• Calendar
  • Committees
  • Community Councils
  • Consultations
  • Decisions
  • Election results
  • ePetitions
  • Forthcoming Decisions
  • Forward Plans
  • Library
  • Meetings
  • Outside bodies
  • Search documents
  • Subscribe to updates
  • Your councillors
  • Your MPs
  • Your MEPs
  • What's new
  • Agenda item

    Application No C25/0946/44/EIA Land Along The A483 Corridor, Porthmadog

    • Meeting of Planning Committee, Monday, 28th September, 2026 1.00 pm (Item 7.)

     

    The extension of the existing Wern Cables Sealing End Compound (CSEC) including a new permanent access; a new Minffordd CSEC and Tunnel Head House (THH) with permanent access; the removal of the existing Garth CSEC; installation of new 400 kilovolt (kV) cables to replace redundant 400 kV and 132 kV cables; and other associated infrastructure and ancillary works. 

     

    LOCAL MEMBERS:

     

    Councillor Nia Jeffreys

    Councillor Gwilym Jones

    Councillor June Jones

    Councillor Meryl Roberts

     

    Link to relevant background documents

     

    Decision:

    DECISION: To permit

     

    1.     Time Limit  

    The development must commence within 5 years of the date of the permission.

    2.     Approved Schemes        

    The development to be carried out in accordance with the approved plans and documents.

    3.     Hours of Work:     

    Limits construction work hours and manages out-of-hours operations.

    4.     Piling

    Requires non-percussive piling methods and restricts piling hours. 

    5.     Lighting      

    Requires approval of a lighting scheme to protect bats and control light spill before operational lighting is installed. 

    6.     Enclosures 

    Requires approval of colours and finishes for fences, walls, gates and other boundary treatments.

    7.     Contamination      

    Requires investigation and remediation of any previously unidentified contamination encountered during development.    

    8.     Flood Mitigation

    Requires approval and implementation of a temporary flood mitigation scheme for construction works.  

    9.     Wern Registered Park and Garden     

    Requires a mitigation/offsetting scheme for impacts on the Wern Registered Park and Garden. 

    10. Habitat Management and Monitoring Plan (HMP)   

    Secures habitat compensation, biodiversity net benefit, habitat monitoring and INNS management over the long term.  

     

    11. Landscape and Ecological Management Plan (LEMP)     

    Secures landscape restoration, planting, habitat management, ecological monitoring and long-term maintenance. 

    12. Archaeological Investigation (WSI)    

    Requires archaeological investigation and recording before groundworks commence.  

    13. Archaeological Reporting         

    Requires submission of an archaeological report and archive following fieldwork. 

    14. Materials and Waste Management Plan

    Secures sustainable management, reuse, recovery and disposal of excavated materials and waste.

    15. Public Rights of Way      

    Requires management arrangements for public rights of way and National Cycle Route 8 during construction.

    16. Construction Method Statement        

    Prior to the commencement of any works on site, Construction Method Statements (CMS) and Risk Assessments shall be submitted to the satisfaction of the Overseeing Organisation for the Strategic Roads Network (SRN).

    17. Carriageway reinstatement design     

    Prior to the commencement of any works on site a carriageway reinstatement design and pavement specification shall be submitted to the satisfaction of the Welsh Government as Overseeing Organisation for the Strategic Roads Network.

    18. Welsh Water Assets       

    Requires surveys and protection/diversion arrangements for water and sewerage infrastructure. 

    19. Surface Water Drainage

    Prevents connection of surface water to the public sewer network.

    20. Welsh language signs    

    Requires development-related signage to be Welsh or bilingual with Welsh given priority. 

    21. Minffordd Tunnel Head House CTMP 

    Requires a package-specific Construction Traffic Management Plan for the Minffordd Tunnel Head House works. 

    22. Minffordd Tunnel Head House CEMP 

    Requests a package-specific Construction Environmental Management Plan for the Minffordd Tunnel Head House works. 

    23. Minffordd Tunnel Head House HMP   

    Requests a package-specific Habitat Management Plan for the Minffordd Tunnel Head House works.

    24. CTMPs for the Main Work Packages   

    Requires separate Construction Traffic Management Plans for the Wern CSEC, Garth CSEC, Minffordd CSEC and Glaslyn Cables work packages.   

    25. CEMPs for the Main Work Packages

    Requires separate Construction Environmental Management Plans for the Wern CSEC, Garth CSEC, Minffordd CSEC and Glaslyn Cables work packages.

    26. Community facilities restoration plan

    Bodawen Playground and Ysgol Eifionydd.

     

    Note: Amendment of Dŵr Cymru/Welsh Water conditions in line with the late representations received

     

    Minutes:

    Extension to the existing Wern cable sealing end compound including a new permanent access, a new sealing end compound and tunnel head house with permanent access at Minffordd; removal of the existing Garth sealing end compound; installation of new 400 kilovolt (kV) cables to replace redundant 400 kV and 132 kV cables; and related infrastructure and ancillary works.  

     

    Attention was drawn to the late observations form, specifically a comment from Welsh Water on the wording of the condition. Reference was made to a correction that comments on the Railway (paragraph 5.299 - 5.303 of the report), had been submitted by the Welsh Highland Railway Ltd, which operates the Welsh Highland Heritage Railway.

     

    a)           The Senior Minerals and Waste Planning Officer highlighted that the Project was a part of the broader network transmission upgrades required to facilitate the work of connecting 50 Gigawat (GW) of offshore wind energy by 2030. Increasing capacity on the existing transmission line between Pentir and Trawsfynydd substations has been identified as a step that urgently needs to be taken to provide more transmission capacity. This is acknowledged by Ofgem, the national energy regulators, who have identified the necessary works as an Accelerated Strategic Transmission Investment.

     

    The proposed work of the application included encompassing 106.4 hectares and measured approximately 6km between the CSEC (Cable Sealing End Compounds) of Wern and Minffordd. The path of the work passes through the Porthmadog Roundabout, under the A487 Porthmadog Bypass, and crosses the Welsh Highland Heritage Railway (WHHR) and Ffestiniog and Welsh Highland Railways (FWHR); continuing to the north of Clwb Chwaraeon Madog before passing again under Porthmadog Bypass. It will cross the Glaslyn Site of Special Scientific Interest (SSSI) and continue eastwards towards its end point at the existing Garth CSEC. The proposed work is divided into the following elements; Wern CSEC, Glaslyn Cables, Garth CSEC, Tunnel Head House and Minffordd CSEC.

     

     

    It was reported that the application submitted was an Environmental Impact Assessment application, which has considered all developments that are a part of the whole Reinforcement Project between Pentir and Trawsfynydd.

     

    In terms of the principle of the development, it was noted that the new cables would use XLPE technology, to replace the existing oil-filled cable system and therefore that there are advantages in terms of modernising the resilience of the network, as well as reduce the environmental risks associated with the existing oil cables. It was reiterated that the project was also a part of the broader network work required to facilitate progress in the renewable energy provision, therefore the principle is afforded national policy support, including Future Wales and Planning Policy Wales, which acknowledges the need for additional grid infrastructure to support the switch to low carbon energy.

     

    In the context of the landscape and visual amenities, as the cables are being installed underground, it was considered that the biggest visual impacts would happen during the construction period. It was explained that the Landscape and Visual Appraisal identifies temporary moderate and substantial detrimental impacts in parts of the corridor, including in relation with the setting of Eryri National Park. To that end, these are local and temporary impacts with the land, and after installing the cables, will be restored. It was reiterated that neither Natural Resources Wales (NRW) nor the Eryri National Park Planning Authority objected to the proposal based on its impact on the National Park. It was also noted that a condition required a detailed Landscape and Ecological Management Plan, which will manage the restoration work, planting, tree preservation and long-term management.

     

    In the context of ecology and biodiversity, which is one of the most sensitive considerations of the application, it was reported that the path crosses or ventures close to several sites of ecological importance, most notably, the Glaslyn SSSI and the Coedydd Derw and Ystlumod Meirion SAC. Around 1.6 hectares of habitat within the Glaslyn SSSI will be temporarily affected, as well as a limited permanent loss. It was noted that the design had used Horizontal Drilling, or HDD, in several of the most sensitive locations in order to pass under habitats, watercourses and infrastructure, instead of cutting through them. The Council's Biodiversity Unit raised substantial concerns regarding restoring habitats, water voles, badgers, tree and hedgerow loss, lights and the possibility of affecting the flightpath of the lesser horseshoe bat.

     

    As the work crosses a SAC, the Council conducted a Habitats Regulations Assessment.  The Propriety Assessment concluded, with relevant mitigation measures, that the proposal will not have a detrimental impact on the integrity of the relevant SACs. Following the consultation with NRW on the Propriety Assessment, agreement was reached on the conclusion, subject to imposing mitigation measures which includes substantial management via conditions, including managing and monitoring long-term habitats, LEMP (Landscape and Ecology Management Plan), control of invasive species, lights and ecological surveys.

     

    When discussing noise and vibration, it was noted that the Environmental Statement acknowledges that some construction activities can create substantial noise impacts temporarily, in particular the HDD drilling work in some locations in Porthmadog and Minffordd with the possibility that some HDD drilling operations will last for 24 hours for technical and safety reasons. It was highlighted that the Public Protection Service has raised concern because not all operational details have been completed - this includes the exact timing of the noisiest work, mitigation measures and monitoring arrangements. However, the officers were of the view that these matters can be managed through a CEMP condition in a specific pack for every work area, noise and vibration management plans, and, as appropriate, the process of Section 61 of the Pollution Control Act 1974. The Planning officers did not disregard the potential impacts; instead, they recommended that detailed controls are in place before every relevant work pack commences.

     

    In the context of flooding, it was noted that an extensive proportion of the work is in an area at flood risk with initial modelling work showing that the temporary construction infrastructure could increase flood levels in some areas of Porthmadog and Tremadog. Consequently, additional hydraulic modelling was conducted, and a temporary mitigation plan was developed with the strategy, including pumping arrangements to manage the increase in flood risk during the main construction work. The model was reviewed by NRW, and they did not object to the development, subject to securing the mitigation plan by means of a condition. Confirmation was received from the Lead Local Flood Authority, expressing that they did not have concerns about the content of the Flood Consequence Assessment. The officers were of the opinion that the proposal could comply with the requirements of TAN 15.

     

    In terms of traffic matters, an increase in construction traffic would be expected due to the development, as well as creating temporary new accesses. Attention was drawn to the Environmental Statement, which projected 148 two-way vehicular movements per day, including around 100 HGV movements, for the Glaslyn Cables work. The assessment also notes proportionate increases in HGV traffic along some roads, but the increase in the total traffic remains relatively small. Following discussions with the applicant, the North and Mid Wales Trunk Road Agent confirmed that permission can be granted, subject to conditions that would ensure traffic management plans, construction method statements and risk assessments in relation to the Strategic Roads Network. A condition would also secure detailed control of the Public Rights of Way and National Cycling Route 8 during the work.

     

    The main elements of heritage can be seen in the Wern area with the assessment noting the substantial detrimental impact on the Wern Registered Historic Park and Garden and on the setting of the mansion house. It was reported that Cadw had raised a substantial concern about this originally, but following further discussions, they were satisfied that the impact can be addressed by means of a mitigation or counterbalancing plan, secured through a planning condition - as a result they no longer objected to the advice of approving the application. It was reiterated that conditions secured the archaeological Written Research Plan and subsequent recording work for the remainder of the development.

     

    In coming to a conclusion, the officer noted that the plan was major, and noted, obviously there would be substantial construction impacts, temporary in some locations. All landscape, amenity, noise and vibration, traffic, flooding, ecology and biodiversity, historical environment and public rights of way impacts were considered, as well as the substantial pressures placed on the strategic importance of the electricity infrastructure, modernising the network, underground nature of a vast part of the development, temporary nature of many of the impacts, and the proposed mitigation, restoration and enhancement measures.

     

    Having weighed up all impacts against the strategic need and public interest, the officers recommended approving the application, subject to imposing mitigation measures and material planning conditions.

     

    b)           Taking advantage of the opportunity to speak, a speaker on behalf of the applicant noted

    ·        That the application was a part of the Pentir Trawsfynydd project to reinforce and refurbish the existing electricity lines.

    ·        The proposal will include changing the underground cables between the Wern, Penmorfa and Garth, Minffordd site.

    ·        The work will be a combination of creating open trenches and non-trench techniques which have been designed so that they cause as little disruption as possible.

    ·        Work would be done to extend the existing infrastructure on the Wern site and build a new cable compound in Minffordd - it will be a link site for underground and overground cables.

    ·        The foundations of the Garth site will be decommissioned.

    ·        Having completed the construction work, the temporary work areas will be restored, and biodiversity will be enhanced in locations off the site in the local area.

    ·        That the project will be a part of the upgrade to the national grid - a major transformation to the UK's electricity network.

    ·        The Welsh Government has noted that this is an important plan that will improve the reliability and security of the electricity supply and supports Wales's ambition to meet 70% of the renewable source electricity needs by 2030.

    ·        Planning Policy Wales acknowledges that an effective electricity network is essential in order to achieve the renewable and low-carbon objectives of Wales.

    ·        The proposal will provide an additional essential electricity transmission capacity in North Wales, assisting to connect with renewable energy distribution which is generated now and in the future.

    ·        That the proposed development corresponds with local and national policies and the company has worked with stakeholders to ensure that no key matters remained unresolved in relation to the application.

    ·        There were no objections by statutory stakeholders.

    ·        The proposed development is essential infrastructure that will contribute to achieving the Welsh Government's renewable energy goal.

    ·        Important that the connection has been upgraded and operational by 2030 to achieve this ambition.

     

    c)               Taking advantage of the right to speak, the local member, Councillor Nia Jeffreys (Porthmadog East Ward), made the following comments:

    ·        Thanked officers for the work.

    ·        That she did not object to the application, nevertheless, took the opportunity to highlight some comments raised by residents in her ward, such as the unique ecology of Glaslyn, wildlife and birds, the Cob area.

    ·        That mitigation measures need to be secured during the construction period to reduce the impact on local people - issues such as traffic, travel, noise and dust.

    ·        ⁠That Bodawen Playing Field was very important to the children of Porthmadog and Tremadog and so sought assurances that the playing field would be reopened as soon as possible after the work was completed - the same was the request regarding the Ysgol Eifionydd playing fields - a request not to close the fields for too long.

     

    In response to the comments regarding the playing fields, the Officer referred to the agreement reached with Porthmadog Town Council that everything would be reinstated after the completion period, but that it would be possible to impose an additional, more detailed condition, to secure control over the re-installation of the equipment.

     

    Taking advantage of the right to speak, the local member, Councillor Gwilym Jones (Porthmadog West Ward), made the following comments:

    ·        That he agreed with the comments of Cllr Nia Jeffreys, particularly the comment on Cae Bodawen as discussions had been held with the Town Council and the National Grid. ⁠

    ·       That assurances were needed that the old cables did not contain polychlorinated biphenyl compound, which is material that was used in electrical equipment in the 1970s - although he had discussed this and had obtained assurances that forever chemicals, as they were commonly referred to, were not in the old cables, no reference to this matter could be seen in the report.

     

    ch)    It was proposed and seconded to approve the application in accordance with the recommendation.

     

    d)            During the ensuing discussion, the following observations were made by members:

    ·        Why was Pentir to Trawsfynydd the priority, considering that other areas of the County needed a better connection?

    ·        That the plan appeared to be rushed and despite acknowledging the substantial risks such as traffic, noise and dust, the community risks had not been considered.

    ·        More information was needed on how to mitigate the risks to ensure that the process was less obtrusive to the local community and to nature and ecology in the areas.

    ·        That the Biodiversity Unit had noted insufficient mitigation measures in terms of details regarding the long-term period, suggesting that the situation should be monitored for 25 years, not 5 years. Could the biodiversity conditions be strengthened before it is approved?

    ·        That the scheme ran through a very sensitive area - consistency and fairness was needed when interpreting what a 'sensitive area' was in planning applications.

    ·        That the need had been noted clearly; a bulk of work had been done on the application with several recommendations and conditions to manage it.

    ·        Welcomed the fact that this was an application to underground and not install pylons.

    ·        The national grid, in its current form, was not fit-for-purpose when looking towards the future.

    ·        This was an opportunity to take advantage of green energy.

     

    In response to a comment that the application seemed to be rushed, the officer noted that the application submitted was one that had been prioritised by Ofgem to improve the network between Pentir and Trawsfynydd to facilitate the work of connecting 50 Gigawat (GW) of offshore wind energy by 2030. The Assistant Head of Department reiterated that the application had not been rushed and that it would not have been submitted to the Committee unless it was ready. It was noted that a detailed assessment of every material planning consideration had been thoroughly considered and after weighing-up all material planning considerations, the Planning Authority was of the view that the development was acceptable with further mitigation measures associated to the conditions. He reiterated that the application to upgrade the electricity network was not unique to Gwynedd - that developments were happening across Britain; the application was supported in terms of principle by Welsh Government policies and local policies.

     

    RESOLVED: To approve with conditions

     

    1.     Time Limit           

    The development must commence within 5 years of the date of the permission.

    2.     Approved Plans 

    The development to be carried out in accordance with the approved plans and documents.

    3.     Hours of Work

    Limits construction work hours and manages out-of-hours operations.

    4.     Piling       

    Requires non-percussive piling methods and restricts piling hours. 

    5.     Lighting   

    Requires approval of a lighting scheme to protect bats and control light spill before operational lighting is installed. 

    6.     Enclosures          

    Requires approval of colours and finishes for fences, walls, gates and other boundary treatments.

    7.     Contamination    

    Requires investigation and remediation of any previously unidentified contamination encountered during development.    

    8.     Flood Mitigation

    Requires approval and implementation of a temporary flood mitigation scheme for construction works.  

    9.     Wern Registered Park and Garden      

    Requires a mitigation/offsetting scheme for impacts on the Wern Registered Park and Garden. 

    10.  Habitat Management and Monitoring Plan (HMP)      

    Secures habitat compensation, biodiversity net benefit, habitat monitoring and INNS management over the long term.  

    11.  Landscape and Ecological Management Plan (LEMP)          

    Secures landscape restoration, planting, habitat management, ecological monitoring and long-term maintenance. 

    12.  Archaeological Investigation (WSI)     

    Requires archaeological investigation and recording before groundworks commence.  

    13.  Archaeological Reporting         

    Requires submission of an archaeological report and archive following fieldwork. 

    14.  Materials and Waste Management Plan

    Secures sustainable management, reuse, recovery and disposal of excavated materials and waste.

    15.  Public Rights of Way     

    Requires management arrangements for public rights of way and National Cycle Route 8 during construction.

    16.  Construction Method Statement          

    Prior to the commencement of any works on site, Construction Method Statements (CMS) and Risk Assessments shall be submitted to the satisfaction of the Overseeing Organisation for the Strategic Roads Network (SRN).

    17.  Carriageway reinstatement design      

    Prior to the commencement of any works on site a carriageway reinstatement design and pavement specification shall be submitted to the satisfaction of the Welsh Government as Overseeing Organisation for the Strategic Roads Network.

    18.  Welsh Water Assets      

    Requires surveys and protection/diversion arrangements for water and sewerage infrastructure. 

    19.  Surface Water Drainage            

    Prevents connection of surface water to the public sewer network.

    20.  Welsh language signs   

    Requires development-related signage to be Welsh or bilingual with Welsh given priority. 

    21.  Minffordd Tunnel Head House 

    Requires a package-specific Construction Traffic Management Plan for the Minffordd Tunnel Head House works. 

    22.  Minffordd Tunnel Head House CEMP  

    Requests a package-specific Construction Environmental Management Plan for the Minffordd Tunnel Head House works. 

    23.  Minffordd Tunnel Head House HMP    

    Requests a package-specific Habitat Management Plan for the Minffordd Tunnel Head House works.

    24.  CTMPs for the Main Work Packages   

    Requires separate Construction Traffic Management Plans for the Wern CSEC, Garth CSEC, Minffordd CSEC and Glaslyn Cables work packages.   

    25.  CEMPs for the Main Work Packages

    Requires separate Construction Environmental Management Plans for the Wern CSEC, Garth CSEC, Minffordd CSEC and Glaslyn Cables work packages.

    26.  Community facilities restoration plan

    Bodawen and Ysgol Eifionydd Playing Fields.

     

    Note: Amendment of Dŵr Cymru Welsh Water conditions in line with the late representations received

     

    Supporting documents:

    • Land Along The A483 Corridor, Porthmadog, item 7. pdf icon PDF 921 KB
    • Plans, item 7. pdf icon PDF 5 MB
    • 2 - Glaslyn Cables Temporary Site Plans, item 7. pdf icon PDF 34 MB
    • 3 - Glaslyn Cables Proposed Permanent Site Plans, item 7. pdf icon PDF 43 MB
    • 4 - Glaslyn Cables Wern CSE Compound Proposed Site Plan, item 7. pdf icon PDF 2 MB
    • 5 - Glaslyn Cables Wern CSE Compound Sections and Elevations, item 7. pdf icon PDF 1 MB
    • 6 - Glaslyn Cables Minffordd CSE Compound Proposed Site Plan, item 7. pdf icon PDF 2 MB
    • 7 - Glaslyn Cables Minffordd CSE Compound Sections and Elevations, item 7. pdf icon PDF 3 MB
    • 8 - Glaslyn Cables Minffordd THH North South Elevations, item 7. pdf icon PDF 108 KB