David
Mathews (Land and Property Programme Manager) to present the report.
Decision:
To approve the request to extend the validity period to complete the
Grant Funding Agreement by three months to the 1st of October 2026.
Confirm that the Portfolio Director is authorised to take all necessary
operational steps to proceed with and complete the Grant Funding Agreement
within the extended validity period, subject to customary legal, financial,
procurement and governance requirements.
To confirm that the Sub-Committee's approval
is valid until 1st October 2026 and should the project not proceed to a signed
Grant Funding Agreement by this date, it will be required to return and
resubmit the business case to the Sub-Committee for approval.
Minutes:
The report was
presented by the Land and Property
Programme Manager.
DECISION
To approve the request to extend the validity period to complete the
Grant Funding Agreement by three months to the 1st of October 2026.
To confirm that the Portfolio Director is authorised to take all
necessary operational steps to proceed with and complete the Grant Funding
Agreement within the extended validity period, subject to customary legal,
financial, procurement and governance requirements.
To confirm that the Sub-Committee's approval is valid until 1st October
2026 and should the project not proceed to a signed Grant Funding Agreement by
this date, it will be required to return and resubmit the business case to the
Sub-Committee for approval.
REASONS FOR THE DECISION
To
seek the Sub-committee's approval to extend the review date for the Grant
Funding Agreement by three months for the reasons set out in the report.
DISCUSSION
Members were reminded
that this project had been approved by this Sub-committee at its meeting on 3
October 2025, approving a 6-month validity period to discuss and deliver a
grant funding agreement for the project.
It was acknowledged
that those requirements could not be delivered within the timetable provided by
the Sub-committee, therefore the item was re-submitted in Spring 2026 to
receive three additional months to deliver the discussions and receive a grant
funding agreement. There was confidence that the discussions could be achieved
within three months, but it was confirmed that the discussions had not been
completed on this project. Similarly, it was explained that discussions were
ongoing on the Gogledd Môn Sites and Premises project, and further discussions
had been achieved with the Local Authority on that project.
It was reported that
the Freeport Gateway project was now in a procurement process, with the
tendering process underway until 7 August. It was noted that the Isle of
Anglesey County Council would score the tenders before appointing the
successful company before the end of the month. It was elaborated that the hope
was to complete discussions with the local authority in September 2026, for the
work to commence in October.
It was asked to
extend the validity period for three months to allow this schedule to take
place, and for the project to proceed.
During the discussion, the following
observations were made:-
It was considered
that a 3-month extension was not a substantial period of time.
The need to ensure that any extension was sufficient to ensure that no need
arose to return to the Sub-committee for a subsequent extension was discussed.
In response to the observations, the Land and Property
Programme Manager emphasised that lessons had been learned in conducting
discussions on the Gogledd Môn Sites and Premises project to save time on
discussions. Assurances were given that this would be in place for this
project, declaring confidence that the project would develop in a timely manner
should the extension be approved.
It was confirmed that there was a wish to see
this project succeeding, in the hope that the discussions would come to
fruition in a timely manner.
The members expressed
their thanks for the report.