitted to Welsh Ministers for a potential wind farm on the same site.
However, the existing application does not relate to the wind farm itself and
weighting could not be given to the principle of that development when
assessing the application. The anemometer mast must be considered on its own
merits.
It was emphasised
that the proposal related to a temporary structure for a five-year period only.
Planning conditions would ensure that the mast, the guy wires and all
associated infrastructure were taken from the site and
the land would be restored to its previous condition at the end of the period.
Consequently, it was considered that the development was not likely to lead to
permanent or long-term impacts on the site. It was also considered that the
principle of installing a temporary anemometer mast for the purpose of
gathering meteorology data was acceptable in policy, subject to a detailed
consideration of the relevant impacts, including landscape, visibility,
biodiversity, heritage, amenities and other technical matters.
In the context of
visual matters, it was noted that policies PCYFF 3, AMG 2 and AMG 3 of the LDP
were relevant when assessing the impact of the development on the character of
the landscape and visual amenities. The site would be located on high land
within the 'Cefnwlad y Bala' Special Landscape Area,
and in a location that was seen from parts of Eryri National Park. A Landscape
and Visual Impact Assessment (LVA) was submitted to support the application, as
well as additional information on viewpoints. Following reviewing the
information, it was reported that NRW was satisfied that sufficient evidence
had been provided to assess the impacts on the landscape and the visual amenities, and concluded that the development would not harm
the character of the landscape, the visual amenity nor the special
characteristics of Eryri National Park. It was acknowledged that the 100m high
mast would be visible over a wide area and it would present an element of human
work in some open views. However, the assessment showed that small or low
impacts would arise in most perspectives, with some moderate or moderate-low
impacts in a limited number of sensitive locations; the mast's slender lattice
structure, as well as its temporary nature, would reduce its general visual
impact.
Given the view of
NRW, the findings of the Landscape and Visual Impact Assessment, and the
temporary nature of the development, it was considered that the proposal would
not lead to unacceptable impacts on the landscape or visual amenities and it
would comply with the requirements of policies PCYFF 3, AMG 2 and AMG 3 of the
LDP.
In the context of
Residential Amenities and given the distance between the site and the nearest
residential property, as well as the relatively simple nature of the
development, the narrow design of the mast and the land's topography influence,
it was not considered that it would have an unacceptable impact on the visual
amenity or general residential amenities. Consequently, it was considered that
the development complied with the requirements of Policy PCYFF 2 of the LDP,
which sought to ensure that developments did not have a significant detrimental
impact on the health, safety or amenities of nearby residents.
In relation to
proposed aviation lights, it was noted that the lights would be low density
infra-red lights and therefore it was not considered that they would have a
significant visual impact or cause unacceptable light pollution to nearby
properties.
Observations were
received regarding the possibility of noise, but because the mast included very
few mobile parts, it was not expected for it to generate substantial
operational noise. In addition, any temporary disruption during the
construction phase would be limited in terms of its length and would be
controlled through standard construction practices. On this basis, it was
considered that the proposal was acceptable in terms of amenities and complied
with Policy PCYFF 2.
Given Transport
Matters, it was noted that the proposed development did not include any changes
to the existing access arrangements and it was not
anticipated that it would lead to a significant increase in traffic movements
during the operational period. Consequently, the proposal would not have a
detrimental impact on the safety or implementation of the local road network
and therefore, in terms of transport, would comply with the requirements of
Policies PS 4 and TRA 4 of the LDP.
In the context of
Ecological Matters, it was reported that the site was located relatively close
to many designated European sites, including the Dee River and Llyn Tegid SAC,
the Migneint-Arenig-Dduallt
SAC/SPA, the Llyn Tegid RAMSAR site and the Berwyn SAC/SPA. NRW noted that the
main risks arising from the construction period, especially in relation to
pollution, would be sedimentation and disruption to water courses. However, it
was considered that these risks could be controlled by ensuring a Construction
Environmental Management Plan (CEMP) condition. NRW confirmed, subject to
implementing appropriate mitigation measures, that the development would not
have a detrimental impact on the integrity of the designated sites. It was also
not considered that the development would likely lead to significant impacts in
terms of nutrients or water quality during the operational phase.
From an ecological
perspective, although concerns had been raised in relation to nesting birds,
specifically the possibility that the mast could act as a perch for predators,
it was considered that this matter could be controlled through a Breeding Bird Protection
Plan (BBPP). NRW and the Council’s Ecologist were satisfied that the
development was unlikely to have a significant impact on protected species or
sensitive habitats, with a very limited habitat loss deriving from the
proposal. The Habitat Regulation Assessment came to the
conclusion that the main risks to European sites could be controlled,
which related mainly to the construction phase and breeding birds, through
appropriate planning conditions, including a Construction Environmental
Management Plan (CEMP) and a Breeding Bird Protection Plan (BBPP). As a result,
it was considered that the development would not have a detrimental impact on
the integrity of any European site, either in isolation or in conjunction with
other plans or projects. Subject to appropriate conditions that ensured the
implementation of the mitigation measures and the proposed biodiversity
improvements, it was considered that the development was acceptable and
complied with Policies PS 19, AMG 3, AMG 5 and GWA 1 of the LDP.
There were no
heritage designations near the site and CADW confirmed that they had no
objection to the development. It was considered that the mast would not have an
impact on designated heritage assets because the land's topography restricted
the visible connection between it and those assets; the proposal complied with
the requirements of Policy PS 20 of the LDP.
It was highlighted
that the site was located within the Low Flying Area 7 training area. The
Ministry of Defence confirmed that they had no objection to the development,
subject to imposing standard conditions relating to obstruction lights for
aviation, chartered aviation and relevant safety requirements. It was
considered that these conditions were necessary to ensure that the mast would
not have a detrimental impact on aviation safety or military low flying
operations and therefore complied with the requirements of Policy PCYFF 2 of
the LDP.
As the development
did not reach the threshold requiring a Welsh Language Statement, and due to
its temporary and limited nature, it was not considered that it would have a
detrimental impact on the Welsh language and therefore complied with Policy PS
1 of the LDP and the Maintaining and Creating Unique and Sustainable
Communities SPG.
It was considered
that the principle of the development was acceptable as associated
infrastructure for renewable energy and it would not lead to long-term impacts
because the mast would be removed, and the site restored at the end of a 5-year
period. It was not considered that it would have an unacceptable impact on the
landscape, amenities, biodiversity, designated European sites, heritage,
aviation safety, subject to imposing appropriate conditions; the development
complied with the relevant local and national policies
and the recommendation was to approve subject to conditions.
b)
The
Local Member noted that he agreed with the recommendation.
c)
It
was proposed and seconded to approve the application.
d)
During
the ensuing discussion, the following observations were made by Members:
·
There
were sufficient conditions to ensure control
·
This was one mast to gather
data about wind speed - what would come in its wake? A wind farm and ugly
pylons that would try to connect to the national grid
RESOLVED: To delegate powers to the
Senior Planning Manager to approve the application, subject to the following
conditions:
1.
The
development should commence within five years of the date of the decision.
2.
The
development must be undertaken in accordance with the following approved plans
and documents.
3.
The mast
hereby approved must be taken down and the land restored to its previous
condition within 5 years to the date of commission. The applicant must inform
the Local Planning Authority of the commission date within 3 months of that
date.
4.
Prior to
the commencement of the development (including the land work and clearance of
vegetation), a detailed Method Statement that describes how the site will be
returned to its original condition will be submitted to the Local Planning
Authority, and it must be approved in writing.
The approved measures should be adhered to and implemented in full.
5.
No
development, including site clearance, will commence until a Construction
Environmental Management Plan (CEMP) has been submitted to the Local Planning
Authority and approved in writing by it.
6.
No
development or phase of the development to commence until a Breeding Bird
Protection Plan (BBPP) has been submitted to the Local Planning Authority and
approved by it.
7.
No
development shall be permitted until a biodiversity enhancement plan has been
submitted to the Local Planning Authority and approved in writing by it. The
development will be carried out in accordance with the approved details.
8.
No
clearance of vegetation, land work or building activities will be permitted
during the bird nesting season (1 March to 31 August inclusive) unless this has
been agreed in writing beforehand with the Local Planning Authority. When work is required during this period, a
survey of the site must be undertaken by a competent ecologist no more than 48
hours prior to commencing the work. Any recommendations given must be fully
implemented, and if active nests are found, an appropriate protection zone must
be established and maintained until the chicks have fledged.
9.
Devices to divert birds must be installed on each
external supporting wire of the mast at a distance of no
more than 2 metres in length along them all prior to the mast becoming
operational. These devices must be maintained throughout the development's
lifespan. Any damaged, removed or disconnected devices must be replaced within
one month of finding them.
10.
Prior to commencement of building any
meteorological masts, or using any construction equipment or temporary
structure(s) of 50 metres or more in height (above ground level), the developer
must submit an aviation lighting scheme to be approved by Cyngor Gwynedd
jointly with the Ministry of Defence, noting how the development will be
illuminated throughout its lifespan to maintain the safety requirements of
civil and military aviation as determined necessary by the Ministry of Defence.
This should include:
a) The
details of any construction equipment and temporary structures with a total
height of 50 metres or more (above ground level) that will be used during the
construction of the meteorological mast, together with the details of any
aviation warning lights that will be installed on them; and
b)
Location and height of every meteorological mast within the development, noting
those with aviation warning lights, location of the lights on the mast, the
type of lights to be used, and the lighting performance specifications.
Then the developer must install the
lights as noted in the approved aviation lighting plan, and the lights will
continue to be operational throughout the development's lifespan.
11. The developer must inform the Ministry of
Defence in writing, at least 14 days prior to the commencement of the work, of
the following information:
a) the
commencement date to erect the meteorological mast(s);
b) the maximum height of any
construction equipment used when erecting the mast;
c) the
date when any meteorological mast comes into use;
d) the
latitude, longitude and maximum height of each meteorological mast.
12. The Ministry of Defence must also be informed
of any changes to this information and following the completion of the
construction work.
Supporting documents: